General Description |
|---|
Number of days to transform a PReq (Purchasing Requisition) into a PO (Purchasing Order)
|
KPI Name | Definition |
|
Lead time to transform a conform Preq into a PO |
# of days between conform PReq Release date vs PO Item Creation date:Variation in days between Preq and PO |
|
Lead time to transform a non conform Preq into a PO | # of days between non confrom PReq Release date vs PO Item Creation date:Variation in days between Preq and PO |
|
Lead time to transform a Preq into a PO | # of days between PReq Release date vs PO Item Creation date:Variation in days between Preq and PO |
|
# PO Item with PReq | Number of PO Items with PReq (PReq number <>#)
|
|
# Conform PReq | Numbers of PReq in accordance to the conformity (refers to all mandatory information are filled when creating a purchase request)
|
|
# Non Conform PReq | Numbers of PReq out of accordance to the conformity (Nom conform)Nom conform refers to either one of these Purchasing Groups is equal E02, E03, FQE, N01, N02, N03, N04, N05, N06, N07, N08, N09, N10, N11, N12, N13, N14, N15 (missing of at least 1 mandatory information when creating a purchase request to create a PO). Below is the process of Non conform PREq. |
|
% Nom Conform PReq | Nb of non-conform Preq |
|
Leadtime by range of days | % of a conform/Non conform Preq transformed into a PO spread by range of days |
| Source Information: BW (WP1 & PF1) | |
|---|---|
Core Query: | BW_QRY_MV_PROVG_0004 |
QV Query: | QVSBS_BW_QRY_MV_PROVG_0001 (PREQ) |
BW Filters |
|
Specific Dimensions | |
PO Item Created By | |
Capex Flag | For CAPEX (IM), the Project type assigned to the relevant WBS element is: II (Investments) type in WP1.For OPEX (NC), the Project type assigned to the relevant WBS element is OI (Internal Operations) type in WP1 |
PO Category | E-Catalogue : PO Need Origin = 1Ref. Material in Stock : Material <> # + Account assignment code = #Ref. Material non in Stock : Material <> # + Account assignment code <> #Services & Material non Ref. : Material = # |
PO Item Critical | Y/N
|
VIP Supplier | Y/N (Vendor Attribute = VIP Vendor => Y=VIP ; N=#) |
Internal Suppliers | Y/N (Vendor Attribute = Class => Y=G ; N=the rest) |
Purchasing Group | |
Purchasing Organization | |