Currently, there are multiple applications to manage Sysenqo's portfolio of projects. In principle, all these applications ( COLMAR, WEGO, BIARRITZ, WAVE) provide the ability to manage the lifecycle of a project from idea/proposal stage to its closure. However, these systems do not automatically integrate with the financial systems to get the complete monitoring and tracking of all projects at Group and GBU level. Lack of single common and integrated portfolio & project management solution poses following challenges for Syensqo.
Based on the analysis and evaluation of pro's and con's of the proposed options Option A - SAP S/4Hana EPPM (Enterprise Portfolio and Project Management) is recommended for effective portfolio and project management in Syensqo.
Syensqo’s project portfolio is largely comprised of the Capex related projects. Capex management is detailed in the CAPEX01 procedure based on the project classification (i.e. Current, Medium, Major and Major > 50 M€). Capex01 procedure defines the process and guidelines for prioritizing and ranking the Capital projects based on the investment reasons that are aligned with the Group and GBU strategic objectives and envelops.
The Group Investment Committee provides the ELT with recommendations for approval of major projects (> 7M€) . However, approvals and challenges are not mandatory for current and Medium projects, therefore current and medium projects are managed (for realization) by GBU/Sites without the help of the GEC (Group Engineering and Construction) and is not systematic. There are multiple local/site specific project management tools for detailed planning of schedule, deliverables, milestones and resources.
WBS elements in SAP are used for procurement of materials and services and posting other financial transactions.
Syensqo have below portfolio and project management applications.
| Application | Used by | Features/ Functionalities | Challenges |
|---|---|---|---|
| COLMAR | Group and GBUs (inconsistently) |
|
|
| Accolade (WEGO) | R&I |
|
|
| Accolade (BIARRITZ) | IT |
|
|
| WAVE | Manufacturing Excellence |
|
|
It is evident from above analysis that there is a lack of standardized and integrated Portfolio and Project management in Syensqo. This KDD intends to evaluate potential options to enable integrated portfolio and project management solutions which provides
No constraints identified in this phase. Further assessments will be done in detailed design phase.
Implementation of SAP S/4Hana EPPM as following impacts
Existing business rules and procedure such as Phase/gates and CAPEX01 procedure and guidelines can be adopted in implementation of SAP S/4Hana EPPM. Further details will be analyzed during detailed design phase.
Option A: SAP S/4Hana Enterprise Portfolio and Project Management (EPPM)
SAP S/4Hana Enterprise Portfolio and Project Management (EPPM) is an integrated portfolio and project management solution that helps organizations to manage their projects and portfolio of projects effectively. It provides the ability to manage enterprise wide portfolio across each lifecycle phase to align project investments and activities with strategic objectives of the organization. EPPM allows management of different kinds of projects portfolios.
EPPM consists of :
Below picture shows the integrated portfolio and project management lifecycle.

Option B: Continue as-is (multiple applications) but with integrated reporting solution
Continue using the existing multiple applications for managing portfolio of projects. Since, not all existing applications are integrated with SAP, an integrated reporting solution should be implemented to bring all the projects together from various sources to provide the overall portfolio reporting, tracking and decision making of all projects.
This approach may require updating CAPEX01 procedure to be aligned with the GBU specific project management framework such as phases/gates, metrics ,deliverables and execution.
Option A - S/4Hana EPPM | Option B - Multiple Applications with integrated reporting | |
|---|---|---|
|
| |
|
|
Table below outlines the comparison of the proposed options for effective portfolio and project management. Despite higher change management efforts to get business buy-in, there are long term benefits of Option A-S/4 Hana EPPM to provide integrated portfolio and project management.
| Evaluation criteria | Option A - S/4Hana EPPM | Option B - Multiple Applications with integrated reporting |
|---|---|---|
Standardized and consistent methodology and Framework | ||
Source of truth | ||
Integrated Portfolio management with Project management | ||
Audit Trail | ||
Automation and Efficiency | ||
Cost of implementation & Maintenance | ||
Change Management |
Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.