This document outlines the Syensqo-wide approach to data migration and readiness to move to SAP S/4HANA. It establishes a strategic and operational framework to ensure data is clean, reliable, structured and available at go-live.
The objectives are:
To plan, govern and control data migration activities from legacy systems to the SAP S/4HANA platform.
To define scope, dependencies, roles, risks and timelines aligned with cutover planning.
To ensure business engagement and ownership in all data quality and validation activities.
To meet global regulatory, operational and integration requirements with third-party systems.
To institutionalize data quality and governance practices that extend beyond go-live.
The migration to SAP S/4HANA is a core enabler of business transformation and digital integration across Syensqo operations. Accurate and high-quality data is critical for the success of this initiative as it directly impacts core business processes, user adoption, reporting accuracy and legal compliance.
This data approach takes into consideration the need to:
Harmonize disparate legacy system data models into a unified global standard.
Ensure operational continuity during cutover by preloading critical data and validating business readiness.
Enable phased go-lives while managing cross-system data dependencies.
Use repeatable and scalable tools and methods that support global harmonization efforts.
Key steps include:
Inventory and classification of all data objects
Definition of transformation rules and mappings
Execution of data profiling, cleansing and enrichment
Mock load cycles for reconciliation and process testing
Final cutover execution with validation and audit trails
The scope of data migration for this global ERP transformation encompasses all essential master data, open transactional data and selected historical records required to ensure business continuity, legal compliance and readiness at the point of cutover. Data will be migrated from multiple SAP ECC source systems, legacy third-party applications and local tools into a harmonized SAP S/4HANA environment.
Provide the sources of the data to be migrated
Describe the target application for the data to be migrated
The data dependencies diagram will be used to ensure Syensqo's data migration timeline remains achievable, dependent object loads may begin once the corresponding predecessor objects have been technically loaded with 100% success and have passed initial data verification. This approach supports timely execution across all load waves and has been designed to balance efficiency with data integrity.
Link - Data Dependencies Diagram
Describe the detailed process of conversion process
Explain how data will be extracted from the source systems, including tools and methods used.
Describe the transformation processes that will be applied to the data such as cleansing, formatting and enrichment to ensure compatibility with the target system.
Outline the steps involved in loading the transformed data into the target application, including any validation or verification processes.
Specify any special requirements or considerations that may impact the data migration process based on specific locations, regulatory compliance or system limitations. Clearly outline any regional or localization requirements such as country-specific data formats, legal reporting obligations or industry standards that must be adhered to (e.g., localization rules for countries like China).
If the data migration involves third-party systems or external data sources, such as Icertis, describe any additional requirements related to data extraction, transformation logic, validation rules or security measures that must be followed.
Identify the data team responsible for executing the migration and outline their key deliverables.
Identify the functional team involved in the project, detailing their deliverables and associated roles to ensure clarity in responsibilities.
Define the roles of each team member within the functional team outlining their responsibilities in relation to the data migration process.
Identify the members of the data team, listing their deliverables and responsibilities associated with the data migration efforts.
Define the specific roles and responsibilities of each member within the data team to ensure accountability and clarity in the migration process.
Identify the business team members engaged in the project, outlining their deliverables and how they contribute to the overall migration effort.
Define the roles and responsibilities of each member within the business team to ensure that all aspects of the migration process are covered and managed effectively.
Outline deliverables that will be produced by third party (e.g. tracker, reports, etc)
Outline the roles of the Third Party
Outline the assumptions that form the basis for this document and the development approach. Ensure the assumptions are realistic, specific and relevant to avoid potential misunderstandings or misalignment.
Describe any risks and issues identified for conversion and corresponding action to resolve/mitigate them
| Risk/Issue | Mitigation Action |
|---|---|
Describe detailed data validation process including proof of completeness of validation, accuracy and data cleansing validation. Include data migration process flow
Clearly describe the measures and protocols necessary to protect sensitive data during the migration process.