General presentation

The aim of the document is to list daily and monthly checks to do and following actions.


All checks are done by CGI team.

In case of BW assistance, contact Felipe Rodrigues (Competence Center / SCMS domain)

In case of DynaSys assistance, contact DynaSys.Interface.Team@solvay.com

In case of MFT/Webservice assistance, contact support.xml@solvay.com

 

Please register all production issue in following google spreasheet

Due to several complaints from DynaSys Team and DynaSys users, it is important to fill the document with detailed information

 

Every day by 9.15 am CET

with transaction ST13 / BW-Tools,  use the variants DYNASYS_INTERF and DYNASYS_REPORT to have all the chains of interface and reporting

Check Interfaces chains - Steps to follow & Actions to do


Check following chains has run, and ended ok.

ChainTypeDescriptionFrequencyCriticity

PC_DPS_DYNASYS_01

InterfaceDPS DynaSys: META PART1 - D - Daily Meta-Chain Part 1

Daily after Global sales chains (Not on week-ends or certains bank holidays )

=> starter = EVENT Z_EVT_END_GL006

HIGH

PC_DPS_DYNASYS_25

InterfaceDPS DynaSys: META PART2 - D - Daily Meta-Chain Part 2

Daily after Global sales chains (Not on week-ends or certains bank holidays )

=> starter = EVENT Z_EVT_END_GL003

HIGH
PC_DPS_DYNASYS_03InterfaceDPS Dynasys: META - W - Weekly Meta-ChainWeekly on saturdays à 9am CET

HIGH

Certain GBUs are weekly refreshed on DynaSys => In case of issue, inform DynaSys team on Monday

CAUTION : This chain should not be repaired on Mondays as daily chain is replacing it



If both daily chains have not finished by 7 am, identify the root cause and estimate the ended time (if possible)

Inform DynaSys Interface Team before by 9:15 am CET => DynaSys Interface Team : Interface Issue

Check Reporting chains - Steps to follow & Actions to do

Check the process chain from the night before 6pm until current day 7am.

ChainTypeDescriptionFrequencyCriticityComment

PC_DPS_DYNASYS_15

ReportingDPS Dynasys: META - D - 6.Reporting DynaSys (Dynamic KPIs)Daily at 7am , 2pm , 6pm , 11pm (Not on week-ends or certains bank holidays )HIGH

PC_DPS_DYNASYS_09

ReportingDPS Dynasys: META - M - 6.Reporting DynaSys (Snapshots)Every 6th of month at 6amHIGH
PC_DPS_DYNASYS_23ReportingDPS Dynasys: META - M - 6.Reporting DynaSys (MasterData)

Daily at 10pm (Not on week-ends or certains bank holidays )

MEDIUM
PC_DPS_DYNASYS_33ReportingDPS Dynasys: TD - D - Reporting Dynasys (DIP Inventory KPIs)Daily at 10am (or 11am), 2pm , 6pm , 11pm (Not on week-ends or certains bank holidays )MEDIUM

PC_APO_17

ReportingMETA - D - APO - Current period and future periodsDaily at 1am (Not on week-ends or certains bank holidays )LOWremoved from scheduling 07/07/2020 (Special Chem Go-Live)

PC_APO_18

ReportingMETA - M - APO - SnapshotsEvery 6th of month at 9amLOWremoved from scheduling 07/07/2020 (Special Chem Go-Live)



If chain PC_DPS_DYNASYS_15 has not run at 6pm CET previous night or 11pm CET previous night

=> inform DynaSys.Interface.Team@solvay.com


If chain PC_DPS_DYNASYS_15 has not run at 7am CET 

=> get last timestamp in DPS DPDYN39 / DYN - Table SYS_TIMESTAMP ( Write-Optimized ) by running IP "IP: DTS_SYS_TIMESTAMP (Dynasys) - Full with filters"

=> check time stamps date + time

=> inform  DynaSys.Interface.Team@solvay.com

If timestamp is over 7am, BW DynaSys Team will analyse if it is worth it to force an intermediate upload.

In case of intermediate load, no need to inform users. Otherwise users will be noticed by DynaSys.Interface.Team@solvay.com => DynaSys Interface Team : Reporting Issue

If no timestamp at all,  inform DynaSys.Interface.Team@solvay.com => DynaSys Interface Team : Reporting Issue


If chain PC_DPS_DYNASYS_33 has not run at 6pm CET previous night or 11pm CET previous night

=> inform DynaSys.Interface.Team@solvay.com


If chain PC_DPS_DYNASYS_33 has not run at 10am CET or 11am CET

=> get last timestamp in DPS DPDYN39 / DYN - Table SYS_TIMESTAMP ( Write-Optimized ) by running IP "IP: DTS_SYS_TIMESTAMP (Dynasys) - Full with filters"

Daynasys Source = BW

Dynasys - Table Name = EXP_DIP_BW

Dynasys - Type = TECH : EXPORT BW

=> check time stamps date + time

=> inform  DynaSys.Interface.Team@solvay.com

If timestamp is over 11am, BW DynaSys Team will analyse if it is worth it to force an intermediate upload.

