The purpose of this document is to define the conversion approach to migrate the balance of Capex WBS from legacy system to S/4HANA.
All the financial transactions posted of all open WBS Elements as at 30 June 2028 (for Go live 1 July 2028) and as at 31 Dec 2028 (for Go live 1 Jan 2029) in the source systems (PF2 and WP2). All these transactions will be totaled into the one single value and then be posted to the relevant WBS Elements in S/4HANA. The approach will also run SAP settlement to the relevant Asset Under Construction.
The scope of this document covers the approach for converting active Capex WBS element from Legacy Source Systems into S/4HANA.
All the relevant WBS Elements (after applying the approved relevancy rules) open as at end of last month before go live that have received primary and secondary transactions posted to the cost elements within the WBS Elements
The scope of this document will therefore extract the settlement transactions from each individual WBS Element to provide a base for posting to the S/4HANA WBS Elements as at end of last month before go live. The total of the transactions will be used to compare to the balance in the Asset Under Construction that is used for settlement. The total of the settlement transactions will also be reconciled against the total costs posted to the WBS Element to ensure that all costs have been captured. Therefore, the scope will extend to the reconciliation of the legacy Asset Under Construction values
Below are the list of AUC classes for SyWay:
The data from legacy system includes:
The data from legacy system excludes:
There will be 3 SAP boxes:
a. CUI box (US, GB, DE)
b. China box
c. ROW (Rest of the World) box
Please refer to file "Entreprise Structure Catalog" to see which company codes fall under which SAP boxes.
In terms of data migration, below is the guideline:
- Non CUI objects : Migration to US system by Syniti
- CUI objects : Manual cleansing/separate migration cockpit (Syniti is not certified)
List of source systems and approximate number of records
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
| Legacy systems | Project level exclusions based on following relevancy rules:
| S/4HANA | ||
| Legacy systems |
Exceptions:
| S/4HANA | ||
| DCT | Where legal entities do not use SAP to record their projects, the DCT will be used to collect the balance of Capex WBS element data. | TBC | S/4HANA | TBC |
PF2 and WP2 | Extraction of the Sender Credit values from settlement that uses primary cost elements for settlement (Table COSP) | ??? | S/4HANA | |
PF2 and WP2 | Extraction of the Sender Credit values from settlement that uses secondary cost elements for settlement (Table COSS) | ??? | S/4HANA |
N/A
N/A
N/A
Specify any special requirements or considerations that may impact the data conversion process based on specific locations, regulatory compliance or system limitations. Clearly outline any regional or localization requirements such as country-specific data formats, legal reporting obligations or industry standards that must be adhered to (e.g., localization rules for countries like China).
If the data conversion involves third-party systems or external data sources, such as Icertis, describe any additional requirements related to data mapping, transformation logic, validation rules or security measures that must be followed.
There are two types of costs in the WBS Elements:
There is no need to replicate the postings that have occurred in the source system. The value that has been settled to the receiver object can be used to post with a selected General Ledger account. The settlement can then also use this account to clear the balance at the level. The offset General Ledger account will still be used to balance the journal entries.
The technical design of the target for this conversion approach.
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| MARA | MATNR | MATNR | Material Number | CHAR | 18 | Mandatory |
All data cleansing should take place in the data source system as defined in this document, unless system limitations prevent it.
There will be cleansing required outside of that handled in the following DCA’s
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
The high-level process is represented by the diagram below:
Summarize High-Level Process. Include diagrams, where applicable. Include information supporting details of Extract, Transform and Load specific to the Data Object

Extract data from a source into Syniti Migrate. There are 2 possibilities:
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
| Req # | Requirement Description | Team Responsible | ||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | Extract data from source systems based on the current relevancy rules that apply to the Project and WBS Element Master Data. For each relevant WBS Element extract the object number from source systems with WBS Elements from table PRPS. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 2. | The following tables will be used to extract the settlement data:
To ensure that all costs have been collected via these tables (COSP & COSS), run a report (transaction code CJI3) to extract all the costs posted to the WBS Element/s to reconcile against the totals extracted from table COSP & COSS. Compare and agree the reconciliation values before progressing further to the next steps. For each open Project, confirm that the final balance is zero which will ensure that the settlement costs represent all the postings (debit and credit) within the Project by WBS Element. Extract the transactions by business transaction type. Use table AUFK to reconcile the settlement costs against actual posting extracts (extract by year by period by settlement transaction for each Project. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 3. | Go to source systems (PF2 and WP2) Primary Costs Total (Table COSP)
Go to source system (PF2 and WP2) Secondary Costs Total (Table COSS)
From the above, system will generate report as below. The report will need to be summarized by object number by total for all the fiscal years.
| Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 4. | Step #3 provides what needs to be posted for each WBS Element. These can be split across cost elements, but the proposal is to use one Cost Element for both posting and settlement (GL account TBD) | Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 5. | Extract the Settlement Rule object from table COBRB in source systems (PF2 and WP2) to find the settlement objects for the above project.
