Preparation for the (re)launch of the first train on DCJ.

DCI.PI.XX - where XX is the iteration

(RTE = Release Train Engineer / TT = Transformation Team, PM = Product Management)

GREEN - DONE; GREY - NOT NOW; RED - PROBLEM/RISK 


Theme             Step   DescriptionOwnerDue DateActions
ART readiness

Confirm ART design

(Name, Mission, scope)

Is the scope (product, system, technology domains) of the organization understood?

  • Have we identified our end-to-end flow?
  • Have we identified the right customers/end users?

Train is based on the depto hence the above is not end to end value based for now 

RTE , TT

END OF OCT

Scope " Pricing and commercial analytics" 

To Rethink depending on the involvement of @hugo rosario's team

ART readiness

Identify ART level members

Have we identified the Release Train Engineer? Does he/she understand the scope of the role in preparing the organization and preparing for the PI Planning meeting?

Have we identified the Product Management team? Do they understand the scope of their role?



TT

RTE ad iterim = Bola

PM team =  Rogerio, Andrei, Dina (for the platform team)

Systems Architect = Gilles

ART readiness

System Team

Has the System Team (or any support functions) been identified and formed?

For now since the system team is usually to: Reduce the burden on individual Agile teams by handling complex integration tasks and/or supporting continuous integration and delivery, etc we will shift for a phase 2 (2nd release/prio)


ART readiness

Identify team members

POs , SMs

Does each Feature/component team have an identified Scrum Master/Team Coach and Product Owner?

RTE, TTEND OF OCT
ART readiness

Team commitment

Are there dedicated team members on every team?


ART readiness

Identify training for the launch

Does everyone (staff) in the organization receive the appropriate SAFe training?

(Leading SAFe, SAFe for Teams, RTE, PM...)

TTMID NOV

DCJ training set for the internal teams - LEMOS, Barbara 

SAFe awareness for the contractors

Barbara & Alix

DCJ workshop on roles and responsibilities -

Bongiorno-ext, Alix  and Bola 

DCJ PM on creating features

LEMOS, Barbara / @Bola 

ART readiness

Provide SAFe training

Does everyone can attend the session? TT

END OF NOV


Training to be provided to all internal people belonging to DCJ . Exception considered for Bola as the interim RTE

ART readiness

Planning timeframe, Iteration, and PI cadence

Have we identified the PI Planning dates, the Iteration cadence, and the PI cadence? Management, TT, RTE

END OF NOV

4*3 = 12 + 1 to kick off


ART readiness

Development infrastructure


Do we understand the impact on and/or plans for environments (for example, Continuous Integration and build environments, Freeze period)? Have we taken into account these constraints to set cadence & dates?Management, TT, RTE


 Cadence topic discussed in another item. 

Scope ReadinessExecutive, Business Owner participationDo we know who will set the business context and present the Product/Solution Vision? Do we have the high level vision and roadmap ready?Management, TT, RTE



Scope Readiness

Vision and ART Backlog

Is there a clear Vision of what we are building, at least over the next few PIs? Have we identified the top 10 or so Features that are the subject of the next PI?Management, TT, RTE



Scope Readiness

Define the features with PM

Is the backlog well define and ready (features have the right template and information)

TT, PMs, Sponsor?

END OF NOV

LEMOS, Barbara , Roscetti, Nicolas 

collaborating with Rogerio , Andrei and Dina (to be assigned)


PM as a role 

Is there reasonable agreement on priorities amongst the Business Owners and Product Management?

Coach and improve their knowledge on PM responsibilities (priorities, deadlines...) in order to support their work during Planning event and day to day activities




Scope Readiness

3 amigos coaching


Do we have regular meeting together + individually to coach PMs, RTE & Archi?

TT



Scope Readiness

Work with the POs to design USs


Coach and improve their knowledge on PO responsibilities (sizing, splitting) in order to support their work during Planning events and then, day to day activitiesPOs, TT, RTEUntil PI Planning for backlog readiness & after for improvement 

Bongiorno-ext, Alix to support the POs

Scope Readiness

Coach the SMs

(recurring activities, distraction ratio, ramp-up for newcomers,..)

