→ Put the tickets we are treating for now and classify concerning the difficulty
1) Bonjour La projection de stock s'arrête à Avril 22. Pourquoi ? Ghyslaine

2) Is it possible to add ressources AHL2MEL on Melle plant (7666) ? It is used for the attached materials which appeared in the list of SKU without MDC.
3) I will take over a part of Felix Lessard mission. Therefore, you can give the same rights as in his profile.; User ID : YOKO3589
Felix will keep Ospiate, New comer will take the Moerdjik plant.
4) I have a question about what is loaded into MRP?
Example: Material 143899 at 0294
July Forecast shows 25,397 and we have two orders from Rohm & Haas, so I would think the forecast should be 25,397 + 32,000 KG = 57,397 (assuming the forecast is consumed by orders in MRP)
This is the forecast I see in MRP

DIP Netting = 53,897...they are close, but I wonder why they are different. And, if I would see more extreme differences in other products.
Also, I see the 32MT open orders in the netting screen, but can I assume the netting takes place in MRP?


Response:
The forecast is sent to SAP after the S&OP validation at around 10 of the month. After that we’re not in the frozen period and the data is moving which explains the difference between what we have today in DIP Netting and SAP.
If we check what was sent to SAP after the last validation, we find in U01-Novecare Z800- S&OP reference datas-> independent requirement :

The sum of the independent requirements in July is 57397, which is the same value that we find in SAP by clicking in “element details” of ind req at 29.07.2022

In the view below, we find the independent requirement equal to 25397 because we have received two customer orders with the total of 32000 so that was deduced from the 57395 that we had before.