Once a plant starts using the SAP QM Module, the next step is to leverage on the new capability to determine when each new lot will be available (=released from QC).

This also allows SAP (and especially ATP) to prevent a lot to ship while it is in quality inspection.

In addition, it allows SAP (and especially ATP) to determine if a specific lot can ship at a given date, while still being under quality inspection.

In order to achieve this, the Lab reviews their statistics and establishes the expected completion time of a given product (or family of products), which goes into SAP.

Step-by-step guide

Add the steps involved:

Now, in order to determine the SAP QC Time, SAP Average Inspection Time, SAP Goods Receipt Processing Time, SAP Planned Delivery Time, Picaso QC Lag, and Picaso QC Lag Adjustment, first determine what material flow applies:

Terminology

Both Picaso and SAP have to be kept in synchronization when accounting for time the Lab needs to complete quality control.

In the real world, the Lab typically starts working on samples during production. The time to process a sample and release a lot is called Lab Turnaround Time.


Material flows:

PhaseScenario A

Production Run Time: 6 days

Lab Turnaround Time = 4 days

(in the schematics, Lab Turnaround Time is referred to as 'Lab Time')

Before Goods Receipt from Production in the manufacturing plant

(why the interface created a 10 days planned order in SAP when the original Picaso run is 6 days? Find the answer here)

After Goods Receipt from Production in the manufacturing plant

After QC Release

Master Data:

Picaso: QC Lag = Lab Turnaround Time (4 days)

SAP (at the plant)

  • Av.Ins.Duration (@plant) = Lab Turnaround Time (ex. : 4 days)
  • Make sure these are blank (or 0):
    • Planned Delivery Time (@plant)
    • Goods Receipt Processing Time (@plant)
PhaseScenario B

Production Run Time: 6 days

Lab Turnaround time = 4 days

(in the schematics, Lab Turnaround Time is referred to as 'Lab Time')

Transfer time between manufacturing plant and warehouse = 1 day

Lot moved to the warehouse after QC release

Before Goods Receipt

(why the interface created a 10 days planned order in SAP when the original Picaso run is 6 days? Find the answer here)

After Goods Receipt from Production in the manufacturing plant

After QC Release

After Goods Receipt from Transfer in the warehouse

Master Data:

Picaso:

  • QC Lag = Lab Turnaround Time + transfer to the warehouse, including handling. (ex. : 5 days)
  • Schedule Upload Lag Adjustment = - transfer & handling time (ex. : -1 days)

SAP (at the plant)

  • Av.Ins.Duration (@plant) = Lab Turnaround Time (ex. : 4 days)
  • Make sure these are blank (or 0):
    • Planned Delivery Time (@plant)
    • Goods Receipt Processing Time (@plant)

SAP (at the warehouse)

  • Planned Delivery Time (@warehouse)= Transfer time (ex. : 1 days)
  • Make sure these are blank (or 0):
    • Av.Ins.Duration (@warehouse)
    • Goods Receipt Processing Time (@warehouse)
PhaseScenario C

Production run time: 6 days

Lab Turnaround Time = 4 days

Transfer time between manufacturing plant and warehouse = 1 day

Lot moved to the warehouse during QC

Before Goods Receipt from Production

After Goods Receipt from Production in the manufacturing plant

After Goods Receipt from Transfer in the warehouse

After QC Release



Master Data:

Picaso:

  • QC Lag = expected max of Lab Time / transfer to the warehouse, including handling. (ex. : 4 days)
  • Schedule Upload Lag Adjustment = - QC Lag (ex. : -4 days)

SAP (at the plant)

  • Make sure these are blank (or 0):
    • Av.Ins.Duration (@plant)
    • Planned Delivery Time (@plant)
    • Goods Receipt Processing Time (@plant)

SAP (at the warehouse)

  • Planned Delivery Time (@warehouse)= Transfer time (ex. : 1 days)
  • Goods Receipt Processing Time (@warehouse)= Lab Time - Transfer time (ex. : 3 days)
  • Av.Ins.Duration (@warehouse)= Lab Time - Transfer time (ex. : 3 days) = GRPT
PhaseScenario C w/autoMIGO

Production run time: 6 days

Lab Turnaround Time = 4 days

Transfer time between manufacturing plant and warehouse = 1 day (real transfer time, not transfer time in SAP)

Lot moved to the warehouse during QC

autoMIGO for stock transfer → lot received at the warehouse (in SAP) immediately after GI from the plant.

Therefore, even though the actual transfer time is 1 day, the transfer time in SAP is 0 days. We will call this the SAP Transfer Time

Before Goods Receipt from Production

After Goods Receipt from Production in the manufacturing plant

After Goods Issue for Transfer from the plant.

The Average Ins. Duration is therefore greater than in scenario C.

It does not mean that the lab takes more time to turnaround a lot.

The Lab takes the exact same time.

It means that the lot arrives earlier at the warehouse (in SAP) than with scenario C,

while the lab still have to do the same work.


