The purpose of this document is to define the conversion approach to create Inspection Methods in S/4HANA.

Inspection Methods are master data objects in SAP Quality Management (QM) that describe how inspections are to be carried out. They specify the procedure, tools, or references to be used for measuring or evaluating inspection characteristics, and can include documents such as test instructions, work instructions, or external references. This feature ensures standardized execution of quality inspections across plants, materials, and processes.

In SAP S/4HANA, the structure and usage of inspection methods remain consistent with SAP ECC. Inspection methods are typically created at the plant level and assigned to master inspection characteristics (MICs) or directly to inspection plan characteristics. Methods may also include language-dependent descriptions, versioning, validity dates, and document references.

In SAP ECC, aside from the standard structure of inspection method master data (method number, version, plant, and description), additional combinations may exist, such as methods assigned to specific catalogs, methods linked to custom documentation, or methods maintained with plant-independent validity. Some legacy ECC systems may also contain methods with non-standard extensions or inactive versions that need to be reviewed and cleansed (pending MDS).

This conversion aims to migrate active and relevant inspection method records from existing ECC systems into S/4HANA by applying the required transformation logic using Syniti as the data migration and transformation platform. The converted records will be loaded into the target S/4HANA system using standard SAP mechanisms such as BAPIs (e.g., BAPI_INSPECTIONMETHOD_CREATE), IDOCs, or direct table loads where applicable, ensuring consistency, compliance, and reusability in quality processes.



Conversion Scope

The scope of this document covers the approach for converting active 1043 Inspection Methods from Legacy Source Systems into S/4HANA following the Inspection Method Master Data Design Standard.

The data from legacy system includes:

  1. Active Inspection Methods used within the last four (4) years in inspection plans or master inspection characteristics or Master recipe.

  2. Inspection Methods without deletion flag.

  3. Consider inspection methods only with being created & released status for migration(LOEKZ = 1, 2)
  4. Plant-specific and global Inspection Methods that will be migrated to the To-Be Plant Mapping (taking into consideration the To-Be definition of Plants).

  5. Inspection Methods referenced in active MICs or inspection plans.

The data from legacy system excludes:

  1. Inactive Inspection Methods not used in more than four (4) years.

  2. Inspection Methods marked for deletion.

  3. Inspection methods other than released , being created status.
  4. Inspection Methods belonging to deleted plants (per To-Be Plant mapping).

  5. Obsolete or duplicate Inspection Methods that are no longer relevant


Relevancy rule

  1. Active Inspection Methods used within the last four (4) years in inspection plans or master inspection characteristics or Master recipe. 

Derive the last 4 years of Inspection plans or MICs from rules provided in respective CS, after that follow the below logics to get the list of Inspection methods.

(PLMK-QMTB_WERKS = QMTB-WERKS AND PLMK-PMETHOD = QMTB-PMTNR AND PLMK-PLNTY IN ('Q', '2')  )

OR 
(QPMZ-WERKPM = QMTB-WERKS AND QMPZ-PMETHOD = QMTB-PMTNR)

      2. Inspection Methods without deletion flag. QMTB-LOEKZ <> '4'(Deletion flag)

      3. Consider inspection methods only with released or being created status for migration. QMTB-LOEKZ = '2'(Released) or QMTB-LOEKZ '1'(Being created)


List of source systems and approximate number of records
SourceScope

Source Approx No. of Records

Target SystemTarget Approx

No. of Records

PF2/WP2

Inspection Methods will be extracted from PF2 and WP2

PF2 = 153

WP2 = 479

S/4 HANA

632 records

Additional Information

Multi-language Requirement

Inspection Method description will be maintained in English by default.

Since multi-language support is available for Inspection Method, users logging in with a different language will see the description displayed in their logon language, provided that the corresponding language key has been maintained in the on Inspection Method.

Document Management

Migration required if documents are identified. The conversion scope is limited to the migration of Inspection Method object. No images, or supporting files are included.