System will provide a report as below that will include the following fields:
Extract the asset numbers from this report. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 6. | Extract the fixed asset values from table ANEP in source systems (PF2 and WP2) to check what has been posted to the Asset under Construction (AUC).
System will generate as below:
This report will need to be summarized by Object Number by total for all months. Check against the WBS Element postings before loading into S/4HANA.
| Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 7. | Run transaction code S_ALR_87011963 (Asset Balances report) for all AUC assets within the relevant Company Code. Check each individual asset balance before making any posting to a WBS Element. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||
| 8. | Once the overall balance has been agreed above, posting will be required and run settlement (CJ8G) | Data Team |
| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
| N/A |
A DCT will be required to collect the transactions posted to the WBS Elements/Project that are not in PF2 and WP2 but have been selected in the DCT for master data for Projects and WBS Elements – CAPEX.
Target Ready Data Collection Template will be created for Data Object data with exception of some fields which require transformation as mentioned in the transformation rule.
<Object> DCT Rules
| Field Name | Field Description | Rules |
ACDOCA-POSID | WBS Element | To be prepopulated based on WBS element load with new WBS number. |
ACDOCA-WSL | Amount | For previous year actuals, total all transaction values and post as a single transaction with the posting date of the 31 Dec of the previous year. For current year actuals, total all transaction values by month and post as a single transaction with the posting date of the last month end of each month |
ACDOCA-BUDAT | Posting Date | For previous year actuals, total all transaction values and post as a single transaction with the posting date of the 31 Dec of the previous year. For current year actuals, total all transaction values by month and post as a single transaction with the posting date of the last month end of each month |
ACDOCA-POPER | Posting Period | Enter Posting Period. This should default in the DCT based on Posting Date |
ACDOCA-GJAHR | Fiscal Year | Enter fiscal year. This should default based on Posting Date |
ACDOCA-BLART | Document Type | Use Document Type “SA” (TBC) or "UE"? |
ACDOCA-BLDAT | Document Date | Same as Posting Date |
ACDOCA-BKTXT | Header Text | TBC |
ACDOCA-RBUKRS | Company Code | Enter Company Code |
ACDOCA-RACCT | GL Account | Default to GL XXXXX (TBC) |
ACDOCA-RWCUR | Currency | Enter Local Currency. Group currency will be calculated. |
ACDOCA-SGTXT | Item Text | Migration transaction TBC |
List the steps that need to occur before extraction can commence
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1. | All CAPEX WBS element cleansing has been completed in PF2 and WP2 | Business |
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1. | In ADMM, select Object 9031 and launch this to execute transformation | Syniti Team |
| 2. | Perform transformation for all relevant WBS Elements. Legacy WBS Element is mapped to S/4HANA WBS elements in mapping table. | Syniti Team |
| 3. | Generate Pre-Load reports in ADMM for the extracted WBS Element amounts. | Syniti Team |
| 4. | Validate the transformed file as part of pre-load validation, raise data defects or provide the pre-load sign-off. | Business |
| 5. | Analyze and resolve any pre-load defects logged by business. | Data Team |
Transformation Rules
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1. | PF2 and WP2 | COSP | OBJNR | Object Number | S/4HANA | ACDOCA | POSID | WBS Element Number | COSP Object Number will identify the WBS Element from PF2 and WP2 (PRPS table) which will map to the S/4HANA WBS Element identified in WBS mapping table. |
| 2. | PF2 and WP2 | COSS | OBJNR | Object Number | S/4HANA | ACDOCA | POSID | WBS Element Number | COSS Object Number will identify the WBS Element from PF2 and WP2 (PRPS table) which will map to the S/4HANA WBS Element identified in WBS mapping table. |
