Access ADM and WebDP with this link: http://alphdb05.eua.solvay.com/ADMPrd/
Picaso materials are not package specific. They match the SAP concept of a Material group.

The material filelds are to be populated as below:
| Field | Mandatory/Optional | Rule | Comment |
|---|---|---|---|
| Material | Mandatory | Picaso materials are not package specific. They match the SAP concept of a Material group. | |
| Nome Code | Mandatory | Same as Material | |
| Manager | Mandatory | Whomever is in charge. Usually the GP or the PM. | |
| Material Type | Mandatory | Material Type | |
| Description | Mandatory | Free text | |
| Quality Test Lag | |||
| Material types | What for |
|---|---|
| Finished Goods | Finished goods |
| Additives | Raw Materials |
| Intermediates | Bulk, polymers |
| Package Materials | Package Materials |
| Resins | Resins |
| sfm | monomers (TFEM, Sulfones, VF2,...) |
| wide spec |
The material shows a global Quality test lag:

What if the QC time is not the same in the two (or more) production plants that this product is manufactured?
The Location dependent Quality test lag let you deal with locations where the Quality test lag differs from the material default.

Effect of the Quality Test Lag on:
In order to avoid duplicating QC times when one is maintained in SAP, you want to use the Schedule Upload Lag Adjustment Table.
Keep in mind that the Picaso → SAP interface always uses these two factors. This is hardcoded in the interface.
A formula is a list of ingredients. It is our SAP Bill of Materials.
Most formulas are created in Picaso by uploading SAP BOM's.
(automatic refresh if BOM modified? TBC)
Picaso formulas are named after the SAP Production version they are selected from. Therefore, a BOM not associated to a Production Version will not load in Picaso.
Formulas numbers are generated automatically in Picaso. These numbers will be used in Production Standards Effectivity..







The schedule upload lag adjustment no effect in Picaso (neither on the grid, no anywhere else). Only affect the interface to SAP for planned orders.
Used when the GRPT / QM Module with Average Inspection Duration are used in SAP.
The Planned order end date = Run End Date + QC Lag + Schedule Upload Lag Adjustment