Main steps:

  1. Assess
  2. Prepare
  3. Launch
  4. Accelerate
  5. Sustain and improve



StepsIdeal timeline before launch TopicJira epicsNotes

Assess

6 months

Need for change set 

  • Vision
  • Economic view
  • SAFe Awareness

See article of SAFe (something Tipping point..) which describes reasons for this change

Assess

6 monthsTrain leadership (leading safe)


Assess6 to 4 months

Define and validate the main milestones

Define transformation team



Transformation team seems to be set - to discuss with Florence if the meeting Wednesdays includes the full team members
Assess6 to 4 monthsCommunicate vision/ Engage teams
Plan created by Alix, cannot find vision nor economic view, to be discussed
Prepare3 months

Identify value streams and ARTs (workshop):

  • Systems thinking
  • People needed (#s and roles)
  • ...

Identify and communicate ideal attributes:

  • 50/120 people?
  • Stable teams
  • Independent from external ARTs/ groups

Experience: The bigger the ART is , the most likely is a full value stream but the more complex it becomes to organise.  

 Ideally, also on experience, we should start with one ART and focus on that launch.


 

Prepare3 months

Pick the first value stream.

Define value stream mission, who are the people

Core team for the ART launch defined

Agree on the KPIs.


This is the right time time to define the training for the teams .

Prepare2 months

Skill training

Business owners identified

RTE, Architect, PM appointed

Create teams (with POs and 

Set launch date

Set cadence


(From Alix assessment):Improve and harmonize backlogs good practices: DoR, DoD, acceptance criterias

Prepare2 months

Program all ceremonies

Train on the planning event (role based)

Safe awareness sessions


 Safe 

This is the right time time to define any additional  training for the teams (POs, PMs, RTE etc).



Prepare 1 month

Backlog is prepared

PI planning event is prepared





Launch day!