Syensqo has close to 700 non-standard/custom units of measure created in the system.
Based on the evaluation of the solution options, it is recommended to Use SAP / ISO Standard UoMs and conversions. This follows the Simplification/Standardisation approach of the project and ensures consistency and ease of integration across the landscape.
Any legacy data using non-standard UoMs will be mapped to standard UoMs during data migration.
Syensqo has close to 700 non-standard/custom units of measure created in the system. These units are historically created to cater to UoM's published by suppliers in various catalogs and also as a workaround to support certain business processes. Below are some of the issues faced currently
Below table provides the statistics of non-standard UoM's in the system along with the usage of the same.
| System | Non-Standard UoM's | POs in past 5 years | PO's with non-Standard UoM | % | UoM's used in affected POs | Materials changed in 10 Years | Materials with Non-Standard UoM | % | UoM's used in Material Masters |
| QF2 | 404 | 4,642,346 | 184,587 | 4% | 66 | 613,651 | 27,648* | 5% | 32 |
| WQ2 | 357 | 2,877,450 | 82,007 | 3% | 73 | 567,413 | 5,995 | 1% | 51 |
As a part of the above analysis, though there are ~700 non-standard UoM's that are existing in the system, there are only ~200 of them are currently active and being used in material master and Purchase Orders.
N/A
Data Migration
Downstream systems
Communication
All the master data and Business processes use only Standard SAP / ISO Units of Measure
Following are the options considered.
Option 1: Use SAP / ISO Standard UoMs and conversions
As a part of this option, all the master data and business processes use only the standard SAP/ISO unit of measures available in the system. Non-standard UoM's are not permitted to be created / used. Mapping activity will be carried out when the master data / transactional data is migrated from the legacy systems to the new S/4 HANA system.
Advantages:
As a part of this option, the existing As-Is active non-standard UoM's are migrated to the new S/4 Hana system.
Based on the evaluation of the solution options, Option 1: Use SAP / ISO Standard UoM's and conversions is recommended. This follows the Simplification/Standardisation approach of the project and minimises any maintenance burden going forward.
| Criteria | Option 1: Use SAP / ISO Standard UoM's and conversions | Option 2: Allow the use of non-standard UoM's |
|---|---|---|
| Alignment with project charter - Standardization and Simplification |
|
|
| Integration |
| |
| Data Migration |
| |
| Reporting |
|
|
Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.