François Carette
 Performance & Capex Reporting Manager - GEC
Marie-Line Ardito

General Description

Capability to have a view of the Forecasts by approval status and the related yearly authorized amount for a selected period
  • Colmar Capex/Capspend by approval status : based on the selected period, capability to see by GBU, Zone, Bundle, Plant :
The authorized amount
The total of Actuals
The total of Forecasts
split by approval status of the project
Calculation 
Capex Forecast
is the prevision of capex filled and updated by the GBU into Colmar
  
Capspend Forecast
is the prevision of Capspend filled and updated by the GBU into Colmar
  
General Reason
directly updated by the reason of investment according to the Capex 01 procedure
  
General Reason
is the main reason for investment

Sources

Capex/Capspend Forecasts

Core query
BW_COLMAR_MVIPCO17_0001
QV query
QVCOLMAR_BW_QRY_MVIPCO17_0003
Refresh frequency
Daily - full reload
Filters
Investment type <> training

Specific Dimensions

  • Version : Active version (last version updated in Colmar), Y versions, Y-1 versions
  • Project type : Capitalized, Not Capitalized
  • Planned : Yes, No
  • Bundle : list of bundles (def + key)
  • Project status : Approved (as soon as there is an authorized amount), Not Approved
  • Project approval status : Present approval status of the project
  • Project approval year : for a bundle, 1rst date of approval of the projects of the bundle

Scope

  • All the projects entered in Colmar with forecasted budget on the available versions
All the accesses must be validated by the
GBU Capex Coordinators
Authorisations' rights per GBU, Zone or Plant
Access form