Legal Requirement

Not applicable

Special Requirements

Not applicable


Target Design

Inspection Method strictly adheres to the Master Data Standard. The complete information of the tables and key fields that hold the Inspection Method information follows the Master Data Standard document.

The technical design of the target for this conversion approach.

TableFieldData ElementField DescriptionData TypeLengthRequirement
QMTBWERKSQ_METH_PLANTFor inspection methods this plant is the planning plant, in which the inspection method was created in QM.CHAR4R
QMTBPMTNRQPMETHODEName that uniquely identifies an inspection method within a plant.
An inspection method describes how to inspect an inspection characteristic. We can assign an inspection method to a master inspection characteristic or directly to an inspection characteristic in an inspection plan.
CHAR8R
QMTBVERSIONQVERSNRPMVersion Number for inspection MethodCHAR6S
QMTBGUELTIGAB
DATUV
Specifies the start date for the validity period of the Inspection MethodDATS8R
QMTBLOEKZQLOESCHKZIndicates the processing status of the master record; for example, created, released, blocked, marked for deletion.CHAR1C
QMTBSORTFELDQSORTFELDThis field uses the search help to make it easier to find master data records.CHAR40C
DRADDOKARDOKARPart of the document key, which categorizes documents according to their distinguishing features and the organizational procedures which result from them.CHAR3C
DRADDOKTLDOKTLSection of a document which is maintained as an independent document.
Design departments, for example, can use document parts to divide up large documents such as design drawings into pages.
CHAR3C
DRADDOKVRDOKVRNumber which identifies the version of a document.CHAR2C
DRADDOKNRDOKNRDocument NumberCHAR25C
QMTBDUMMY10
This field is used to store information only. The system does not use the contents of this field. Its only purpose is to provide a place to store information that is relevant to an object, such as an inspection method or a master inspection characteristic.CHAR10C
QMTBDUMMY20
This field is used to store information only. The system does not use the contents of this field. Its only purpose is to provide a place to store information that is relevant to an object, such as an inspection method or a master inspection characteristic.CHAR20C
QMTBDUMMY40
This field is used to store information only. The system does not use the contents of this field. Its only purpose is to provide a place to store information that is relevant to an object, such as an inspection method or a master inspection characteristic.CHAR40C
QMTTWERKSQ_METH_PLANTFor inspection methods this plant is the planning plant, in which the inspection method was created in QM.CHAR4R
QMTTPMTNRQPMETHODEName that uniquely identifies an inspection method within a plant.
An inspection method describes how to inspect an inspection characteristic. We can assign an inspection method to a master inspection characteristic or directly to an inspection characteristic in an inspection plan.
CHAR8R
QMTTVERSIONQVERSNRPM_TXTVersion Number for inspection MethodCHAR6S
QMTTSPRACHE
SPRAS
The language key for the inspection method text.CHAR1R
QMTTKURZTEXT

QKURZTEXT

Text up to 40 characters in length that describes the Inspection MethodCHAR40C


Data Cleansing

IDCriticalityError Message/Report DescriptionRuleOutputSource System
1043_001C1Method not released or obsoleteMethod record is flagged for deletion (QMTB-LOEKZ) or has status that is not active. Only active methods should be migrated.Inspection MethodPF2/WP2
1043_002C1Invalid Validity DateValid-from date (QMTB-GUELTIGAB) is in the future.Validity DatesPF2/WP2
1043_003C1Missing Short TextMethod description (QMTT-KURZTEXT) is missing Method TextPF2/WP2
1043_004C1Orphaned Method ReferenceInspection plan characteristic (PLMK) references an inspection method (QMTB) that does not exist or is inactive.Inspection Plan LinkPF2/WP2
1043_005C2Duplicate MethodsMultiple active inspection methods exist with the same Plant + Method ID + Version combination.Inspection MethodPF2/WP2
1043_006C2Missing Long TextsMethod flagged for long text (QMTT-LTEXTKZ) but no lont is text maintained.Long TextPF2/WP2
1043_007C2Invalid Inspector QualificationMethod requires inspector qualification (QMTB-PRFQL) not available in customizing (TQ11).QualificationPF2/WP2