Help them improve on Agile good practices: capacity computation, KPIs, facilitation skills, in order to unify and align practices.TT, RTEUntil PI Planning & after for improvement

Bongiorno-ext, Alix supporting with the capacity computation 


LYAKH-ext, Marina  and Jaiye-ext, Bola included on the SAFe training

Scope Readiness

Quality practices

Is there a strategy for unit testing and test automation? Any other practice guidelines?


Scope ReadinessAgileIs there any good practices guidelines in place or that should be improved?


Launch readiness

Set launch date PI Planning with the Management


Management, TT, RTE

END OF OCT.

04NOV

15 January - 16 January

Launch readiness

Send SAVE the date into calendar

Who needs to be invited? Do they understand why they are invited?

END OF OCT

ETD: 08NOV

New people:

Frank

Florence

Simon/Megane

Launch readinessDecide where and if hybrid etcAre all team members present in person or are arrangements made to involve them remotely?Management, TT, RTE

END OF OCT

ETD: 13NOV

BL to follow up
Launch readiness

Agenda agreement


MID DEC

Example:

Business context

Product vision -

Architecture vision - LEMOS, Barbara to set the meeting

Planning context and lunch (RTE - how it will all happen)

Team breakouts

Draft plan review

Management review + Problem solving (challenges, risks , impediments)

Launch readiness

Create a slide set template


PM, RTE, TT

Jaiye-ext, Bola 

END OF OCT

BL shared template on 04NOV


Launch readinessRehearsal sessionHave we rehearse the presentation to see if timing/content is good/efficient?Management, TT, RTE, PMEND OF NOV
Launch readinessSend comm to the stakeholders detailing what will happen with the dateHave we sent a communication to the stakeholders detailing what will happen during the PI Planning day? Have they been informed before of the agile way of working?

RTE


END OF NOV
Launch readinessSend PI iterations invites to all stakeholders

Have we block the agendas for the whole increment with PI iterations invites to all stakeholders?

  • Teams events include: Iteration Planning, Iteration Review, Iteration Retrospective.
  • ART events include: PI Planning, System Demo, Inspect & Adapt, Coach Sync, and PO Sync.
RTEEND NOV
Launch readinessSend I&A invites
RTEMID DEC
Launch readinessIdentify theme
RTEMID DEC
Launch readiness

Prepare tools

(Miro boards, channels, confidence forms)


RTEMID DEC
Launch readiness

Align the SMs on the capacity computation

(recurring activities, distraction ratio, ramp-up for newcomers,..)


RTEEND NOV
Launch readiness

Setup weekly scrum of scrums (ART sync)


RTE leads - SMsEND NOVJaiye-ext, Bola 
Launch readiness

Setup weekly PO sync (ART sync)


RTE leads - PMs/POsEND NOVJaiye-ext, Bola 
Launch readiness

Setup demo invites


RTEMID DEC

One backlog for the whole train


TT


Risks and dependencies tracking are set





Launch readiness

Changes to standard  minimu practices for each team.

Jira identified, team composition DoR, DoD , Feature/enabler template set, US flow, risk board is understood



END NOV

Jaiye-ext, Bola , @Marina 



PI Presentation content preparation 

ItemDescriptionResponsibility
Final agenda 

Final agenda with start and stop times, timeboxes, speaker callouts, etc.

/!\ Take into account time zone differences if the planning meeting is spread across multiple locations.

RTE
Facilitator preparationEnsure everything is ready on time, tools set-up, invitations, breakouts... Connect 10' prior to event to check connection (if remote)TT/ 
RTE/SMs
Introductory briefingEstablishes schedule, objectives, context, and requirements for each sessionTT/ 
RTE
Executive briefingDefines current business contextExecutive/Sponsor
Product Vision briefing(s)Briefings prepared by Product Management. Handouts/backlogs prepared with supporting detail (Features, priorities, market reports, use cases, UX guidelines, etc.).PM(s) and Business Owners
ART BacklogTop 10 Features. To prepare, review Vision, understand Strategic Themes, and gain alignment with product strategies.PM(s) and POs
Architectural Vision briefingCommunicate any new architectural Epics and system quality (nonfunctional) requirements.CTO/Architects, Security Directors, etc.
Tech practices briefingChanges to standard practices, new tools (test automation, Continuous Integration), expectations for the "definition of done," etc.PMs? Archi? Senior Tech Lead?