Status

Owner
StakeholdersThe business stakeholders involved in making, reviewing, and endorsing this decision. Type @ to mention people by name

Purpose

The purpose of this document is to define the conversion approach to create Product Resource & Tools in S/4 HANA.

Legacy Plant Production Resources & Tools is using a diverse range of formats across the different systems. There are instances where the same Production Resources & Tools is duplicated within and across sources, with informal words. This results in data inconsistency. As per SyWay design, EAM Maintenance Production Resources & Tools will be standardized.


Conversion Scope

The scope of this document covers the approach for converting active Production Resources & Tools from Legacy Source Systems into S/4HANA following the Production Resources & Tools Master Data Design Standard.


The data from legacy system includes:

  1. PRT Category: E-Equipment, P-Measuring Point, Not Marked for Deletion (Tcode: CF03 (All from Selection list)

The data from legacy system excludes:

  1. Exclusion Criteria 1


List of source systems and approximate number of records
SourceScope

Source Approx No. of Records

Target SystemTarget Approx

No. of Records

PF2, WP2

An initial extract will be provided to business to evaluate.

Additional data/records may be required and these will be constructed via DCT.

Enrichment of in-scope data may be required and will be added via transformation rules (business/technical).

2

S/4HANA

2

Additional Information

Multi-language Requirement

Summarize Multi-language Requirement/s, if any

Document Management

Long text and DIR are not covered in this document as they are defined as another data object.

Legal Requirement

Not Applicable

Special Requirements

Not Applicable




Target Design

With Functional input, document the technical design of the target fields that are in the scope of this document.

The technical design of the target for this conversion approach.

PLFH : Task list - production resources/tools details

TableFieldData ElementField DescriptionData TypeLengthRequirement
PLFHMANDTMANDTClientCLNT3T000
PLFHPLNTYPLNTYTask List TypeCHAR1Check table: TCA01
PLFHPLNNRPLNNRKey for Task List GroupCHAR8
PLFHPZLFHPZLFHItem counter for production resources/toolsNUMC8
PLFHZAEHLCIM_COUNTInternal counterNUMC8
PLFHDATUVDATUVValid-From DateDATS8
PLFHTECHVTECHVTechnical status fromCHAR12
PLFHLOEKZLKENZDeletion IndicatorCHAR1
PLFHPARKZPARKZIndicator: inactive changesCHAR1
PLFHAENNRAENNRChange NumberCHAR12AENR
PLFHDATUIANDATDate record created onDATS8
PLFHUSERIANNAMUser who created recordCHAR12
PLFHDATUCAEDATChanged OnDATS8
PLFHUSERCAENAMName of Person Who Changed ObjectCHAR12
PLFHOBJTYCR_OBJTYObject types of the CIM resourceCHAR2
PLFHOBJIDCR_OBJIDObject ID of the resourceNUMC8CRID
PLFHOBJCTOBJCT_DObject of a task listCHAR1
PLFHPLNALPLNALGroup CounterCHAR2
PLFHPLNFLPLNFOLGESequenceCHAR6
PLFHPLNKNPLNKNNumber of the task list nodeNUMC8
PLFHPSNFHPSNFHItem Number for Production Resource/ToolNUMC4
PLFHSTEUFSTEUFControl key for management of production resources/toolsCHAR4TCF10
PLFHKZKBLKZKBLIndicator: Create load records for prod. resources/toolsCHAR1
PLFHBZOFFBBZOFFBReference date to start of production resource/tool usageCHAR2TCA54
PLFHOFFSTBOFFSTBOffset to start of production resource/tool usageQUAN5
PLFHEHOFFBEHOFFBOffset unit for start of prod. resource/tool usageUNIT3T006
PLFHBZOFFEBZOFFEReference date for end of production resource/tool usageCHAR2TCA54
PLFHOFFSTEOFFSTEOffset to finish of production resource/tool usageQUAN5
PLFHEHOFFEEHOFFEOffset unit for end of production resource/tool usageUNIT3T006
PLFHMGEINHMGEINHQuantity unit of production resource/toolUNIT3T006
PLFHMGVGWMGVGWStandard value for the PRT quantityQUAN9(3)
PLFHMGFORMCF_MGFORMFormula for calculating the total quantity of PRTCHAR6TC25
PLFHEWEINHEWEINHUsage value unit of the production resource/toolUNIT3T006
PLFHEWVGWEWVGWStandard usage value for production resources/toolsQUAN9(3)
PLFHEWFORMCF_EWFORMFormula for calculating the total usage value of PRTCHAR6TC25
PLFHTXTSPSPRASLanguage KeyLANG1T002
PLFHKTSCHCF_KTSCHStandard text key for production resources/toolsCHAR7T435
PLFHTXTZ1TXTZ1First line of text for production resources/toolsCHAR40
PLFHKNOBJKNOBJNumber of Object with Assigned DependenciesNUMC18
PLFHGP_KRIT1PLOBJPlanning objectCHAR18