In case of intermediate load, no need to inform users. Otherwise users will be noticed by DynaSys.Interface.Team@solvay.com => DynaSys Interface Team : Reporting Issue

If no timestamp at all,  inform DynaSys.Interface.Team@solvay.com => DynaSys Interface Team : Reporting Issue

Every day by 2.45 pm CET

Check following chain or check you have received the automatic email called "Demand planning BW report successfully update" (for PC_DPS_DYNASYS_15)  and "DiP-PP reporting in BW successfully updated" (PC_DPS_DYNASYS_33).

ChainTypeDescriptionFrequencyCriticity

PC_DPS_DYNASYS_15

ReportingDPS Dynasys: META - D - 6.Reporting DynaSys (Dynamic KPIs)Daily at 7am , 2pm , 6pm , 11pm (Not on week-ends or certains bank holidays )HIGH
PC_DPS_DYNASYS_33 Reporting DPS Dynasys: TD - D - Reporting Dynasys (DIP Inventory KPIs)Daily at 10am (or 11am), 2pm , 6pm , 11pm (Not on week-ends or certains bank holidays )Medium

if no, refer to action described for morning reporting checks.

Communication

DynaSys Interface Team : Interface Issue

Email address:  DynaSys.Interface.Team@solvay.com

If only PC_DPS_DYNASYS_25 is late => adapt object and content of the email refering to DP
if both chains are late => adapt object and content of the email refering to both  DP / DiP-PP


Email Object  /!\ [DP/DiP-PP] Dynamic import will be late today


Email Content (to be adjusted according to impact DP and / or DiP-PP):

"Hello,

Due to an issue on BW side, data files will not be available for Dynasys integration before 11:00 CET.
The integration in Dynasys will be ended approximatively round 12:00 CET for DiP1/DiP2/DiP3 and 12:30 CET for DP1/DP2/DP3
Regards,"

 * give more details about the issue (Global Sales delay, Global Sales error, DynaSys chain issue, Source System PF1/WP1 issue...)


DynaSys Interface Team : Reporting Issue

email or tchat DynaSys.Interface.Team@solvay.com with DPDYN39 contain

DynaSys Team : Interface/Reporting Issue

KeyUsers : Reporting message 

Message to users by using last received emails called (or create new message)


Add distribution list :

$SBS-IS-DynaSys team => IS Team

$DynaSysDP2-KeyUsers (DP2 = CM Aero) =>  for CM Aero message

$DynaSysDP3-KeyUsers (DP3 = Novecare) => for others GBUs

$DynaSysDP-KeyUsers (DP = rest of GBUs) => for others GBUs


=> inform QV team if necessary  guillaume.viaux-exterieur@solvay.com (depending of the issue)

Check impact on QV - Demand Review for SBS Dashboard - All except CM (Aero)


Change Email Object

Demand planning BW report => Not up to date or Not available   => for others GBUs

CM Aero-Demand planning BW report => Not up to date  or Not available => for CM Aero


Put Email content 

"Hello, 

Due to an issue, Demand planning BW reports are  not up to date  or not available
I will keep you informed when report are available."


KeyUsers : Interface message 


$DynasysDP1-KeyUsers
$DynasysDP2-KeyUsers
$DynasysDP3-KeyUsers
$DynasysUsersDiP1 (Silica Soad Perox) <DynasysUsersDiP-PP@solvay.com>
$DynaSysUsersDiP2 (TS - Aroma)  <DynaSysUsersDiP-PP2@solvay.com>
$DynaSysUsersDiP3 (Novecare) <DynasysUsersDiP3@solvay.com>

If there is a requirement for follow-up (on incident status), a wiki or google doc could be 

Contacts 

CGI team for WBP Chains Issues



Generic email address (caution 23 members) : SBS-IS-Appli-Techno-Report-BW.CGI@solvay.com

DynaSys team for DYNASYS PROD Issues 

DynaSys.Interface.Team@solvay.com


Know Issues


Interface Flat files are generated but not transfered to BW


Sometimes Dynasys do not receive the interface flat files from BW, due to an issue in the connection between both systems. Normally in this case a ticket is raised by Dynasys Team to BW L3 team.

The first thing to do is to check in AL11 that all files are correctly generated in the directories with the date of current day :

Then, run the process chain associated to the AL11 folder to send all files from BW to DYnasys :


Field XXX is not a member of XXX

See Connection with UD CONNECT


Weekly and Monthly release days for DynaSys team (impact on loadings)

DynaSys DP = Weekly release all Mondays from 12pm to 12h45pm + Monthly release every 1st Thursday of the month 

  DynaSys DIP = Monthly Release every 2nd Thurdays of the month


Note that during the days of the monthly release, Demand Planning BW report is not updated at 2pm and sometimes also 6pm.


Below, an example of email to inform users:

"Hello,

Due to Release on DynaSys side, Demand Planning BW report will not be updated at 2pm CET. The next update is scheduled today at 6pm CET.
Thanks for your understanding.

Regards,
"  


Issue on APD => Dump on ST22 : TSV_TNEW_PAGE_ALLOC_FAILED

Sometimes it can be possible to have an issue at APD level when there is no more memory available.


ST22 Dump log :


When it's happened, try to modify the Performance settings at APD Level :

By default the flag is active.


TODO :

Uncheck the Process Data in Memory, activate the APD and repeat the step in issue at the process chain level.


If WBP is not available Saturday

If WBP in not available during saturday morning, you have to manually generate weekly files

Run temporally chain PC_PP_BOM_06 to update BOM (until PF1 bug fixing) + reload ADSO ABDPDY50 then generate BOM file