Core Rules

All the rules used in Global Sales were determined by SAP experts.

Solvay:

Rhodia:

To Be Invoiced Date

The to be invoiced date is calculated following the rules below (WP1 and PF1):

The Rest To Be Delivered for PO's Transfers

The rest to be delivered is the quantity which need to be delivered to the customer to complete the requested quantity. The rest to be delivered is defined at the purchase order line level. It is used in the Open order part, to determine the to be invoiced quantities and the values. The calculation is done following the rules below:

IMPORTANT: If the rest to be delivered is negative, the quantity: rest to be delivered is forced to 0.

Purchase Order (Transfers) Status

Open Order

Definitions: A PO transfers order is open if:

Example:

The PO's line 4512394035/10 is closed because the indicator Final Delivery is flagged.

Billed

Definition: A PO transfers order line is billed, when a billing line is created with reference document:

IMPORTANT: On the transfers process, just purchase documents type NB will generate billing documents.

Example:

The PO 4511943102 has a billing document created in reference of the delivery document 86095478. The PO's transfers is billed.

Delivered Quantity

Definition: Is the quantity issued (the delivery line has an actual GI date).

Example:

The delivery line 87422928/10 which contain the batch 900001 is issued. The quantity was delivered.