Pierre BoyerProcess Manager RtR |
Marie-Line Ardito |
General Description |
|---|
Gives a global view of Actual Destionation Fixed Costs using the Cost Element hierarchy or the Cost Center hierarchy
|
| Calculation | |||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Actual Destination | All costs which are debit/credit postings. It includes both Primary and Secondary costs (refer below table on Cost type, Cost Element & Cost Category).
| ||||||||||||||||||
Budget - GBU | It corresponds to Plan Value V0 or V1 (budget entered on the cost centers in the ERP)
Note: The V0 is currently filled only for production cost centers. | ||||||||||||||||||
Budget - Function | It corresponds to the budget given by the Corporate function - manual files |
Sources | Fixed Costs GBU View |
|---|---|
Core query | BW_QRY_MPR_FC003_0003 |
QV query | QVSBS_BW_QRY_MPR_FC003_0003 |
Refresh frequency | Everyday for the first 2 weeks of the month (for the previous month data) |
Filters | BFC GBU (Responsible Cost Center), Responsible Plant (Resp Cost Center) |
Specific Dimensions |
|---|
|
Scope |
|---|
The scopes cover are:
|
|
All the accesses must be validated by theGBU Finance or Industrial DirectorsAuthorisations' rights per GBU or Funtion, Zone, PlantAccess form |