Upon reception of the monthly notification, you want to:
Add the steps involved:
open the MYYYYMM sheet. YYYYMM is the current month. E.g. if today is April 03 2023, you want to work on M202304.
Use a filter view to help. Many have been already created. Feel free to use them or create yours.
|
Here, in this example:
February 2024 production schedule is highlighted.
The schedule of February has been downloaded from Picaso into that spreadsheet on February the 1st.
|
Review/validate these numbers, and make necessary adjustments. When should you adjust these numbers?
if you made schedule changes on the first days of the month, that you think should have been accounted for in the monthly snapshot
Once you are done, open the "Schedule Validation Punch Card" sheet.
|
let me know that you are done and that the numbers are validated:
|
if you think there is something wrong with the extraction and want to let me know, check the other box:
|
You will be reviewing last month's performances. E.g. if today is April 03 2023, you will be reviewing the performances of March 2023
Open the your sheet (=your plant). It shows this:
|
Open the "Monthly" section
Summary per product line on top
Details per product on the bottom.
|
where Adherence is green or blue: no comment necessary. Adherence is within range of, or higher than, the target. Just enter "OK" to confirm that you have reviewed the performances.
see example below
|
| You may also want to use visual panels to communicate related information, tips or things users need to be aware of. |
Related articles appear here based on the labels you select. Click to edit the macro and add or change labels.
|