The purpose of this document is to define the conversion approach to create 2005 - Material Master - Work Scheduling View
in S/4 HANA.

In SAP PP-PI, the Work Scheduling view in the Material Master is a plant-specific view that contains essential data for producing a material in-house, allowing you to create and schedule production orders for it. Key fields within this view include the Production Scheduling Profile, which automates key tasks for production orders, and the Production Scheduler, who manages the material's capacity requirements. Maintaining this view is necessary for managing production processes and enabling the system to calculate production and operation start and end dates.

Purpose of the Work Scheduling View

Enables Production Orders:

You must maintain the Work Scheduling view for a material to allow the system to create production or process orders for it.

Plant-Level Data:

This view contains data specific to a particular plant, as production processes are managed at the plant level.

Key Fields and Their Functions

Production Scheduler:

A person or role responsible for managing the material's production in a specific plant. They determine how capacity requirements are calculated during a scheduling run.

Production Scheduling Profile (PSP):

A crucial tool for standardizing and automating production processes. It can dictate actions like automatically releasing and scheduling orders, triggering goods receipts, or managing batch creation.

While PF2 and WP2 serve as source systems, extensive mapping and transformation logic will be necessary to produce properly formatted load templates in line with the target design. Due to the new plant mapping and the Material / plant mapping, an extensive cleansing, transformation to do for this object

The data from legacy system may include:

  1. Only Active materials

  2. Material /Plant combination for all the "E" & "X" procurement materials as this view only intended for the manufactured products

The data from legacy system excludes:

  1. All materials flagged for deletion
  2. Any blocked or obsolete materials
  3. Any inactive materials that are out of scope


Conversion Scope

The scope of this document covers the approach for converting active Material Master - Work Scheduling view from Legacy Source Systems into S/4HANA following the Material Master - Work Scheduling view Master Data Design Standard.


The data from legacy system includes:

  1. Use the logic for Data Relevancy for the CNV-2019 Material Master - Basic Views
  2. All materials created in the previous 6 months will be included unless flagged for deletion
  3. Material Types ZUNB, ZBOM, ZPRC will be included regardless of activity (unless flagged for deletion)
  4. We will only include materials that are extended to the following (excluding ZPRC material type as these do not require plant extension):
    1. Company Codes in scope
    2. Plants in scope
    3. Purchasing Orgs in scope
    4. Sales Orgs in scope
  5. Include only Material Types in scope
  6. We will include for migration all materials that have activity over the previous 3 years, to include:
    1. For procurement data use EKKO/EKPO tables (remove any records in EKKO/EKPO where LOEKZ = 'X') and use EKPO/AEDAT for previous 3 years filter
    2. For sales data use VBAK/VBAP tables
    3. For production data use AFKO/AFPO tables 
  7. Additionally, we can check material movements using MKPF/MSEG tables (and Transaction Types: IB,ID,IZ,RS,SI,WA,WE,WF,WH,WI,WL,WO,WQ,WR,WS,WV,WZ)
  8. We will include for migration all materials that have open documents including the following:
    1. Open PO
    2. Open contracts
    3. Open STO
    4. Open SO
    5. Open WO
  9. Have current stock/open inventory
    1. For Open Inventory use the following tables:

      MARD

      MKOL (Consignment stock)

      MSKA (Sales Order stock)

      MSLB (Special stock)

      MSPR (Project stock)

  10. We will include all BOM data for materials in scope using tables: MAST/STKO/STPO
  11. Materials with Deletion Flags will be excluded unless appearing in the following open transactions:
    1. Open PO
    2. Open contracts
    3. Open STO
    4. Open SO
    5. Open WO
  12. Deletion Flags (Table/Field) are as follows: MARA/LVORM = 'X' MARA/MSTAE = Z3, Z4, ZZ (PF2 system) Z0 (WP2 system)
  13. Materials with the word 'OBSOLETE' or 'DELETED' contained within the Short Description will be excluded. Also excluded are Materials where Short Description contains '**OBS', '**OBS**', '**OBS***', '*OBS*', '*OBS**', '***OBS***'
  14. For selected data, if Procurement type MARC.BESKZ = 'E' , then MARC PSTAT like '%A%' - WS relevancy for all the relevant materials