CRVE_A : Assignment PRT data - equipment

TableFieldData ElementField DescriptionData TypeLengthRequirement
CRVE_A OBJTYCR_OBJTYObject types of the CIM resourceCHAR2(0)
CRVE_A OBJIDCR_OBJIDObject ID of the resourceNUMC8(0)CRID
CRVE_A EQUNREQUNREquipment NumberCHAR18(0)EQUI


AFFH : PRT assignment data for the work order details

TableFieldData ElementField DescriptionData TypeLengthRequirement
AFFHMANDTMANDTClientCLNT3T000
AFFHAUFPLCO_AUFPLRouting number of operations in the orderNUMC10
AFFHPZLFHPZLFHItem counter for production resources/toolsNUMC8
AFFHLOEKZLKENZDeletion IndicatorCHAR1
AFFHPARKZPARKZIndicator: inactive changesCHAR1
AFFHDATUIANDATDate record created onDATS8
AFFHUSERIANNAMUser who created recordCHAR12
AFFHDATUCAEDATChanged OnDATS8
AFFHUSERCAENAMName of Person Who Changed ObjectCHAR12
AFFHOBJTYCR_OBJTYObject types of the CIM resourceCHAR2
AFFHOBJIDCR_OBJIDObject ID of the resourceNUMC8CRID
AFFHPLNTY_KEYPLNTYTask List TypeCHAR1TCA01
AFFHPLNNR_KEYPLNNRKey for Task List GroupCHAR8
AFFHPZLFH_KEYPZLFHItem counter for production resources/toolsNUMC8
AFFHZAEHL_KEYCIM_COUNTInternal counterNUMC8
AFFHOBJCTOBJCT_DObject of a task listCHAR1
AFFHAPLZLCIM_COUNTInternal counterNUMC8
AFFHPSNFHPSNFHItem Number for Production Resource/ToolNUMC4
AFFHOBJNRJ_OBJNRObject numberCHAR22ONR00
AFFHSTEUFSTEUFControl key for management of production resources/toolsCHAR4TCF10
AFFHKZKBLKZKBLIndicator: Create load records for prod. resources/toolsCHAR1
AFFHBZOFFBBZOFFBReference date to start of production resource/tool usageCHAR2TCA54
AFFHOFFSTBOFFSTBOffset to start of production resource/tool usageQUAN5
AFFHEHOFFBEHOFFBOffset unit for start of prod. resource/tool usageUNIT3T006
AFFHBZOFFEBZOFFEReference date for end of production resource/tool usageCHAR2TCA54
AFFHOFFSTEOFFSTEOffset to finish of production resource/tool usageQUAN5
AFFHEHOFFEEHOFFEOffset unit for end of production resource/tool usageUNIT3T006
AFFHFSFHDCF_FSFHDEarliest scheduled start (date) for PRT usageDATS8
AFFHFSFHZCF_FSFHZEarliest scheduled start (time) for PRT usageTIMS6
AFFHFEFHDCF_FEFHDEarliest scheduled finish (date) of PRT usageDATS8
AFFHFEFHZCF_FEFHZEarliest scheduled end (time) of PRT usageTIMS6
AFFHSSFHDCF_SSFHDLatest scheduled start (date) for PRT usageDATS8
AFFHSSFHZCF_SSFHZLatest scheduled start (time) for PRT usageTIMS6
AFFHSEFHDCF_SEFHDLatest scheduled finish (date) of PRT usageDATS8
AFFHSEFHZCF_SEFHZLatest scheduled end (time) for PRT usageTIMS6
AFFHISFHDCF_ISFHDActual start (date) of PRT usageDATS8
AFFHISFHZCF_ISFHZActual start (time) of PRT usageTIMS6
AFFHIEFHDCF_IEFHDActual finish (date) of PRT usageDATS8
AFFHIEFHZCF_IEFHZActual finish (time) of PRT usageTIMS6
AFFHDAUFLCF_DAUFLDuration of PRT usageFLTP16(16)
AFFHDAUEHCF_DAUEHTime unit for duration of PRT usageUNIT3T006
AFFHMGEINHMGEINHQuantity unit of production resource/toolUNIT3T006
AFFHMGVGWMGVGWStandard value for the PRT quantityQUAN9(3)
AFFHMGSOLEHMGEINHQuantity unit of production resource/toolUNIT3T006
AFFHMGSOLMGSOLTotal planned quantity of production resource/toolQUAN9(3)
AFFHMGISTEHMGEINHQuantity unit of production resource/toolUNIT3T006
AFFHMGISTMGISTConfirmed quantity of production resource/toolQUAN9(3)
AFFHMGRSTEHMGEINHQuantity unit of production resource/toolUNIT3T006
AFFHMGRSTMGRSTRemaining quantity of the production resource/toolQUAN9(3)
AFFHMGAUSEHMGEINHQuantity unit of production resource/toolUNIT3T006
AFFHMGAUSMGAUSQuantity of checked-out production resources/toolsQUAN9(3)
AFFHMGFORMCF_MGFORMFormula for calculating the total quantity of PRTCHAR6TC25
AFFHEWEINHEWEINHUsage value unit of the production resource/toolUNIT3T006
AFFHEWVGWEWVGWStandard usage value for production resources/toolsQUAN9(3)
AFFHEWSOLEHEWEINHUsage value unit of the production resource/toolUNIT3T006
AFFHEWSOLEWSOLTotal planned usage value of production resource/toolQUAN9(3)
AFFHEWISTEHEWEINHUsage value unit of the production resource/toolUNIT3T006
AFFHEWISTEWISTActual usage value for production resource/toolQUAN9(3)
AFFHEWRSTEHEWEINHUsage value unit of the production resource/toolUNIT3T006
AFFHEWRSTEWRSTRemaining usage value of the production resource/toolQUAN9(3)
AFFHEWFORMCF_EWFORMFormula for calculating the total usage value of PRTCHAR6TC25
AFFHTXTSPSPRASLanguage KeyLANG1T002
AFFHKTSCHCF_KTSCHStandard text key for production resources/toolsCHAR7T435
AFFHTXTZ1TXTZ1First line of text for production resources/toolsCHAR40
AFFHOBJTYPEOCM_OBJ_TYPEChange indicatorCHAR1
AFFHCH_PROCOCM_CH_PROCProcess that has lead to the change of an objectCHAR1
AFFHAENNRAENNRChange NumberCHAR12Assigned to domain