Conversion Process

The high-level process is represented by the diagram below:

The ETL (Extract, Transform, Load) process is a structured approach to data migration and management, ensuring high-quality data is seamlessly transferred across systems. Here’s a breakdown of its key components:

1. Extraction
The process begins with extracting metadata and raw data from source systems, such as Syensqo ECC system (i.e. WP2/PF2) periodically. The extracted data is then staged for transformation.


2. Transformation
Once extracted, the data undergoes cleansing, consolidation, and governance. This step ensures data integrity, consistency, and compliance with business rules. The transformation process includes:
- Data validation to remove inconsistencies.
- Standardization to align formats across datasets.
- Business rule application to refine data for operational use.


3. Loading
The transformed data is then loaded into the target S/4HANA system. 

Data Privacy and Sensitivity

Not applicable


Extraction

Extract data from a source into Syniti Migrate. There are 2 possibilities:

  1. The data exists. Syniti Migrate connects to the source and loads the data into Syniti Migrate. There are 3 methods:
    1. Perform full data extraction from relevant tables in the source system(s).
    2. Perform extraction through the application layer.
    3. Only if Syniti Migrate; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
  2. The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate

The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads

Extraction Run Sheet

Req #Requirement DescriptionTeam Responsible
Extraction Scope Definition- Identify the source systems and databases involved.
- Define the data objects (tables, fields, records) to be extracted.
- Establish business rules for data selection.

Syniti / LTC Data team

Extraction Methodology- Specify the extraction approach (full, incremental, or delta extraction).
- Determine the tools and technologies used.
- Define data filtering criteria to exclude irrelevant records.
Syniti 
Extraction Execution Plan- Establish execution timelines and batch processing schedules.
- Assign responsibilities for extraction monitoring.
- Document dependencies on other migration tasks.
Syniti
Data Quality and Validation- Define error handling mechanisms for extraction failures.Syniti


Selection Screen

Selection Ref ScreenParameter NameSelection TypeRequirementValue to be entered/set
Not applicable



















Data Collection Template (DCT)

A Target-Ready Data Collection Template will be created for all required fields in the QM Inspection Methods, except for fields that require transformation in accordance with the defined transformation rules. Each template will follow the structure and format required by the target S/4HANA Material Master configuration for Quality Management.

TableField NameField DescriptionData TypeLengthRequirementRule

Mapping

QMTBWERKSPlantCHAR4RequiredSpP and P&C will use one central plant (for each of them) to store all QM Master Data, then assign them to plant/materials across the world. Composite will store QM Master Data independently plant by plant. A dedicated Plant per GBU will be created in order to maintain all the QM Master Data within it and to be used for the specific GBU when needed.
P&C (ex-TS + ex-Noveare): QM01
SpP: QM02
Composite: No dedicated plant is required