The data from legacy system excludes:

  1. All materials flagged for deletion
  2. Any blocked or obsolete materials
  3. Any inactive materials that are out of scope


List of source systems and approximate number of records
SourceScope

Source Approx. No. of Records

Target SystemTarget Approx

No. of Records

PF2SAP ECC PF2 records for approximately 60 manufacturing plants divided in the 2 source systems8,000S4 HANA6,000
WP2SAP ECC PF2 records for approximately 60 manufacturing plants divided in the 2 source systems25,000S4 HANA20,000










Additional Information

Multi-language Requirement

System Pre-defined Languages

Document Management

N/A

Legal Requirement

N/A

Special Requirements

N/A





Target Design

With Functional input, document the technical design of the target fields that are in the scope of this document.

The technical design of the target for this conversion approach. The target is on the transformation rules. This list includes what type of field, length and others.

TableFieldData ElementField DescriptionData TypeLengthRequirement
MARCAUSMEAUSMEUnit of issueUNIT3C
MARCFRTMEFRTMEProduction unitUNIT3C
MARCFEVORFEVORProdn SupervisorCHAR3

R
List of customizing values and mapping with AS IS will be build as per

MARCLGPROLGPROStorage LocationCHAR4

R
List of customizing values and mapping with AS IS will be build as per

MARCSFCPFCO_PRODPRFProd. Sched. ProfileCHAR6

R : Mapping with As Is values and to be values to be provided

MARCMATGRMATNRGROUPMat. GroupingCHAR20NU
MARCSERNPSERAILSerial Number ProfileCHAR4NU
MARASERLVSERLVSerLevelCHAR1NU
MARCOCMPFOCM_GPROFILEOverall profileCHAR6NU
MARCKZKRIKZKRIIndicator: Critical partCHAR1NU
MARCKZECHKZECHBatch entryCHAR1R : Empty is a valid value
MARAXGCHPXGCHPApproved Batch Record RequiredCHAR1NU
MARCXCHPFXCHPFBatch Management
Requirement Indicator for Plant
CHAR1R : Empty is a valid value
MARCUNETOUNETOUnderdel. Tol.DEC3NU
MARCUEETOUEETOOverdeliv. Tol.DEC3NU
MARCUEETKUEETKIndicator: Unlimited
Overdelivery Allowed
CHAR1NU
MARCRUEZTRUEZTSetup timeDEC5NU
MARCTRANZTRANZInteroperationDEC5NU
MARCDZEITDZEITIn-house production timeDEC3NU
MARCBEARZBEARZProcessing timeDEC5NU
MARCBASMGBASMGBase quantityQUAN13NU


Data Cleansing

All data cleansing should take place in the data source system as defined in this document, unless system limitations prevent it.

If data cleansing is managed outside of the source system (e.g. Syniti Migrate, 3rd Party Vendor, DCT), the necessary documentation must be produced and appended to this deliverable for sign-off.

IDCriticalityError Message/Report DescriptionRuleOutputSource System
01CNV-01Material is not an "E" Procurement typeMaterials with "E" Procurement needs to have Work Scheduling ViewMaterials with no "E" procurement are out of scopePF2/WP2
02CNV-02Production Scheduling Profile is missingMaterials with WS View in Material Master must have Production Scheduling  ProfileMaterials with no Prod. Sched Profile needs to be updated by the businessPF2/WP2
03CNV-03Production Supervisor is MissingMaterials with WS view and No Prod Supervisor filled, needs to be checked by the BusinessProd Supervisor has been updated for all relevant materialsPF2/WP2
04CNV-04Production Storage Location is missingMaterials with WS view need to have Production Storage location definedMaterial without Prod Storage Location needs to be updated for all relevant materialsPF2/WP2
05CNV-05Production Version is missingMaterials with WS view needs to have a PVReport to show Proc Type E, WS view, w/o PV flagPF2/WP2
06CNV-06Work Scheduling View is missingMaterials with MARC-BESK = E but <> "A" as MARC statusNo Procurement type E has no Work Scheduling ViewPF2/WP2