| 3. | PF2 and WP2 | COSP | BUKRS | Company Code | S/4HANA | ACDOCA | RBUKRS | Company Code | Mapping table from legacy company code to S/4HANA Company Code. |
| 4. | PF2 and WP2 | COSS | BUKRS | Company Code | S/4HANA | ACDOCA | RBUKRS | Company Code | Mapping table from legacy company code to S/4HANA Company Code. |
| 5. | PF2 and WP2 | PRPS | PRCTR | Profit Center | S/4HANA | ACDOCA | PRCTR | Profit Center | Map Legacy Profit Centre to the S/4 HANA Profit Centers. |
| 6. | PF2 and WP2 | COSP | GJAHR | Fiscal Year | S/4HANA | ACDOCA | GJAHR | Fiscal Year | |
| 7. | PF2 and WP2 | COSS | GJAHR | Fiscal Year | S/4HANA | ACDOCA | GJAHR | Fiscal Year | |
| 8. | N/A | N/A | N/A | N/A | S/4HANA | ACDOCA | RACCT | Account Number | Use GL Account to post to the new WBS Element. TBC |
| 9. | PF2 and WP2 | COSP | WOGxx | Value Obj Curr | S/4HANA | ACDOCA | POPER | Posting Period | |
| 10. | PF2 and WP2 | COSS | WOGxx | Value Obj Curr | S/4HANA | ACDOCA | POPER | Posting Period | |
| 11. | N/A | S/4HANA | ACDOCA | BUDAT | Posting Date | ||||
| 12. | N/A | S/4HANA | ACDOCA | BLDAT | Document Date | ||||
| 13. | PF2 and WP2 | COSP | WOGxx | Value Obj Curr | S/4HANA | ACDOCA | WSL | Amount in Transaction Currency | xx represents all periods for previous years. Value type (COSP-WRTTP) must be “4” and Dr/Cr Indicator (COSP-BEKNZ) set to “O - Special: Sender credit from settlement”. Once the data is collected the signage must be changed prior to posting. As most of the settlement amounts will be a negative amount, this value must be changed to a positive amount before posting back to the S/4HANA WBS Element. If the settlement amount is a positive value, it must be changed to a negative value. Logic will be required to determine the posting period from the field name WOGxx, with xx being the posting month. E.g. 01,02,03 |
| 14. | PF2 and WP2 | COSS | WOGxx | Value Obj Curr | S/4HANA | ACDOCA | WSL | Amount in Transaction Currency | xx represents all periods for previous years. Value type (COSP-WRTTP) must be “4” and Dr/Cr Indicator (COSP-BEKNZ) set to “O - Special: Sender credit from settlement”. Once the data is collected the signage must be changed prior to posting. As most of the settlement amounts will be a negative amount, this value must be changed to a positive amount before posting back to the S/4HANA WBS Element. If the settlement amount is a positive value, it must be changed to a negative value. Logic will be required to determine the posting period from the field name WOGxx, with xx being the posting month. E.g. 01,02,03 |
| 15. | N/A | S/4HANA | ACDOCA | BLART | Document Type | Default to UE? TBC | |||
| 16. | N/A | S/4HANA | ACDOCA | USNAM | User Name | Default to data migration user ID | |||
| 17. | N/A | S/4HANA | ACDOCA | SGTXT | Item Text | Specify source WBS Element | |||
| 18. | PF2 and WP2 | S/4HANA | ACDOCA | BKTXT | Header Text | Default to “Data Object 9031” | |||
| 19. | PF2 and WP2 | S/4HANA | ACDOCA | RACCT | Offsetting GL Account | Use the Offset GL Account used for GL Balance migration - (TBC). This will be used for migration for transactions that will eventually settle to AUC |
| Mapping Table Name | Mapping Table Description |
|---|---|
Company code | Mapping of legacy company code to S/4HANA company code |
Cost Centre | Map legacy Cost Centres to S/4HANA Cost Centres |
GL Accounts | Map legacy GL Accounts to S/4HANA GL Accounts |
Profit Centre | Map legacy Profit Centre to S/4HANA Profit Centre |
Fixed Asset Number | Map legacy Fixed Asset number to S/4HANA Fixed Asset number for CAPEX WBS Elements that have changed status to TECO |
WBS Elements | Map legacy WBS Elements to S/4HANA WBS Elements |
Currency | Map legacy currency to S4/HANA currency code |
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1. | Ensure all the fields that require value mapping, as stipulated in Section "Mapping tables", have the correct values mapped. | Data Team |
The following pre-load validations will be performed by Project Team.
This is to validate the total transactional movement in each open WBS Element. Validate the financial movement of all transactions excluding settlement transactions by WBS Element by Cost Element (GL Account) for the open WBS Elements as the closing balance.