Copy from DCT


QMTBPMTNRInspection MethodCHAR8RequiredName that uniquely identifies an inspection method within a plant.Copy from DCT
QMTBGUELTIGABValid-From DateDATS8RequiredSpecifies the start date for the validity period of the Inspection MethodCopy from DCT
QMTBLOEKZStatusCHAR1Conditional"If the Inspection Method is maintained, the “Status” field must be filled to reflect its lifecycle—set to “Released” for active use or “Blocked” to prevent assignment in inspection plans.
The following statuses can be used:
Being created
If you create a master record, the system proposes the status ""Being created"" You can, however, change this status. You cannot use master records with this status.
Released
Before you can create a reference to the master record, you must release it by setting the status to ""Released"".
Can no longer be used
If a master record is no longer to be used, you must set the status to ""Can no longer be used"". Master records that are already being used are not affected by this status.
Deletion flag
To delete a master record during the next archiving run, you need to set the status to Deletion flag. A batch program then checks, if references exist to the master record. In addition, it also checks the actual usage and not the usage indicator."
Copy from DCT
QMTBSORTFELDSearch FieldCHAR40ConditionalIf the Inspection Method is maintained, the “Search Field” must be filled with keywords or identifiers—enabling efficient retrieval and matching of inspection methods during task list or characteristic assignment.Copy from DCT
DRADDOKARlinked Document TypeCHAR3ConditionalIf this inspection method is described or integrated with a technical PDF document, here add the link to the corresponding DMS objectCopy from DCT
DRADDOKTLDocument PartCHAR3ConditionalIf this inspection method is described or integrated with a technical PDF document, here add the link to the corresponding DMS objectCopy from DCT
DRADDOKVRDocument VersionCHAR2ConditionalIf this inspection method is described or integrated with a technical PDF document, here add the link to the corresponding DMS objectCopy from DCT
DRADDOKNRDocument NumberCHAR25ConditionalDocument NumberCopy from DCT
QMTBDUMMY10Info field 1CHAR10ConditionalIf the Inspection Method is maintained, “Info Field 1” must be filled with supplementary method details—such as equipment, standards, or notes—supporting clarity and traceability in inspection execution.Copy from DCT
QMTBDUMMY20Info field 2CHAR20ConditionalIf the Inspection Method is maintained, “Info Field 2” must be filled with additional method-specific notes—such as calibration details, environmental conditions, or reference documents supporting inspection consistency.Copy from DCT
QMTBDUMMY40Info field 3CHAR40ConditionalIf the Inspection Method is maintained, “Info Field 3” must be filled with contextual notes—such as sampling strategy, risk classification, or method variations—to support consistent interpretation across plants and users.Copy from DCT
QMTTWERKSPlantCHAR4RequiredSpP and P&C will use one central plant (for each of them) to store all QM Master Data, then assign them to plant/materials across the world. Composite will store QM Master Data independently plant by plant. A dedicated Plant per GBU will be created in order to maintain all the QM Master Data within it and to be used for the specific GBU when needed.
P&C (ex-TS + ex-Noveare): QM01
SpP: QM02
Composite: No dedicated plant is required
Copy from DCT
QMTTPMTNRInspection MethodCHAR8RequiredName that uniquely identifies an inspection method within a plant.Copy from DCT
QMTTSPRACHELanguageCHAR1RequiredThe language key for the inspection method text.Copy from DCT
QMTTKURZTEXTShort TextCHAR40ConditionalIf the Inspection Method is maintained, the “Short Text” field must be filled with a clear, concise description of the method—reflecting its purpose, scope, or technique for quality execution.Copy from DCT
STXHTDOBJECTText ObjectCHAR10RequiredDefault to"QPMETHODE"Default to"QPMETHODE"
STXHTDNAMENameCHAR70RequiredCopy from DCTCopy from DCT
STXHTDIDText IDCHAR4RequiredDefault to"QMTT"Default to"QMTT"
STXHTDSPRASLanguage KeyCHAR1RequiredDefault = EN unless multilingualDefault = EN unless multilingual
STXLCLUSTDText Cluster DataCHAR2000RequiredMust contain QIR long text linesCopy from DCT

Note

Please check the link attached for Layout:

 




  

Extraction Dependencies

Before data extraction can commence, several prerequisite steps and conditions must be met to ensure a smooth and accurate extraction process. These dependencies involve confirming system readiness, validating data structures, and ensuring that appropriate access rights and credentials are in place.

Each step must be clearly defined, assigned to responsible teams, and completed prior to extraction activities. Proper coordination across stakeholders is required to mitigate risks and avoid delays in the migration timeline.

1

Source System Availability

  • Ensure that the source database or application is accessible.
  • Confirm that necessary credentials and permissions are granted

Syensqo IT

2

Data Structure

  • Identify relationships between tables, views, and stored procedures.

