Status

Owner
StakeholdersThe business stakeholders involved in making, reviewing, and endorsing this decision. Type @ to mention people by name

Issue

The purpose of this document is to describe the Delegation of Authority (DOA) feature as it exists across the following platforms: SAP SuccessFactors, SAP Ariba, Salesforce, and Icertis. It outlines how each system implements DOA, including its core functionality, configuration options, limitations, and use cases.


Recommendation

Recommended approach is option A, i.e., DOA matrix and Framework in S4 HANA. 


Background & Context

The DOA matrix will be governed by the executive leadership team and the approved group controller or designate.

Employee Organization data will be used to determine DOA Approval. 


Assumptions

Clearly describe the underlying assumptions which informed or limited the choices available, or impacted the decision: cost, schedule, regulatory requirements, business drivers, country footprint, technology, etc. Include links as necessary. This section is important because a future change in circumstances might invalidate some key assumptions, which then prompts a decision to be revisited. 


Constraints

The following transaction type will be subject to DOA approval.

Functional AreaTransaction Type
SalesSales Proposals and Contracts

Sales Quotations

Contracts < N years

Contracts > N years

Sales Orders

Rebate Contracts
Credit ManagementCustomer Credit Limits and Rebates

Set-up Credit Limit

Increase Credit Limit

Release Credit Limit Block

Bad Debt Write-off

Dispute Management / Write-off

Credit Memo (Returns / Rebates / Contract Write-off)
Procurement & SupplySupply / Procurement Proposals and Contracts

Purchase Requisition

Contracts < N years (Take-or-Pay / No Take-or-Pay)

Contracts > N years (Take-or-Pay / No Take-or-Pay)

Third-Party (Supplier) Expenditure

Non-Order Invoice (NOI)

One-Time Vendor (OTV)

Urgent Payment Requests

Down Payment Requests
Capital AssetsCAPEX Projects and Assets

Disposal and Write-off of Fixed Assets
InventoryProvision of Inventory

Inventory Review Write-on / Write-off
Mergers & AcquisitionsAcquisitions & Divestments – Transactions

Letter of Intent (LOI) – Non-Binding

Letter of Intent (LOI) – Binding
TreasuryBorrowing or Other Facilities

Provision of Corporate or Bank Guarantee




Impacts

Describe the impact of the decision on other aspects such as other processes, infrastructure, other SAP modules or systems, data cleansing and migration, developments, automations, interfaces, in-flight projects, etc.


Business Rules

Approval Process Principles

  1. Approval Basis

    • Approval decisions are determined by the Master data object, like cost centre, WBS, and Business Partner, in the document requiring approval.

  2. Final Approver

    • Each approval workflow task is routed directly to the Final approver identified in the Delegation of Authority (DOA) matrix.

    • The ultimate approver must be authorized to approve the entire transactional value within the relevant organizational boundary.

  3. Single-Step Approval

    • The process will follow a single-step approval approach.

    • No multi-step approvals will be implemented to minimize potential delays.

  4. Vacant Position Escalation

    • If the designated approver position is vacant, the system will automatically escalate the task to the next higher filled position in the organizational hierarchy.

  5. Eligible Approvers

    • The approver may be:

      • A permanent Syensqo employee, or

      • A contingent worker, provided they are officially appointed to the relevant position in SAP SuccessFactors.

  6. Task Centre
    • BTP Task Centre will be the central Inbox for all approvals from S4 Hana, Ariba, and iCertis.


Options considered

List the options (viable options or alternatives) you considered. These often require a longer explanation with diagrams, or references to other documents (links are best, but attachments are also possible). Use enough detail to adequately explain what you considered so that a project or business stakeholder reviewing this decision will not come back and ask "did you think about...?"; this leads to loss of credibility and questioning of other decisions. This section also helps ensure that you considered enough suitable alternatives rather than just copy/pasting SAP's recommendations.

Option A: DOA matrix and Framework in S4 HANA

Describe the option in sufficient detail for a reader familiar with the subject matter to understand it properly


Option B: DOA matrix and Framework in BTP

Describe the option in sufficient detail for a reader familiar with the subject matter to understand it properly


Option C: DOA matrix and Framework in respective cloud applications 

Describe the option in sufficient detail for a reader familiar with the subject matter to understand it properly


Evaluation

Outline why you selected a position. The best format could be a pro/con table (sample below), but is up to you as the author. You must consider complexity, feasibility, cost/effort to implement, but also ongoing operational impact and cost. You must consider the program principles and explain any deviations in detail. This is probably as important as the decision itself.



Option A

Option B
Option C

DOA Maintainance

(plus)Pro

(minus)Con

(plus)Pro

(plus)Pro

(plus)Pro

(minus)Con


Intgeration 

(plus)Pro

(minus)Con

(minus)Con

(plus)Pro

(plus)Pro


Employe Replication(plus)Pro(minus)Con(minus)Con

See also

Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.


Change log