Conversion Process

The high-level process is represented by the diagram below:


Data Privacy and Sensitivity

Summarize Data Privacy and Sensitivity Requirements, if any


Extraction

Extract data from a source into Syniti Migrate. There are 2 possibilities:

  1. The data exists. Syniti Migrate connects to the source and loads the data into Syniti Migrate. There are 3 methods:
    1. Perform full data extraction from relevant tables in the source system(s).
    2. Perform extraction through the application layer.
    3. Only if Syniti Migrate; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
  2. The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate

The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads

Extraction Run Sheet

Req #Requirement DescriptionTeam Responsible
1Extract from MARC all Material/Plant relevant as Procurement Type E, and be updated as "A" means that the Work Scheduling view is updatedSinity / Data Team

2

Extract data from source system based on relevancy rule

SyWay Data Team

3

Google Sheet report pre-populated with PF2 and WP2 information to be generated based on relevancy criteria. 

SyWay Data Team

4Sinity will extract data and convert it into SQL data base ad share with the teamSinity team


Selection Screen

If applicable, this section will give the details on any selection screen parameters, including the parameter type, that are required to be entered to ensure consistent data extracts.
Selection Ref ScreenParameter NameSelection TypeRequirementValue to be entered/set





















Data Collection Template (DCT)

Target Ready Data Collection Template will be created for Data Object data with exception of some fields which require transformation as mentioned in the transformation rule.

<Object> DCT Rules

Field NameField DescriptionRule
WERKSPLANTShow List
MATNRMaterial NumberShow List
AUSMEUnit of issueShow List
FRTMEProduction unitShow List
MMSTAMaterial StatusShow List
MMSTDValid FromReport day
LGPROProduction Storage Location

Selection Option / Values from System

KZECHBatch EntrySelection Option / Values from System
XCHPFBatch ManagementSelection Option / Values from System
INSMKPost to Inspection StockSelection Option / Values from System
FEVORProd SupervisorSelection Option / Values from System
SCHPFProd Sch ProfileSelection Option / Values from System
Link to the Layout


Extraction Dependencies

List the steps that need to occur before extraction can commence

Item #Step DescriptionTeam Responsible
1Data Profiling. MARC table Data Profiling needs to happen before the extraction of data.Sinity
2Data Cleansing Reports need to be createdSinity
3Data cleansing already done by the BusinessBusiness / Data Team
4Data has to be validated from the Business to get ready to extract from the sourceBusiness / Data Team




Transformation

The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:

  1. Perform value mapping and data transformation rules.
    1. Legacy values are mapped to the to-be values (this could include a default value)
    2. Values are transformed according to the rules defined in Syniti Migrate
  2. Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation

Transformation Run Sheet

Item #Step DescriptionTeam Responsible

1

<Add steps from Syniti Migrate here>

SyWay S2P Data Team

2

Review and Validate Error and Preload Reports

SyWay S2P Data Team

3

Generate Load Files

SyWay S2P Data Team


Transformation Rules

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic
1PF2/WQ2MARCWERKSPLANTS/4 HANAMARCWERKSPLANTFollow the transformation rules of CNV-2010 
1PF2/WQ2S_MARAMATNRMaterial NumberS/4HANAS_MARAMATNRMaterial NumberFollow the rule as per Material Master Basic Views about creation for new Material Numbers CNV-2018 CNV-2010 Materials - General Plant Data / S.Loc Data
2PF2/WQ2MARCAUSMEUnit of issueS/4HANAMARCAUSMEUnit of issueBased from MARA UOM
3PF2/WQ2MARCFRTMEProduction unitS/4HANAMARCFRTMEProduction unitValue Mapping (Unit of issue for material /plant)
6PF2/WQ2MARCLGPROProduction Storage LocationS/4HANAMARCLGPROProduction Storage LocationValue Mapping for Storage Location for Production 
7PF2/WQ2MARCKZECHBatch EntryS/4HANAMARCKZECHBatch EntryCopy
8PF2/WQ2MARCXCHPFBatch ManagementS/4HANAMARCXCHPFBatch ManagementCopy
10PF2/WQ2MARCFEVORProdn SupervisorS/4HANAMARCFEVOR