Syniti

3

Referential Integrity

  • Ensure dependent records are extracted together.

Syniti

4

Extraction Methodology

  • Define whether extraction is full, incremental, or delta-based.
  • Establish batch processing schedules for large datasets.

Syniti

5

Performance and Scalability Considerations

  • Optimize extraction queries to prevent system overload.
  • Ensure network bandwidth supports data transfer volumes.

Syniti

6

Security and Compliance

  • Adhere to regulatory standards for sensitive information if applicable

Syniti

7

Data cleansing of legacy Material Master - QM View with assigned inspection type data must be completed.

If standardization within the DCT begins using relevant data from PF2 and WP2 before the cleansing is finalized, it is understood that the business will take due diligence to ensure any subsequent delta cleansing is verified and aligned within the DCT.

Business

Transformation

The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:

  1. Perform value mapping and data transformation rules.
    1. Legacy values are mapped to the to-be values (this could include a default value)
    2. Values are transformed according to the rules defined in Syniti Migrate
  2. Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation

Transformation Run Sheet

Item #Step DescriptionTeam Responsible

1

Transformation Scope Definition

- Identify the source and target data structures.

- Define business rules for data standardization.

- Establish data cleansing requirements to remove inconsistencies.

Data Team

2

Data Mapping and Standardization

- Align source fields with target fields.

- Ensure unit consistency (e.g., currency, measurement units)

Data Team

3

Business Rule Application

- Implement data enrichment/collection if applicable

- Apply conditional transformations based on predefined logic/business rules

Data Team

4

Transformation Execution Plan

- Define batch processing schedules.

- Assign responsibilities for monitoring execution.

- Establish error-handling mechanisms

Syniti


Transformation Rules

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic
1PF2/WP2QMTBWERKSPlantS/4 HANAQMTBWERKSPlant

R. Xref from Legacy to S4

SpP and P&C will use one central plant (for each of them) to store all QM Master Data, then assign them to plant/materials across the world. Composite will store QM Master Data independently plant by plant. A dedicated Plant per GBU will be created in order to maintain all the QM Master Data within it and to be used for the specific GBU when needed.
P&C (ex-TS + ex-Noveare): QM01
SpP: QM02
Composite: No dedicated plant is required

2PF2/WP2QMTBPMTNRInspection MethodS/4 HANAQMTBPMTNRInspection MethodR. Copy from source system
3PF2/WP2QMTBVERSIONVersionS/4 HANAQMTBVERSIONVersionS.Internal
4PF2/WP2QMTBGUELTIGABValid-From DateS/4 HANAQMTBGUELTIGABValid-From Date

R.Copy from Source system.

Keep the ECC start date as the S/4 effective-from date

5PF2/WP2QMTBLOEKZStatusS/4 HANAQMTBLOEKZStatus

C. Copy from Source system.
Migrate both status 1 (Being Created) and status 2 (Released) records


6PF2/WP2QMTBSORTFELDSearch FieldS/4 HANAQMTBSORTFELDSearch FieldC. Copy from source system
7PF2/WP2DRADDOKARlinked Document TypeS/4 HANADRADDOKARlinked Document TypeC. Copy from source system
8PF2/WP2DRADDOKTLDocument PartS/4 HANADRADDOKTLDocument PartC. Copy from source system
9PF2/WP2DRADDOKVRDocument VersionS/4 HANADRADDOKVRDocument VersionC. Internal
10PF2/WPF2DRADDOKNRDocument NumberS/4 HANADRADDDOKNRDocument Number

C. Copy from source system

(DRAD-DOKOB=QMTBDOC)

11PF2/WP2QMTBDUMMY10Info field 1S/4 HANAQMTBDUMMY10Info field 1C. Copy from source system
12PF2/WP2QMTBDUMMY20Info field 2S/4 HANAQMTBDUMMY20Info field 2C. Copy from source system
13PF2/WP2QMTBDUMMY40Info field 3S/4 HANAQMTBDUMMY40Info field 3C. Copy from source system
14PF2/WP2QMTTWERKSPlantS/4 HANAQMTTWERKSPlant

