Purpose

The purpose of this document is to define the conversion approach to create Project Definition (CAPEX, OPEX) in S/4 HANA.

Project Definition is the framework of the Work breakdown structure in SAP. Project Definition holds the default, header information such as Start and end date and scope of the Projects.

 As per Syensqo design below are the list of project scenarios.

CAPITAL/ Operational  Expense
Operational Expense
Statistical Expense
Intercompany Recharges
Provisional Expense

 As per Syensqo design below are the types of project.

Project TypeDescription
11Direct Asset Purchase
12Restructuring Provision
13Safety and Environment Provision
14IAS19 Provision
15Intercompany Recharge
16Capital Lease
17Industrial Projects
RINew Product Introduction
RIProduct & Process Improvement
RICustomer and business support
RIOPD Opportunity Development
18IT Project
19Turnaround Projects
20Contingency
21Variation
22Environmental Fines
23Social Fines
24Corruption Fines
25Waste
26Demolition - Recurring
27Demolition - Non -Recurring
28Marketing
29Budgeted Maintenance
30Continous Improvement
31Operational Performance improvement
32Site impact of Strikes
33Campaigns


Each SAP Project contain Project profile. Project profile contain default values and control parameters for processing objects and functions in the Project System.

Based on scenarios, PS Project can be automatically created from PPM item once stagegate 1 is approved or created manually independent of PPM. 

Below Project Profiles will be allowed for creation of Project definition directly without PPM item.

ZPS0003Statistical Expense
ZPS0004Intercompany Recharges
ZPS0005Provisional Expense


Applicable Project code as per design

Project IDDescription
ACoding Mask for Capital Projects
ECoding Mask for Internal/ Operational Projects
RCoding Mask for R&I Projects
TCoding Mask for Project Templates





Conversion Scope

The scope of this document covers the approach for converting active Project Definition (CAPEX, OPEX) from Legacy Source Systems into S/4HANA following the Master Data Design Standard- Project Definition.

Scope include:

  • Extracting existing active Project Definition (CAPEX, OPEX) from SAP ECC systems WP2 and PF2.
  • Applying transformation and cleansing logic via Syniti to conform with the S/4HANA data model.
  • Loading the transformed Project definition into SAP S/4HANA while ensuring data integrity, correct assignment to project profile as per project scenarios.

The conversion will ensure all projects are aligned to the defined project coding mask and relevant Organizational Units as designed for the target S/4HANA landscape.

 The data from legacy system includes:

All the projects below will be migrated from legacy source systems (PF2 and WP2) into S/4HANA –

  1. Active Capex / Opex Projects.

      2. 

The data from legacy system excludes:

  1. Old projects with no actuals or commitment


List of source systems and approximate number of records
SourceScope

Source Approx No. of Records

Target SystemTarget Approx

No. of Records

PF2 and WP2

All Active Capex / Opex Projects, 



S/4HANA















Additional Information

Multi-language Requirement

Summarize Multi-language Requirement/s, if any

Document Management

As per CNV-1025

Legal Requirement

Summarize Legal Requirement/s, if any

Special Requirements



Target Design

The technical design of the target for this conversion approach.

TableFieldData ElementField DescriptionData TypeLengthRequirement
PROJPSPIDPS_PSPIDProject definitionCHAR24Mandatory
PROJPOST1PS_POST1DescriptionCHAR40Mandatory
PROJSTSPRPS_STSPRWBS status profileCHAR8System Generated
PROJVERNRPS_VERNRNo. of Person Resp.NUM8

