This quick reference guide is a cheat sheet or Planning Key Users.

Running Monthly Adherence Report boils down to xxx things:

Step-by-step guide

Add the steps involved:

  1. On the first day of the month
    1. Take a snapshot of the production schedule:
      1. Find the Production Schedule in ADM
      2. make sure no filter is active:  if this function is greyed out, you are good. If it is not greyed out, press the button to clear your filter.
      3. export it  as a spreadsheet

    2. Upload it in the Adherence report database
      1. find the SpP PA Sch Data Extract & Sparsing file
      2. open the PicasoImport sheet
      3. clear the data (important !)
      4. copy/paste from your spreadsheet (see previous step)
      5. make sure the other views (MonthView, RemainingMonthView, WeekView) display no #N/A or #ERROR
      6. soon to come: run function XYZ to get the background process started
    3. reset the validation punch card
      1. find the SpP PA Sch Data Keep file
      2. open the Schedule Validation Punch Card sheet
      3. clear the checkboxes

    4. let the site planners know about the snapshot → they have to validate it
      1. use this distribution list: SCo-$SpP_Monthly_ Adherence
      2. and this template:

        Adherence - Scheduled volumes for Month <MM YYYY>

        Dear all,

        The production volumes you have scheduled in Picaso for <MM YYYY>  have been downloaded in the SpP PA Sch Data Keep file.

        You can already go ahead and validate the schedule snapshot.

        Find step by step instructions in the Planning Wiki.

        Just do step 1 (validate schedule snapshot)

        As for step 2 (review and comment), the file is not ready yet.

        You will receive another email by <Day> when we will be ready to review the adherence of <M-1>.

        Thanks!

  2. On the 3rd working day of the month
    1. verify that actuals are in. Just check the sanity of the actual numbers for your perimeter.
      1. between the first day, and the 3rd day of the month, the actual numbers in the report are wrong. By design. Because Al Quaeda.
      2. starting the 3rd day of the month, the report is refreshed with the real actual numbers.
      3. there are two more refreshes (4th & 5th days of the month) to account for plants being late to report their numbers, vacations, etc. 
    2. email the other site planners
      1. use this distribution list: SCo-$SpP_Monthly_ Adherence
      2. and this template:

        Adherence - Performances of month <MM YYYY>

        Dear all,

        The Production Adherence of <MM YYYY> is now ready for review in the SpP Adh - Heat Map file.

        Please have performance reviewed with Manufacturing before the end of next week ( <day> ).

        Find step by step instructions in the Planning Wiki.

        Thanks.


You may also want to use visual panels to communicate related information, tips or things users need to be aware of.

Related articles

Related articles appear here based on the labels you select. Click to edit the macro and add or change labels.

Related issues