After QC Release



Master Data:

Picaso:

  • QC Lag = expected max of Lab Turnaround Time / transfer to the warehouse, including handling. (ex. : 4 days)
  • Schedule Upload Lag Adjustment = - QC Lag (ex. : -4 days)

SAP (at the plant)

  • Make sure these are blank (or 0):
    • Av.Ins.Duration (@plant)
    • Planned Delivery Time (@plant)
    • Goods Receipt Processing Time (@plant)

SAP (at the warehouse)

  • Planned Delivery Time (@warehouse)= Transfer time (ex. : 1 days)
  • Goods Receipt Processing Time (@warehouse)= Lab Time - Transfer time (ex. : 3 days)
  • Av.Ins.Duration (@warehouse)= Lab Time - autoMIGO Transfer time (ex. : 4 days), hence <>GRPT <= only change vs a Scenario C w/o autoMIGO
PhaseScenario A bis

Production run time: 6 days

Lab time = 4 days

Before Goods Receipt from Production in the manufacturing plant


After Goods Receipt from Production in the manufacturing plant

After QC Release

Master Data:

SAP (at the plant)

  • Av.Ins.Duration (@plant) = Lab Time (ex. : 4 days)
  • Goods Receipt Processing Time (@plant) = Lab Time (ex. : 4 days)
  • Make sure these are blank (or 0):
    • Planned Delivery Time (@plant)
PhaseScenario B bis

Production run time: 6 days

Lab time = 4 days

Transfer time between manufacturing plant and warehouse = 1 day

Lot moved to the warehouse after QC release

Before Goods Receipt


After Goods Receipt from Production in the manufacturing plant

After QC Release

After Goods Receipt from Transfer in the warehouse

Master Data:

SAP (at the plant)

  • Av.Ins.Duration (@plant) = Lab Time (ex. : 4 days)
  • Goods Receipt Processing Time (@plant) = Lab Time (ex. : 4 days)
  • Make sure these are blank (or 0):
    • Planned Delivery Time (@plant)

SAP (at the warehouse)

  • Planned Delivery Time (@warehouse)= Transfer time (ex. : 1 days)
  • Make sure these are blank (or 0):
    • Av.Ins.Duration (@warehouse)
    • Goods Receipt Processing Time (@warehouse)
PhaseScenario C-bis

Production run time: 6 days

Lab time = 4 days

Transfer time between manufacturing plant and warehouse = 1 day

Lot moved to the warehouse during QC

Before Goods Receipt from Production

After Goods Receipt from Production in the manufacturing plant

After Goods Receipt from Transfer in the warehouse

After QC Release



Master Data:

SAP (at the plant)

  • Make sure these are blank (or 0):
    • Av.Ins.Duration (@plant)
    • Planned Delivery Time (@plant)
    • Goods Receipt Processing Time (@plant)

SAP (at the warehouse)

  • Planned Delivery Time (@warehouse)= Transfer time (ex. : 1 days)
  • Goods Receipt Processing Time (@warehouse)= Lab Time - Transfer time (ex. : 4 days)
  • Av.Ins.Duration (@warehouse)= Lab Time - Transfer time (ex. : 3 days) = GRPT


Recap:

ScenarioMaster Data PicasoMaster Data SAP
A

QC Lag = Lab Time

Schedule Upload Lag Adjustment = 0 (or none)

@the plant

Av.Ins.Duration = Lab Time

Planned Delivery Time = 0

Goods Receipt Processing Time = 0

B

QC Lag = Lab Time + transfer to the warehouse, including handling

Schedule Upload Lag Adjustment = - transfer time

@the plant

Av.Ins.Duration = Lab Time

Planned Delivery Time = 0

Goods Receipt Processing Time = 0

@the warehouse

Planned Delivery Time = Transfer time

Av.Ins.Duration = 0

Goods Receipt Processing Time = 0

C

QC Lag = max of (Lab Time // transfer time)

Schedule Upload Lag Adjustment = - QC Lag


@the plant

Av.Ins.Duration = 0

Planned Delivery Time = 0

Goods Receipt Processing Time = 0

@the warehouse

Planned Delivery Time = Transfer time

GRPT = Lab Time - Transfer time

Av.Ins.Duration = Lab Time - Transfer time

C with auto-MIGO

QC Lag = max of (Lab Time // transfer time)

Schedule Upload Lag Adjustment = - QC Lag

@the plant

Av.Ins.Duration = 0

Planned Delivery Time = 0

Goods Receipt Processing Time = 0

@the warehouse

Planned Delivery Time = Transfer time

GRPT = Lab Time - Transfer time

Av.Ins.Duration = Lab Time

A-bisN/A

@the plant

Av.Ins.Duration = Lab Time

Goods Receipt Processing Time = Lab Time

Planned Delivery Time = 0

B-bisN/A

@the plant

Av.Ins.Duration = Lab Time

Goods Receipt Processing Time = Lab Time

Planned Delivery Time = 0

@the warehouse

Planned Delivery Time = Transfer time

Av.Ins.Duration = 0

Goods Receipt Processing Time = 0

C-bisN/A

@the plant

Av.Ins.Duration = 0

Planned Delivery Time = 0

Goods Receipt Processing Time = 0

@the warehouse

Planned Delivery Time = Transfer time

GRPT = Lab Time - Transfer time

Av.Ins.Duration = Lab Time - Transfer time


Conclusion: the SAP QC Time, SAP Average Inspection Time, Goods Receipt Processing Time, Planned Delivery time, Picaso QC Lag, and Picaso QC Lag Adjustment apply during specific events of the life of a lot:

Applies before the lot is received in inventory

Applies once the lot has been received in inventory and the QM Lot has been generated

Picaso QC Lag

Picaso Schedule Upload Lag Adjustment

Goods Receipt Processing Time

Planned Delivery Time

Average Inspection Duration


 Use this  file to help calculate the value of each parameter.



Tips for mass updates in SAP and Picaso:

  • QM Average Inspection Time: raise a ticket with this category: Catalog/Industrial/Quality/Quality Control/ Request for Data mass Creation/Upd
  • Maintain the QC Lag and the Schedule Upload Lag Adjustment in their respective tables in ADM.


Related articles

Related articles appear here based on the labels you select. Click to edit the macro and add or change labels.

Related issues