Once a plant starts using the SAP QM Module, the next step is to leverage on the new capability to determine when each new lot will be available (=released from QC).
This also allows SAP (and especially ATP) to prevent a lot to ship while it is in quality inspection.
In addition, it allows SAP (and especially ATP) to determine if a specific lot can ship at a given date, while still being under quality inspection.
In order to achieve this, the Lab reviews their statistics and establishes the expected completion time of a given product (or family of products), which goes into SAP.
Both Picaso and SAP have to be kept in synchronization when accounting for time the Lab needs to complete quality control. We will call this time: Lab Time. (Lab Time: from receiving sample, to registering results of tests and analysis).
Add the steps involved:
Now, in order to determine the SAP QC Time, SAP Average Inspection Time, Picaso QC Lag, and Picaso QC Lag Adjustment, first determine what material flow applies:
Tips: The SAP QC Time, SAP Average Inspection Time, Picaso QC Lag, and Picaso QC Lag Adjustment apply during specific events of the life of a lot:
Applies before the lot is received in inventory | Applies once the lot has been received in inventory and the QM Lot has been generated |
|---|---|
Picaso QC Lag Picaso Schedule Upload Lag Adjustment Goods Receipt Processing Time Planned Delivery Time | Average Inspection Duration |
Material flows:
| Phase | Scenario A |
|---|---|
Production run time: 6 days Lab time = 4 days | |
| Before Goods Receipt from Production in the manufacturing plant |
|
| After Goods Receipt from Production in the manufacturing plant |
|
| After Release |
|
| Master Data: | Picaso: QC Lag = Lab Time (4 days) SAP: Av.Ins.Duration = Lab Time (ex. : 4 days) |
| Phase | Scenario B |
|---|---|
Production run time: 6 days Lab time = 4 days Transfer time between manufacturing plant and warehouse = 1 day Lot moved to the warehouse after QC release | |
Before Goods Receipt (aka Planning phase) | |
After Goods Receipt from Production in the manufacturing plant (aka Goods Receipt from Production phase) | |
After Release | |
After Goods Receipt from Transfer in the warehouse (aka Goods Receipt from Transfer) | |
| Master Data: | Picaso:
SAP (at the plant)
SAP (at the warehouse)
|
| Phase | Scenario C |
|---|---|
Production run time: 6 days Lab time = 4 days Transfer time between manufacturing plant and warehouse = 1 day Lot moved to the warehouse during QC | |
Before Goods Receipt from Production |
|
After Goods Receipt from Production in the manufacturing plant |
|
After Goods Receipt from Transfer in the warehouse |
|
After QC Release | ![]() |
| Master Data: | Picaso:
SAP (at the warehouse)
|
Recap:
| Scenario | Master Data Picaso | Master Data SAP |
|---|---|---|
| A | QC Lag = Lab Time | @the plant Av.Ins.Duration = Lab Time |
| B | QC Lag = Lab Time + transfer to the warehouse, including handling Schedule Upload Lag Adjustment = - QC Lag + transfer time | @the plant GRPT = Lab Time Av.Ins.Duration = Lab Time @the warehouse Planned Delivery Time = Transfer time |
| C | QC Lag = max of (Lab Time // transfer time) Schedule Upload Lag Adjustment = - QC Lag | @the plant N/A @the warehouse Planned Delivery Time = Transfer time GRPT = Lab Time - Transfer time Av.Ins.Duration = GRPT |
| You may also want to use visual panels to communicate related information, tips or things users need to be aware of. |
Related articles appear here based on the labels you select. Click to edit the macro and add or change labels.
|