| Task | Action |
|---|---|
Verify Counts | Data team to verify the load count is the same as per identified data from Primary Cost Total COSP file and Secondary Cost Total COSS file. |
Validate | Validate that the extracted values from both tables agree with the total transaction costs excluding settlement for each individual WBS Element |
| Task | Action |
|---|---|
| Validate | Validate that the extracted values from both tables agree with the total transaction costs excluding settlement for each individual WBS Element |
| Validate | Validate that the extracted values are identical to those values settled to the Receiver. |
| Reconcile | Total by Asset number to compare to the WBS Element value to be posted. The value to be posted against the WBS Element must agree with the value shown for the relevant Asset Under Construction. See section "Extraction run sheet for legacy WBS element settling to AUCs. |
| Task | Action |
|---|---|
| Verify counts | Business will use the preload report to validate the number of WBS Elements that will migrate values. |
| Task | Action |
|---|---|
| Validate | Validate that the extracted values are identical to those values posted to the WBS Element |
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1. | Ensure Pre-Load signoffs are obtained. | Data Team |
| 2. | Load a small number of records to verify that the process is stable and will load all records as expected. | Syniti Team |
| 3. | If the above is successful, load all remaining records. | Syniti Team |
| 4. | If the above is unsuccessful, review errors and determine whether the error is data related, or system related. | Data Team |
| 5. | After correction, load corrected file or run corrected program to load data. | Syniti Team |
| 6. | Prepare report for Post Load Validation. | Syniti Team |
| 7. | Validate Post Load report. | Business |
Load Phase and Dependencies
Identify the phase as to “when” the load for this object will occur. <Pre-Cutover, Cutover, Post Cutover> and list the steps that need to occur before the load can commence
List the Configurations required before loading can commence
| Item # | Configuration Item |
|---|---|
| 1. | Asset Classes |
| 2. | Cost Element Groups |
| 3. | Settlement Profiles |
| 4. | Allocation Structures |
| 5. | Previous Asset Fiscal Year to be open |
| 6. | Settlement cost elements used for settlement available in all company codes in scope |
| 7. | Number ranges for settlement documents to be set up. This is manual config. |
| Object # | Preceding Object Conversion Approach |
|---|---|
| 1024 | Project Definition (CAPEX, OPEX) |
| 1025 | Project Text & Documents (attachments) |
| 1026 | WBS - CAPEX, OPEX, Statistical |
The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management
| Error Type | Error Description | Action Taken |
|---|---|---|
| Configuration | Document type does not exist in S/4HANA | Engage Functional team to fix the error in the system |
| Task | Action |
|---|---|
| Verify counts | Data team to verify the load count is the same as per identified data from Pre Load file |
| Task | Action |
|---|---|
| Verify values | Ensure the Pre-Load report values are the same as in the Post Load Report. These values have to be verified before settling the costs to the AUCs. |
After validating the WBS Element transaction movements for count and accuracy, run settlement. This will provide balances to the AUCs.
AUC master will be created automatically once the WBS status is changed from CRTD (Created) to REL (Released) status.
Transaction code CJ88 will be used to settle all the WBS Element costs to their respective settlement objects. For those that are settling to the AUCs, a reconciliation must be done to compare the AUCs in the legacy system to those that are now in S/4HANA. Table ANLC will be used for this comparison.
The FA previous fiscal year cannot be closed until the AUC reconciliation for the previous year is completed.
| Task | Action |
|---|---|
Verify Counts | Business to verify the load count is the same as per identified data from Post Load Report. |
| Task | Action |
|---|---|
| Verify values | Ensure the Post Load report values are exactly the same as in the Pre Load report. These values have to be verified before settling the costs to the AUCs. |
Appendix:
Reconciliation process for Assets under Construction (AUC):
| Step | Description | Team responsible | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1. | Identify all AUC asset classesUse SAP Table ANKA – Asset Classes: General Data to identify all the AUC Asset Classes | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2. | Identify all assets under the AUC Asset ClassesApply the results from the above table to identify all assets in legacy systems in table ANLA that are classified as Assets Under Construction. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3. | Identify all the above Assets Under Construction that have a previous year balance.The AUC may be restricted to only the ones with balances. Use table ANLC to gather year end balances. When running the report in Table ANLC it must run by Company Code by selected asset number. If it is run by asset number alone, all assets from across all regions will be selected. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
4. | Identify all the above Assets Under Construction that have a current year balance.Reconcile the results from the above report to identify any new AUC’s that may have been created in the current year. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5. | Identify the monthly movements of all the above Assets Under Construction that have a previous or current year balanceUse table ANEP to extract all the monthly movements | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 6. | This table shows all the fields that are to be extracted:
| Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 7. | Identify from which cost object the Asset Under Construction received financial postingsApply the asset number and company code to this table to receive the results. This will provide the cost object that will require the primary financial postings.
Explanation of the above fields:
This will provide the Object Number from which we can identify the real WBS Element in Table PRPS or the Internal Order number in table AUFK. | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 8. | Settle the cost object financial postings to the new Asset Under ConstructionFrom there, these financial postings can be settled into the new S/4HANA AUC. The new AUC will be created when the cost object is released (from CRTD to REL). | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 9. | Identify the cost object to which the settlement rule applies.Use table COBRB restricted to the WBS Elements selected above | Data Team | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 10. | Identify the internal and external financial postings in each WBS Element.Use tables COSP and COSS to collect the monthly movement by WBS Element by cost element by object currency. | Data Team |
Any additional key assumptions.
Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.