Data Cleansing

All data cleansing should take place in the data source system as defined in this document, unless system limitations prevent it.

If data cleansing is managed outside of the source system (e.g. Syniti Migrate, 3rd Party Vendor, DCT), the necessary documentation must be produced and appended to this deliverable for sign-off.

IDCriticalityError Message/Report DescriptionRuleOutputSource System

1018-001

C1

Invalid or Inactive Material linked to Production Resources & Tools

Production Resources & Tools as per Relevancy Criteria assigned with a Material which does not belong below:
1. Material Master (S2P) as per Relevancy Criteria

Material

PF2, WP2

1018-002

C1

Invalid or Inactive Document Info Record linked to Production Resources & Tools

Production Resources & Tools as per Relevancy Criteria assigned with a Document Info Record which does not belong below:
1. Document Info Record as per Relevancy Criteria

Document Info Record

PF2, WP2

1018-003

C1

Production Resources & Tools UOM Missing / incorrect.

Production Resources & Tools as per Relevancy Criteria with no UoM Assigned or Invalid UoM (T006)

Unit of Measure

PF2, WP2

1018-004

C1




PF2, WP2

Informal Words **

Group 1

Group 2

Group 3

Group 4

Group 5

*DNU

Delete

donot

Formerly

Old #

..

Deletion

DONT USE

From

Old[ ]

/

DELISTED

DON'T USE

Incorrect

PLEASE USE

?

Discontinued

Dup Use

Invalid

Pls Use

@

Disposable

DUPLICATE

New

Previously

^

DNU

-DUPLICATE

NOT ACTIVE

Replace

+

Do Not

DUPLICATION

not in use

Replaced

++

Do Not Re

Duplicidad

Not Used

RESERVED

£

Do Not Sell

Duplikat

NOT VALID

Retired

Defective

Do Not Use

Former

Obsolete

ZZDEL


Conversion Process

The high-level process is represented by the diagram below:

For legacy data that are not on SAP-PF2 and WP2 systems, collection will be done manually in the data collection template.

The high-level process for DCT is represented by the diagram below:


Data Privacy and Sensitivity

Summarize Data Privacy and Sensitivity Requirements, if any


Extraction

Extract data from a source into Syniti Migrate. There are 2 possibilities:

  1. The data exists. Syniti Migrate connects to the source and loads the data into Syniti Migrate. There are 3 methods:
    1. Perform full data extraction from relevant tables in the source system(s).
    2. Perform extraction through the application layer.
    3. Only if Syniti Migrate; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
  2. The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate

The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads

Extraction Run Sheet

Req #Requirement DescriptionTeam Responsible

1

Extract data from source system based on relevancy rule

SyWay Data Team

2

Google Sheet report pre-populated with PF2 and WP2 information to be generated based on relevancy criteria.