R. Xref from Legacy to S4

SpP and P&C will use one central plant (for each of them) to store all QM Master Data, then assign them to plant/materials across the world. Composite will store QM Master Data independently plant by plant. A dedicated Plant per GBU will be created in order to maintain all the QM Master Data within it and to be used for the specific GBU when needed.
TS: QM01
SpP: QM02
Composite: No dedicated plant is required

15PF2/WP2QMTTPMTNRInspection MethodS/4 HANAQMTTPMTNRInspection MethodR. Copy from source system
16PF2/WP2QMTTVERSIONVersionS/4 HANAQMTTVERSIONVersionS.Internal
17PF2/WP2QMTTSPRACHELanguageS/4 HANAQMTTSPRACHELanguageR. Copy from source system
18PF2/WP2QMTTKURZTEXT
Short Text
S/4 HANAQMTTKURZTEXT
Short Text
C. Copy from source system
19PF2/WP2STXHTDOBJECTText ObjectS/4HANASTXHTDOBJECTText ObjectDefault to"QPMETHODE"
20PF2/WP2STXHTDNAMEText NameS/4HANASTXHTDNAMEText Name The STXH table data will be migrated as-is from the current system to S/4HANA, with no modifications, ensuring consistency and traceability of existing records.
TDNAME = MANDT+ WERKS + PMTNR + VERSION + SPRACHE(Language)
21PF2/WP2STXHTDIDText IDS/4HANASTXHTDIDText ID The STXH table data will be migrated as-is from the current system to S/4HANA, with no modifications, ensuring consistency and traceability of existing records.
Default to 'QMTT'
22PF2/WP2STXHTDSPRASLanguage KeyS/4HANASTXHTDSPRASLanguage KeyThe STXH table data will be migrated as-is from the current system to S/4HANA, with no modifications, ensuring consistency and traceability of existing records.
23PF2/WP2STXHTDVERSIONVersion Number of TextS/4HANASTXHTDVERSIONVersion Number of TextThe STXH table data will be migrated as-is from the current system to S/4HANA, with no modifications, ensuring consistency and traceability of existing records.
24PF2/WP2STXLCLUSTDText Line (Compressed)S/4HANASTXLCLUSTDText Line (Compressed)The STXL table data will be migrated as-is from the current system to S/4HANA, with no modifications, ensuring consistency and traceability of existing records.
24PF2/WP2STXLTDOBJECTText Object (Reference from STXH)S/4HANASTXLTDOBJECTText ObjectDefault to"QPMETHODE"
26PF2/WP2STXLTDNAMEText NameS/4HANASTXLTDNAMEText Name The STXH table data will be migrated as-is from the current system to S/4HANA, with no modifications, ensuring consistency and traceability of existing records.
TDNAME = MANDT+ WERKS + PMTNR + VERSION + SPRACHE(Language)


Transformation Mapping

Mapping Table NameMapping Table Description
PlantMapping of legacy Plants to To-Be Plants in S/4HANA

Transformation Dependencies

List the steps that need to occur before transformation can commence
Item #Step DescriptionTeam Responsible

1

Value Mappings are according to the latest design - <List of Value Mappings>

SyWay Data Team


Pre-Load Validation

Project Team

Completeness

TaskAction

Compare Data Counts

  1. Verify row counts between source and target databases.
  2. Identify missing or duplicated records.

Validate the mandatory fields

Validate there is value for all the mandatory fields

Validate Primary Keys and Unique Constraints

  1. Check for duplicate or missing primary key values.
  2. Ensure unique constraints are maintained.

Test Referential Integrity

Confirm dependent records exist in related tables


Accuracy

TaskAction

Validate the transformation

Validate the fields which require transformation have the value after transformation instead of the original field value

Check Data Consistency

  1. Compare field values across systems
  2. Validate data formats and structures

Business

Completeness

TaskAction

Compare Data Count

  1. Verify row counts between source and target databases.
  2. Identify missing or duplicated records.
Review populated templates for missing or incorrect valuesUse checklists to verify completeness and correctness before submission

Accuracy

TaskAction

Conversion Accuracy

Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/ mapping rules (and signed-off DCT data).