Prodn Supervisor

Value Mapping for Plant/Material / Prod Supervisor
11PF2/WQ2MARCSCHPFProd Sch ProfileS/4HANAMARCSCHPF

Prod Sch Profile

Values Mapping for Plant/Material/Prod Sch Profile


Transformation Mapping

Use the exact name and reference this section in the “Transformation rules” above
Mapping Table NameMapping Table Description

Material Type

Mapping of legacy Material Types to target system value

Material Group

Mapping of legacy Material Groups to target system value



Transformation Dependencies

List the steps that need to occur before transformation can commence
Item #Step DescriptionTeam Responsible

1

Data cleansing must be finished and validated

SyWay MFG Data Team

2

Data Transformation load files need to be validated by the business at Plant Level

SyWay MFG Data Team

3All Value Mapping files must be finished and aligned with the CSSyWay MFG Data Team
4All Data dependencies has to be finished. Any delay can bring delays on this


Pre-Load Validation

Project Team

The following pre-load validations will be performed by the Project Team.

Completeness

TaskAction

Verify Record Count

SyWay MFG Data Team to verify that the total number of relevant records from the  DCT is equal to the total number of records in the Preload and Load Sheets.






Accuracy

TaskAction

Conversion Accuracy

SyWay MFG Data Team to verify that all fields below meet pass the checks:

  1. Mandatory Fields
  2. Field and Value Mapping Correctness
  3. Null Checks
  4. Text Length Checks

Review Error Reports

Review and correct the errors.  Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data.




Business

The following pre-load validations will be performed by the business.

Completeness

TaskAction
To check Data Accuracy checking count of records to load and loadedBusiness Data Owner/s to verify that the total number of relevant records from the the DCT is equal to the total number of records in the Preload and Load Sheets.





Accuracy

TaskAction
Data owners to grant that the records in the load files are okay and according with the rules and mappingsTo check and validate the load files with all the transformation and mapping rules, to be signed off.





Load

The load process includes:

  1. Execute the automated data load into target system using load tool or product the load file if the load must be done manually
  2. Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation

Load Run Sheet

Item #Step DescriptionTeam Responsible

1

Go to load file and pick 5 data registers, load manually without any tool. See what happens. If all okay, proceed with the next step.

SyWay MFG Data Team

2

Go to load file and pick 10 records and load them with the tool. No action if the previous step has fallen. If not, then continue to load 10 records with the tool. Check if everything went okay.

SyWay MFG Data Team

3

Proceed with the full load if steps one and two were succeed. 

SyWay MFG Data Team

4

Validate few records loaded by accessing standard transactions from S/4HNA eg. MM03

SyWay MFG Data Team

5

Generate post load report if step 5 is validated

SyWay MFG Data Team


Load Phase and Dependencies

Identify the phase as to “when” the load for this object will occur. <Pre-Cutover, Cutover, Post Cutover> and list the steps that need to occur before the load can commence

Configuration

List the Configurations required before loading can commence

Item #Configuration Item
001Production Scheduling Profile
002Production Supervisor


Conversion Objects

Object #Preceding Object Conversion Approach

list the exact title of the conversion object of only the immediate predecessor – this will then confirm the DDD (Data Dependency Diagram)




Error Handling

The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management

Error TypeError DescriptionAction Taken










Post-Load Validation

Project Team

The following post-load validations will be performed by the Project Team.

Completeness

TaskAction

Verify Count

SyWay P2F MFG Data Team to verify the record count created in target S/4 HANA by accessing post load reports in dspMigrate or standard reports from S/4 HANA.






Accuracy

TaskAction

Verify Logs

Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.).






Business

The following post-load validations will be performed by the business.

Completeness

TaskAction

Verify Count

Download Post Load Reports from dspMigrate and verify that the record count loaded in the target S/4 HANA is the same count as of the endorsed load file.






Accuracy

TaskAction

Conversion Accuracy

Verify that the Material data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA.






Key Assumptions

  • Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
  • CNV-2008 Material Master - Work Scheduling view is in scope based on data design and any exception requested by business.

Any additional key assumptions.


See also

Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.

Change log

Workflow history