| Status | |
| Owner | Anjali Upadhyay |
| Stakeholders | The persons consulted or otherwise involved in making this decision. Type @ to mention people by name |
Currently, there are multiple applications to manage Sysenqo's portfolio of projects. In principle, all these applications ( COLMAR, WEGO, BIARRITZ, WAVE) provide the ability to manage the lifecycle of a project from idea stage to its closure. However, these systems do not automatically integrate with the financial ERP systems to get the complete monitoring and tracking of projects. Some of these applications (such as COLMAR) are at the end of their life and require improvements and upgrades. Existence of multiple applications pose following challenges in overall Portfolio and Project Management
Based on the detailed analysis of evaluation criteria for efficient Portfolio and Project management, Option A - SAP S/4Hana EPPM (Enterprise Portfolio and Project Management) is recommended
Syensqo’s project portfolio is largely comprised of the Capex related projects. Capex management is detailed in the CAPEX 01 procedure based on the project classification (Current, Medium, Major and Major > 50 M€). The Group Investment Committee provides the ELT with recommendations for approval of major projects (> 7M€) but some approvals and challenges are nevertheless mandatory for projects < 7M€. Capex01 procedure defines the process and guidelines for prioritizing and ranking the Capital projects based on the investment reasons that are aligned with the Group and GBU strategic objectives and envelops.
Small projects can be managed (for realization) by GBU/Sites without the help of the GEC (Group Engineering and Construction) but it is not systematic.
OPEX are not managed by projects and OPEX costs are booked to specific cost centers
GBUs use different application to manage their own portfolio and project lifecycle. There is no strict mandate to manage all projects in single application/system. Below are the portfolio and project management applications in Syensqo.
| Application |
| Features/ Functionalities | Challenges |
|---|---|---|---|
| COLMAR | Group and GBUs (inconsistently) |
|
|
| Accolade (WEGO) | R&I |
|
|
| Accolade (BIARRITZ) | IT |
|
|
| WAVE | Manufacturing Excellence |
|
|
It is evident from above analysis that there is a lack of standardized and integrated Portfolio and Project management tool in Syensqo. This KDD intends to evaluate an integrated and consistent tool for the management of the portfolio of projects.
Syensqo's objective is to apply a core and common procedure across all GBUs for managing portfolio of projects. It is assumed that all financial and non financial information resides in SAP S/4Hana for seamless integration and informed decision making process for prioritization, ranking and budget allocation of projects across all GBUs.
No constraints identified in this phase
Implementation of SAP S/4Hana EPPM as following impacts
Existing business rules and procedure such as Phase/gates and CAPEX01 procedure and guidelines can be adopted in implementation of SAP EPPM. Further details will be analyzed in detailed design phase.
Option A: SAP S/4Hana Enterprise Portfolio and Project Management (EPPM)
SAP S/4Hana Enterprise Portfolio and Project Management (EPPM) is an integrated module that helps organizations to manage their projects and portfolio of projects effectively. It provides the ability to manage enterprise wide portfolio across each lifecycle phase to align project investments and activities with strategic objectives of the organization. EPPM allows management of different kinds of projects portfolios.
EPPM consists of :

Continue using the existing multiple applications for managing portfolio of projects. Since not all existing applications are integrated with SAP, an integrated reporting solution should be implemented to bring all the projects together from various sources to provide the overall reporting, tracking and decision making of all projects.
This approach may require updating CAPEX01 procedure to be aligned with the GBU specific project management philosophy such as phases/gates, metrics and deliverables.
Below table outlines the comparison of the proposed options for effective portfolio and project management.
Option A - S/4Hana EPPM | Option B - Multiple Applications with integrated reporting | |
|---|---|---|
|
| |
|
|
Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.