Load

The load process includes:

  1. Execute the automated data load into target system using load tool or product the load file if the load must be done manually
  2. Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation

Load Run Sheet

Item #Step DescriptionTeam Responsible

1

Load Scope Definition

- Identify the target system and database structure.

- Define data objects (tables, fields, records) to be loaded.

- Establish business rules for data validation.

Data team

2

Load Methodology

- Specify the loading tools and technologies (Migration Cockpit, LSMW, custom loading program).

Syniti 

3

Data Quality and Validation

- Ensure data integrity checks (null values, duplicates, format validation).

- Perform pre-load validations to verify completeness.

- Define error handling mechanisms for load failures

Syniti 

4

Load Execution Plan

- Establish execution timelines and batch processing schedules.

- Assign responsibilities for monitoring execution.

- Document dependencies on other migration tasks

Syniti

5

Logging and Reporting

- Maintain detailed logs of loading activities.

- Generate summary reports on loaded data volume and quality.

- Define escalation procedures for errors

Syniti


Load Phase and Dependencies

The Inspection Methods will be loaded in the pre-cutover (PreCutover 4 phase) period.

Before loading, it will have dependency on the following configuration and data objects in the S/4 HANA.

Configuration


Item #Configuration Item
1MARA - General Material Data
2MARC - Material Plant data
3T001W - Plants/Branches

Conversion Objects

Object #Preceding Object Conversion Approach
2009Material Master (QM View must exist before Inspection methods)

Error Handling

Error TypeError DescriptionAction Taken
1Material Master (QM View) does not exist for the plant/material combinationEnsure that the Material Master with QM View is created and valid before plan migration


Post-Load Validation

Project Team

Completeness

TaskAction

Validate Record count in the backend

Validate all tables with prefix “QMTB” has the same records as the loading file

Display Records

Pick up a few random Inspection Methods, and run t-code: QS33 to validate the Material Listing and Exclusions can be displayed without any error.

Perform Source-to-Target Comparisons

  1. Validate that migrated data matches source records.
  2. Check for discrepancies in numerical values, text fields, and timestamps

Validation reports


Accuracy

TaskAction

Execute Sample Queries and Reports

  1. Run queries to validate business logic.
  2. Generate reports to compare expected vs. actual results

Conduct Post-Migration Reconciliation

Generate reports comparing pre- and post-migration data.


Business

Post-load validation is a critical step in data migration, ensuring that transferred data is accurate, complete, and functional within the target system.

1. Ensuring Data Integrity
After migration, data must be consistent with its original structure. Post-load validation checks for missing records, incorrect mappings, and formatting errors to prevent discrepancies.
2. Business Continuity
Faulty data can disrupt operations, leading to financial losses and inefficiencies. Validating post-load data ensures that applications function as expected, preventing downtime.
3. Error Detection and Resolution
By validating data post-migration, businesses can detect anomalies early, reducing the cost and effort required for corrections


Completeness

TaskAction
Perform Source-to-Target Comparisons
  1. Validate that migrated data matches source records.
  2. Check for discrepancies in numerical values, text fields, and timestamps
Conduct Post-Migration ReconciliationGo through reports comparing pre- and post-migration data.

Accuracy

TaskAction

Perform Manual Testing

Conduct manual spot-checks for additional assurance.


Key Assumptions

  • Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
  • Inspection Methods is in scope based on data design and any exception requested by business.
  • Data cleansing has met the required percentage threshold for the specified mock cycle and all preparation activities have been completed.
  • Data entries in DCT are target-ready data unless a specific transformation rule is stated for that field in the transformation rules.



See also


Change log

Workflow history