Once a plant starts using the SAP QM Module, the next step is to leverage on the new capability to determine when each new lot will be available (=released from QC).

This also allows SAP (and especially ATP) to prevent a lot to ship while it is in QI.

It furthermore allows SAP (and especially ATP) to determine if a specific lot can ship at a given date.

In order to achieve this, the Lab reviews their statistics and establishes the expected QC completion duration, which goes into SAP.


Now, in order to determine the QC Time, Average Inspection Time, and QC Lag Adjustment, first determine what material flow applies:


In addition, keep in mind that these various parameters will only apply during specific events of the life of a lot. Namely:

Applies before the lot is producedApplies after goods receipt in inventory

Picaso QC Lag (and Lag Adjustment)

GRPT

Average Inspection Duration

Here is what is going on with Picaso and SAP:

Step-by-step guide

Add the steps involved:

  1. Now, in order to determine the QC Time, Average Inspection Time, and QC Lag Adjustment, first determine what material flow applies:


    Average Inspection DurationGRPTPicaso QC LagPicaso Schedule Upload Lag Adjustmentany additional step?
    Scenario Aas per Lab determinationN/ASame as Av.Ins.DurationN/Anope, you're good to go.
    Scenario Csee below


    yes, see below


You may also want to use visual panels to communicate related information, tips or things users need to be aware of.