The purpose of this document is to define the conversion approach to create Maintenance Strategy in S/4 HANA.
Legacy Plant Maintenance Maintenance Strategy is using a diverse range of formats across the different systems. There are instances where the same Maintenance Strategy is duplicated within and across sources, with informal words. This results in data inconsistency. As per SyWay design, Maintenance Strategy will be standardized.
The scope of this document covers the approach for converting active Maintenance Strategy from Legacy Source Systems into S/4HANA following the Maintenance Strategy Master Data Design Standard.
The data from legacy system includes:
All legacy strategies & packages assigned to valid legacy
The data from legacy system excludes:
List of source systems and approximate number of records
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
PF2, WP2 | An initial extract will be provided to business to evaluate. Additional data/records may be required and these will be constructed via DCT. Enrichment of in-scope data may be required and will be added via transformation rules (business/technical). | 352 | S/4HANA | 352 |
Maintenance Strategy description will be made available in English.
Multi language is supported for Maintenance Strategy. Login via a different language will have its description displayed in the logon language if the language key is maintained in the Maintenance Strategy.
Not Applicable
Not Applicable
Not Applicable
With Functional input, document the technical design of the target fields that are in the scope of this document.
The technical design of the target for this conversion approach.
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| T351 | STRAT | STRAT | Maintenance Strategy | CHAR | 6(0) | |
| T351T | SPRAS | SPRAS | Language Key | LANG | 1(0) | Config Table: T002 |
| T351T | KTEXT | TXWSTRA | Description of maintenance strategy | CHAR | 30(0) | |
| T351 | ZEIEH | DZEIEH | Unit for the performance of maintenance tasks | UNIT | 3(0) | Config Table: T006 |
| T351 | LEIEH | LEIEH | Maintenance strategy activity unit | UNIT | 3(0) | Config Table: T006 |
| T351 | ZYK1G | DZYK1_GES | Total cycle duration of a maintenance strategy | FLTP | 16(16) | |
| T351 | ZYK2G | DZYK2_GES | Total cycle duration of a maintenance strategy | FLTP | 16(16) | |
| T351 | ZYK1K | DZYK1_GGT | Smallest step between two maintenance packages | FLTP | 16(16) | |
| T351 | ZYK2K | DZYK2_GGT | Smallest step between two performance-based MaintPackages | FLTP | 16(16) | |
| T351 | ANZP1 | ANZPAK1 | Number of MaintPackages in the MaintStrategy | NUMC | 2(0) | |
| T351 | ANZP2 | ANZPAK2 | Number of MaintPackages in the MaintStrategy (peformance) | NUMC | 2(0) | |
| T351 | TOLE1 | TOLERPLUS | Tolerance for Late Completion (%) | NUMC | 3(0) | |
| T351 | TOLE2 | TOLERNEG | Tolerance for Early Completion (%) | NUMC | 3(0) | |
| T351 | VERS1 | VERSCHPLUS | Shift Factor for Late Completion | NUMC | 3(0) | |
| T351 | VERS2 | VERSCHNEG | Shift Factor for Early Completion | NUMC | 3(0) | |
| T351 | TERMK | TERMKNZ | Scheduling indicator | CHAR | 1(0) | |
| T351 | HORIZ | HORIZONT | Call horizon for maintenance plan calls | NUMC | 3(0) | |
| T351 | HORIZ_QUALIFIER | EAM_CC_CALLHORIZON_QUALIFIER | Calculation Type of Call Horizon | CHAR | 1(0) | |
| T351 | FABKL | FABKL | Factory calendar key | CHAR | 2(0) | Config Table: TFACD |
| T351 | AUTHGR | EAM_AUTH_GROUP | Authorization Group | CHAR | 4(0) | Config Table: T370B |
All data cleansing should take place in the data source system as defined in this document, unless system limitations prevent it.
If data cleansing is managed outside of the source system (e.g. Syniti Migrate, 3rd Party Vendor, DCT), the necessary documentation must be produced and appended to this deliverable for sign-off.
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
| 1 | C1 | Description must not be blank | KTEXT is blank | STRAT, KTEXT | PF2, WP2, DCT |
| 2 | C1 | Unit for the performance of maintenance tasks not in T006 | ZEIEH is not in T006 | STRAT, KTEXT, ZEIEH | PF2, WP2, DCT |
Informal Words **
Group 1 | Group 2 | Group 3 | Group 4 | Group 5 |
|---|---|---|---|---|
*DNU | Delete | donot | Formerly | Old # |
.. | Deletion | DONT USE | From | Old[ ] |
/ | DELISTED | DON'T USE | Incorrect | PLEASE USE |
? | Discontinued | Dup Use | Invalid | Pls Use |
@ | Disposable | DUPLICATE | New | Previously |
^ | DNU | -DUPLICATE | NOT ACTIVE | Replace |
+ | Do Not | DUPLICATION | not in use | Replaced |
++ | Do Not Re | Duplicidad | Not Used | RESERVED |
£ | Do Not Sell | Duplikat | NOT VALID | Retired |
Defective | Do Not Use | Former | Obsolete | ZZDEL |
The high-level process is represented by the diagram below:

For sites that are not on SAP-PF2 and WP2 systems, collection will be done manually in the data collection template.