SyWay Data Team


Selection Screen

If applicable, this section will give the details on any selection screen parameters, including the parameter type, that are required to be entered to ensure consistent data extracts.
Selection Ref ScreenParameter NameSelection TypeRequirementValue to be entered/set
Not Applicable



















Data Collection Template (DCT)

Target Ready Data Collection Template will be created for Data Object data with exception of some fields which require transformation as mentioned in the transformation rule.

Production Resources & Tools DCT Rules

Field NameField DescriptionRule












Extraction Dependencies

List the steps that need to occur before extraction can commence

Item #Step DescriptionTeam Responsible

1

Ensure Syniti has the necessary connection and access to legacy servers


Data

2

Ensure that the necessary cleansing activities in legacy sources are complete

Data / Business

3

Ensure that create, change and deletion of master data is freeze in legacy Production system

Legacy IT


Transformation

The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:

  1. Perform value mapping and data transformation rules.
    1. Legacy values are mapped to the to-be values (this could include a default value)
    2. Values are transformed according to the rules defined in Syniti Migrate
  2. Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation

Transformation Run Sheet

Item #Step DescriptionTeam Responsible

1

Obtain DCT Sign-off from Business

SyWay A2D Data Team

2

<Add steps from Syniti Migrate here>

SyWay A2D Data Team

3

Review and Validate Error and Preload Reports

SyWay A2D Data Team

4

Generate Load Files

SyWay A2D Data Team


Transformation Rules

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic









































Transformation Mapping

Use the exact name and reference this section in the “Transformation rules” above
Mapping Table NameMapping Table Description








Transformation Dependencies

List the steps that need to occur before transformation can commence
Item #Step DescriptionTeam Responsible

1

Ensure DCT tables completeness

SyWay A2D Data Team

2

Value Mappings are according to the latest design -<List of Value Mappings>

SyWay A2D Data Team


Pre-Load Validation

Project Team

The following pre-load validations will be performed by the Project Team.

Completeness

TaskAction

Verify Record Count

SyWay A2D Data Team to verify that the total number of relevant records from legacy systems and DCTs (if any) is equal to the total number of records in the Preload and Load Sheets.

Verify Data Integrity

SyWay A2D Data Team to verify that the total number of Operations per Work Oder header extracted from legacy systems and DCTs (if any) should be equal to the total number of operations identified in the Preload and Load Sheets


Accuracy

TaskAction

Conversion Accuracy

SyWay A2D Data Team to verify that all fields below meet pass the checks:

  1. Mandatory Fields

  2. Field and Value Mapping Correctness

  3. Null Checks

  4. Text Length Checks

Review Error Reports

Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data.


Business

The following pre-load validations will be performed by the business.

Completeness

TaskAction

Verify Record Count

Business Data Owner/s to verify that the total number of relevant records from legacy systems and DCTs (if any) is equal to the total number of records in the Preload and Load Sheets.


Accuracy

TaskAction

Conversion Accuracy

Business Data Owner/s to verify that all fields below meet pass the checks:

  1. Mandatory Fields

  2. Field and Value Mapping Correctness

  3. Null Checks

  4. Text Length Checks


Load

The load process includes:

  1. Execute the automated data load into target system using load tool or product the load file if the load must be done manually
  2. Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation

Load Run Sheet

Item #Step DescriptionTeam Responsible

1

Syniti will provide load file

Syniti











Load Phase and Dependencies

Identify the phase as to “when” the load for this object will occur. <Pre-Cutover, Cutover, Post Cutover> and list the steps that need to occur before the load can commence

Configuration

List the Configurations required before loading can commence

Item #Configuration Item






Conversion Objects

Object #Preceding Object Conversion Approach

list the exact title of the conversion object of only the immediate predecessor – this will then confirm the DDD (Data Dependency Diagram)




Error Handling

The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management

Error TypeError DescriptionAction Taken










Post-Load Validation

Project Team

The following post-load validations will be performed by the Project Team.

Completeness

TaskAction

Verify Count

SyWay A2D Data Team to verify the record count created in target S/4 HANA by accessing post load reports in dspMigrate or standard reports from S/4 HANA.

Verify Logs

Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.).


Accuracy

TaskAction

Conversion Accuracy

SyWay A2D Data Team to verify that the Work order data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA.


Business

The following post-load validations will be performed by the business.

Completeness

TaskAction

Verify Count

Download Post Load Reports from dspMigrate and verify that the record count loaded in the target S/4 HANA is the same count as of the endorsed load file.


Accuracy

TaskAction

Conversion Accuracy

Verify that the EAM Work order data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA.


Key Assumptions

  • Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
  • Production Resources & Tools is in scope based on data design and any exception requested by business.
  • All data cleansing and preparation has been completed.

Any additional key assumptions.


See also

Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.

Change log

Workflow history