Once a plant starts using the SAP QM Module, the next step is to leverage on the new capability to determine when each new lot will be available (=released from QC).
This also allows SAP (and especially ATP) to prevent a lot to ship while it is in QI.
It furthermore allows SAP (and especially ATP) to determine if a specific lot can ship at a given date.
In order to achieve this, the Lab reviews their statistics and establishes the expected QC completion duration, which goes into SAP.
Now, in order to determine the QC Time, Average Inspection Time, and QC Lag Adjustment, first determine what material flow applies:
In addition, keep in mind that these various parameters will only apply during specific events of the life of a lot. Namely:
| Applies before the lot is produced | Applies after goods receipt in inventory |
|---|---|
Picaso QC Lag (and Lag Adjustment) GRPT | Average Inspection Duration |

Add the steps involved:
Now, in order to determine the QC Time, Average Inspection Time, and QC Lag Adjustment, first determine what material flow applies:
| Average Inspection Duration | GRPT | Picaso QC Lag | Picaso Schedule Upload Lag Adjustment | any additional step? | |
|---|---|---|---|---|---|
| Scenario A | as per Lab determination | N/A | Same as Av.Ins.Duration | N/A | nope, you're good to go. |
| Scenario C | see below | yes, see below |