| Status | |
| Owner | Antonio Zappone |
| Stakeholders | The business stakeholders involved in making, reviewing, and endorsing this decision. Type @ to mention people by name |
Decision is required as the when to deploy the new S4\HANA In-House-Bank.
This is the lowest risk option in an area that is general ly cosnidered higher risk. Payments and receipts is a critical processes. There are additional layer's of complexity with running an in-house-bank along with the higher compexity custom solutions to support the internal factoring process.
Interim interfaces are required, which add compleity, however these interim interfaces are requird in most of the deployment options. The interim interfaces will be developed based on the existing interfaces from PF1\WP1 to PI1, hence they are not new design, although the will have to be adapted for the S4HANA.
Deferring the the deployment requires project resources for a longer period of time, which equates to additional cost. Required resources will be limited to IHB consultants and technical developers. Whether this is an "additional cost, or whether resources can commence later and finish later needs to be determine in the overall project planning.
In-House Bank
The existing IHB within ECC resides in PI1, within the legal entities SSA and SFA. SSA and SFA entities also reside in PF1 for all non IHB processes. Interfaces are current in place to link PF1 and WP1 to the IHB in PI1.
All entities are mandated to participate in the IHB process, except where it's not legally possible. For example, China, x ,x ,x , is not part of the IHB due to legal restrictions.
Internal Factoring
A high level of complexity exists with IHB largely due to the internal factoring process. Internal factoring brings benefits in the way of;
Internal factoring is not a common process and not supported by standard SAP, hence the current solution requires nemerous complex custom developements. To "to-be" design will aim to streamline and simplify, hwever it is epected that some level of custom developments will still be required.
Risk
Cash movements related to payments and receipts is a higher risk area of any ERP implementation. The internal factoring complexity increases the risk.
Risk is a major factor in the recommendation and decision of this KDD.
IHB and internal factoring will continue in S4HANA.
Entities not operating within the IHB will go-live with Bank Communication Managament (BCM) in line with Overall project release\s.
Nil
Depending on the approach, interfaces from S4HANA to PI1 require consideration. If they are required, the existing interfaces from PF1 \ WP1 will need to be replicated for S4HANA.
The new Consolidations tool will go-live in the last release. This requires considerations for the Consolidation of the entities and processes within PI1.
Participation in the IHB will continue to be mandatory unless not legally supported.
Early deployment (prior to the main S4HANA releases) of IHB was considered, however due to the impact of extending the overall ERP project timeline, and earlier transfer of master data, this option was not review in this KDD.
Lowest risk option, for IHB is a high risk \ high complexity process by allowing for a fall back \ contigency for the IHB payments and receipts
Allows time to integrated process to stabalise
Allows the poption of production simulations
Interfaces need to be built between the S4HANA and PI1, although these will largely be relications of existing interfaces.
This option entails deploying the IHB in line with the groups in the release plan. One IHB in PI1 for entites still on ECC, and a second IHB for GBUs\entities that have S4HANA for transitioned to S4HANA.
The main drawbacks with this option;
This option entails IHB being deployed for all entities in the first group of the release plan.
The main drawback with this option;
This option entails IHB being deployed for all entities in the second group of the release plan.
This was seen at the best alternative, However the recommendation Option A is preferred due to additioanal de-risking.
Outline why you selected a position. The best format could be a pro/con table (sample below), but is up to you as the author. You must consider complexity, feasibility, cost/effort to implement, but also ongoing operational impact and cost. You must consider the program principles and explain any deviations in detail. This is probably as important as the decision itself.
Option A | Option B | Option C | Option D | Option A | Option B | Option C | Option D | |
|---|---|---|---|---|---|---|---|---|
De-Risk Strong Contigency \ fallback option |
|
|
|
| High | Medium | Low | Medium |
De-risk Stabilisation on integrated process (Sales\Accounts Receivable, Payments\Accounts Payables) |
| High | Low | Low | Medium | |||
De-risk Ability to run Productions Simulations | High | Low | Low | High | ||||
Less Complexity - Less Interfaces |
|
|
|
| Low | High | Medium | Medium |
Less Complexity - One IHB Operating is less complex than two IHB in operation |
|
|
|
| High | Low | High | High |
| Additional Resource Cost |
| Low | High | High | High | |||
| Business resource impact |
| High | Low | High | High | |||
| Ease of Consolidation |
Stardard process to load into Cosnsol are expected to be utilised |
Stardard process to load into Cosnsol are expected to be utilised | Medium | Medium | High | Medium | ||
| Lower Cut-over impact (less payments outages). | High | Low | High | High |
Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.
