Once a plant starts using the SAP QM Module, the next step is to leverage on the new capability to determine when each new lot will be available (=released from QC).
This also allows SAP (and especially ATP) to prevent a lot to ship while it is in quality inspection.
In addition, it allows SAP (and especially ATP) to determine if a specific lot can ship at a given date, while still being under quality inspection.
In order to achieve this, the Lab reviews their statistics and establishes the expected completion time of a given product (or family of products), which goes into SAP.
Add the steps involved:
Now, in order to determine the SAP QC Time, SAP Average Inspection Time, SAP Goods Receipt Processing Time, SAP Planned Delivery Time, Picaso QC Lag, and Picaso QC Lag Adjustment, first determine what material flow applies:
|
| Terminology |
|---|
Both Picaso and SAP have to be kept in synchronization when accounting for time the Lab needs to complete quality control. In the real world, the Lab typically starts working on samples during production. The time to process a sample and release a lot is called Lab Turnaround Time. |
Material flows:
| Phase | Scenario A |
|---|---|
Production Run Time: 6 days Lab Turnaround Time = 4 days (in the schematics, Lab Turnaround Time is referred to as 'Lab Time') | |
Before Goods Receipt from Production in the manufacturing plant (why the interface created a 10 days planned order in SAP when the original Picaso run is 6 days? Find the answer here) |
|
| After Goods Receipt from Production in the manufacturing plant |
|
| After QC Release |
|
| Master Data: | Picaso: QC Lag = Lab Turnaround Time (4 days) SAP (at the plant)
|
| Phase | Scenario B |
|---|---|
Production Run Time: 6 days Lab Turnaround time = 4 days (in the schematics, Lab Turnaround Time is referred to as 'Lab Time') Transfer time between manufacturing plant and warehouse = 1 day Lot moved to the warehouse after QC release | |
Before Goods Receipt (why the interface created a 10 days planned order in SAP when the original Picaso run is 6 days? Find the answer here) |
|
After Goods Receipt from Production in the manufacturing plant |
|
After QC Release |
|
After Goods Receipt from Transfer in the warehouse |
|
| Master Data: | Picaso:
SAP (at the plant)
SAP (at the warehouse)
|
| Phase | Scenario C |
|---|---|
Production run time: 6 days Lab Turnaround Time = 4 days Transfer time between manufacturing plant and warehouse = 1 day Lot moved to the warehouse during QC | |
Before Goods Receipt from Production |
|
After Goods Receipt from Production in the manufacturing plant |
|
After Goods Receipt from Transfer in the warehouse |
|
After QC Release | ![]() |
| Master Data: | Picaso:
SAP (at the plant)
SAP (at the warehouse)
|
| Phase | Scenario C w/autoMIGO | |
|---|---|---|
Production run time: 6 days Lab Turnaround Time = 4 days Transfer time between manufacturing plant and warehouse = 1 day (real transfer time, not transfer time in SAP) Lot moved to the warehouse during QC
| ||
Before Goods Receipt from Production |
| |
After Goods Receipt from Production in the manufacturing plant |
| |
After Goods Issue for Transfer from the plant. The Average Ins. Duration is therefore greater than in scenario C. It does not mean that the lab takes more time to turnaround a lot. The Lab takes the exact same time. It means that the lot arrives earlier at the warehouse (in SAP) than with scenario C, while the lab still have to do the same work. |
| |
After QC Release | ![]() | |
| Master Data: | Picaso:
SAP (at the plant)
SAP (at the warehouse)
|
| Phase | Scenario A bis |
|---|---|
Production run time: 6 days Lab time = 4 days | |
Before Goods Receipt from Production in the manufacturing plant |
|
| After Goods Receipt from Production in the manufacturing plant |
|
| After QC Release |
|
| Master Data: | SAP (at the plant)
|
| Phase | Scenario B bis |
|---|---|
Production run time: 6 days Lab time = 4 days Transfer time between manufacturing plant and warehouse = 1 day Lot moved to the warehouse after QC release | |
Before Goods Receipt |
|
After Goods Receipt from Production in the manufacturing plant |
|
After QC Release |
|
After Goods Receipt from Transfer in the warehouse |
|
| Master Data: | SAP (at the plant)
SAP (at the warehouse)
|
| Phase | Scenario C-bis |
|---|---|
Production run time: 6 days Lab time = 4 days Transfer time between manufacturing plant and warehouse = 1 day Lot moved to the warehouse during QC | |
Before Goods Receipt from Production |
|
After Goods Receipt from Production in the manufacturing plant |
|
After Goods Receipt from Transfer in the warehouse |
|
After QC Release | ![]() |
| Master Data: | SAP (at the plant)
SAP (at the warehouse)
|
Recap:
| Scenario | Master Data Picaso | Master Data SAP |
|---|---|---|
| A | QC Lag = Lab Time Schedule Upload Lag Adjustment = 0 (or none) | @the plant Av.Ins.Duration = Lab Time Planned Delivery Time = 0 Goods Receipt Processing Time = 0 |
| B | QC Lag = Lab Time + transfer to the warehouse, including handling Schedule Upload Lag Adjustment = - transfer time | @the plant Av.Ins.Duration = Lab Time Planned Delivery Time = 0 Goods Receipt Processing Time = 0 @the warehouse Planned Delivery Time = Transfer time Av.Ins.Duration = 0 Goods Receipt Processing Time = 0 |
| C | QC Lag = max of (Lab Time // transfer time) Schedule Upload Lag Adjustment = - QC Lag | @the plant Av.Ins.Duration = 0 Planned Delivery Time = 0 Goods Receipt Processing Time = 0 @the warehouse Planned Delivery Time = Transfer time GRPT = Lab Time - Transfer time Av.Ins.Duration = Lab Time - Transfer time |
| C with auto-MIGO | QC Lag = max of (Lab Time // transfer time) Schedule Upload Lag Adjustment = - QC Lag | @the plant Av.Ins.Duration = 0 Planned Delivery Time = 0 Goods Receipt Processing Time = 0 @the warehouse Planned Delivery Time = Transfer time GRPT = Lab Time - Transfer time Av.Ins.Duration = Lab Time |
| A-bis | N/A | @the plant Av.Ins.Duration = Lab Time Goods Receipt Processing Time = Lab Time Planned Delivery Time = 0 |
| B-bis | N/A | @the plant Av.Ins.Duration = Lab Time Goods Receipt Processing Time = Lab Time Planned Delivery Time = 0 @the warehouse Planned Delivery Time = Transfer time Av.Ins.Duration = 0 Goods Receipt Processing Time = 0 |
| C-bis | N/A | @the plant Av.Ins.Duration = 0 Planned Delivery Time = 0 Goods Receipt Processing Time = 0 @the warehouse Planned Delivery Time = Transfer time GRPT = Lab Time - Transfer time Av.Ins.Duration = Lab Time - Transfer time |
Conclusion: the SAP QC Time, SAP Average Inspection Time, Goods Receipt Processing Time, Planned Delivery time, Picaso QC Lag, and Picaso QC Lag Adjustment apply during specific events of the life of a lot:
Applies before the lot is received in inventory | Applies once the lot has been received in inventory and the QM Lot has been generated |
|---|---|
Picaso QC Lag Picaso Schedule Upload Lag Adjustment Goods Receipt Processing Time Planned Delivery Time | Average Inspection Duration |
Use this file to help calculate the value of each parameter.
Tips for mass updates in SAP and Picaso:
|
Related articles appear here based on the labels you select. Click to edit the macro and add or change labels.
|