When we receive a request for a User Creation for Novecare here are the following steps:
| # | Actions to do |
|---|---|
| 1. | Create the user using the right User Type (Global Planner should be only for users that will run calculations)
|
| 2. | Associate the user to the right user(s) group(s) |
| 3. | If the user is a S&OP Leader:
Note: for a S&OP Leader, the user group used should be the Zone. |
| 4. | If the user is a S&OP Planner:
change object's visibility and write permission to "Allow"
click ok and save. Do the same thing for the other P&I workspaces.
|
| 4. | Go to workspace user right management, assign the plant to the S&OP Planner |
| 5. | Open the hierarchy → resource; assign the resource to the S&OP Planner |
| 6. | If changes are needed to be applied instantly an update of hierarchies must be done. The sequence : ALL GBU - UPDATE MASTER TABLE has to be wholly executed. It is mandatory to avoid the execution of single actions belonging to the sequence. NOTE : It is very important to test the changes to be applied. First by modeling in TEST or DEVELOPMENT environments, once the desired changes are correctly reflected they can be applied in the PRODUCTIVE environment. |