The high-level process for DCT is represented by the diagram below:

Syniti will extract data from source system based on relevancy rule. This is done only ONCE at the start of the project.
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
| Req # | Requirement Description | Team Responsible |
|---|---|---|
1 | Syniti will extract data from source system based on relevancy rule. This is done only ONCE at the start of the project. | Syniti |
2 | The legacy data will then be used in Syniti Data construction page. | Syniti |
Selection Screen
If applicable, this section will give the details on any selection screen parameters, including the parameter type, that are required to be entered to ensure consistent data extracts.| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
Not Applicable |
Maintenance Strategy DCT Rules
| Field Name | Field Description | Rule |
|---|---|---|
| LegacySTRAT | Legacy Strategy | Mandatory(Key) |
| LegacyKTEXT | Legacy Description | Mandatory |
| LegacyZEIEH | Legacy Unit for the performance of maintenance tasks | Mandatory |
| STRAT | Strategy | S4/HANA value |
| KTEXT | Description | S4/HANA value |
| ZEIEH | Unit for the performance of maintenance tasks | Values must exist in config table T006 |
| LegacyHORIZ | Legacy Call horizon for maintenance plan calls | |
| LegacyHORIZ_QUALIFIER | Legacy Calculation Type of Call Horizon | |
| LegacyLEIEH | Legacy Maintenance strategy activity unit | |
| LegacyZYK1G | Legacy Total cycle duration of a maintenance strategy | |
| LegacyZYK2G | Legacy Total cycle duration of a maintenance strategy | |
| LegacyZYK1K | Legacy Smallest step between two maintenance packages | |
| LegacyZYK2K | Legacy Smallest step between two performance-based MaintPackages | |
| LegacyANZP1 | Legacy Number of MaintPackages in the MaintStrategy | |
| LegacyANZP2 | Legacy Number of MaintPackages in the MaintStrategy (performance) | |
| LegacyTOLE1 | Legacy Tolerance for Late Completion (%) | |
| LegacyTOLE2 | Legacy Tolerance for Early Completion (%) | |
| LegacyVERS1 | Legacy Shift Factor for Late Completion | |
| LegacyVERS2 | Legacy Shift Factor for Early Completion | |
| LegacyTERMK | Legacy Scheduling indicator | |
| LegacyFABKL | Legacy Factory calendar key | |
| LegacyAUTHGR | Legacy Authorization Group |
List the steps that need to occur before extraction can commence
| Item # | Step Description | Team Responsible |
|---|---|---|
Not Applicable |
The legacy data is maintained in Syniti Data Construction page. All mapping is performed in Syniti Data Construction page.
Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Obtain DCT Sign-off from Business | SyWay A2D Data Team |
2 | <Add steps from Syniti Migrate here> | SyWay A2D Data Team |
3 | Review and Validate Error and Preload Reports | SyWay A2D Data Team |
4 | Generate Load Files | SyWay A2D Data Team |
Transformation Rules
All transformation and mapping is performed in Syniti Data Construction page.
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| Mapping Table Name | Mapping Table Description |
|---|---|
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Ensure DCT completeness | Business & SyWay A2D Data Team |
2 | T006 configuration must be completed | Business & SyWay A2D Data Team |
| Task | Action |
|---|---|
Verify Record Count | SyWay A2D Data Team to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets. |
| Task | Action |
|---|---|
Conversion Accuracy | SyWay A2D Data Team to verify that all fields below meet pass the checks:
|
Review Error Reports | Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data. |
| Task | Action |
|---|---|
Verify Record Count | Business Data Owner/s to verify that the total number of relevant records from the the DCT is equal to the total number of records in the Preload and Load Sheets. |
| Task | Action |
|---|---|
Conversion Accuracy | Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules (and signed-off DCT data). |
The load process includes:
| Item # | Step Description | Team Responsible |
|---|---|---|
Load Phase and Dependencies
Identify the phase as to “when” the load for this object will occur. <Pre-Cutover, Cutover, Post Cutover> and list the steps that need to occur before the load can commence
List the Configurations required before loading can commence
| Item # | Configuration Item |
|---|---|
| 1 | T006 - Units of Measurement details |
| Object # | Preceding Object Conversion Approach |
|---|---|
| list the exact title of the conversion object of only the immediate predecessor – this will then confirm the DDD (Data Dependency Diagram) | |
The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management
| Error Type | Error Description | Action Taken |
|---|---|---|
| Task | Action |
|---|---|
Verify Count | SyWay A2D Data Team to verify the record count created in target S/4 HANA by accessing post load reports in dspMigrate or standard reports from S/4 HANA. |
Verify Logs | Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.). |
| Task | Action |
|---|---|
Conversion Accuracy | SyWay A2D Data Team to verify that the Maintenance Strategy data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA. |
| Task | Action |
|---|---|
Verify Count | Download Post Load Reports from dspMigrate and verify that the record count loaded in the target S/4 HANA is the same count as of the endorsed load file. |
| Task | Action |
|---|---|
Conversion Accuracy | Verify that the Maintenance Strategy data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA. |
Any additional key assumptions.
Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.