Mandatory

PROJASTNRPS_ASTNRApplicant no.CHAR25

Mandatory

PROJVBUKRPS_VBUKRCompany codeCHAR4

Mandatory

PROJVKOKRPS_VKOKRControlling areaCHAR4

Mandatory

PROJ


PRCTRPRCTRProfit CenterCHAR10

Mandatory

PROJPWHIEPS_PWHIEProject CurrencyCHAR5

Mandatory

PROJPLFAZPS_PLFAZ_CHGStart dateDATS8

Mandatory

PROJPLSEZ

PS_PLSEZ_CHG

Finish dateDATS8

Conditional

PROJWERKSWERKS_DPlantCHAR4

Conditional

PROJ

KALIDFABKLFactory CalendarCHAR2

System Generated

PROJPROFLPROFIDPROJProject ProfileCHAR7

Mandatory

PROJBPROFBP_BPROFILBudget ProfileCHAR6

Mandatory

PROJBESTAPS_BESTANDProject stockCHAR1

Mandatory

PROJ-XSTAT

PS_XSTAT

StatisticalCHAR1

Conditional

PROJPPROF

BP_PPROFIL

Planning ProfileCHAR6

System generated

PROJPLINTPLINTIntegrated PlanningCHAR1

Mandatory

PROJFUNC_AREAFKBERFunctional AreaCHAR16

Mandatory

PROJZLEGACYID?Legacy Project IDCHAR

Conditional



Data Cleansing



IDCriticalityError Message/Report DescriptionRuleOutputSource System

1024-001

C1

Active project in current year

 Active projects in needs to be reflected in SAP S/4

Active projects

WP2/PF2

1024-002

C2

Closed project that have cost in current year



WP2/PF2

1024-003

C3

Old projects with no actuals / commitment

If the old projects do not have any actual (and/or) commitments in the past year, set the project to status CLSD (CJ20N)

Old project set to closed

WP2/PF2

1024-004

C4

Project with AUC that created <= 2017 there's no movement in FY2023 - FY2024 and haven't been capitalized for long period

- Review AUC asset that there's no movement (changes) for the year 2023-2024

- Review Project with WBS that linked to the asset. If there's no further cost expected, TECO WBS

- Run settlement to capitalized AUC(CJ88)

Only genuine Project WBS with AUC is outstanding and no AUC not capitalized for closed/TECO Capex Project WBS

WP2/PF2



Conversion Process

The high-level process is represented by the diagram below:

Data Privacy and Sensitivity

Summarize Data Privacy and Sensitivity Requirements, if any


Extraction

Extract data from a source into Syniti Migrate. There are 2 possibilities:

  1. The data exists. Syniti Migrate connects to the source and loads the data into Syniti Migrate. There are 3 methods:
    1. Perform full data extraction from relevant tables in the source system(s).
    2. Perform extraction through the application layer.
    3. Only if Syniti Migrate; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
  2. The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate

The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads

Extraction Run Sheet

Req #Requirement DescriptionTeam Responsible

1024-001

Confirm scope and extraction approach for each ECC source systems WP2, PF2 (direct DB or manual extract)

Data Team (I2M), Data Team (Syniti)

1024-002

Establish and validate Syniti connectivity to both ECC source systems

Technical / Basis Team, Data Team (Syniti)

1024-003

Perform full data extraction from relevant SAP PROJ from both source systems WP2, PF2

Data Team (Syniti)

1024-004

Extract Project Definition via the application layer for additional validations for Manual Data Collection using DCTs

Data Team (I2M)

1024-005

Apply agreed Relevancy Criteria to filter only applicable Project records for S/4HANA

Data Team (I2M), Data Team (Syniti)

1024-006

In case of restricted access or connectivity issues, receive pre-extracted reports/files from source system team and upload to Syniti Migrate manually

Data Team (I2M), Data Team (Syniti)

1024-008

Perform data quality checks on extracted records (e.g., missing fields, invalid dates, incorrect formats)

Data Team (I2M), Data Team (Syniti)

1024-009

Review and approve extracted data sample sets from each source system before transformation begins

Business / Functional Team


Selection Screen

If applicable, this section will give the details on any selection screen parameters, including the parameter type, that are required to be entered to ensure consistent data extracts.
Selection Ref ScreenParameter NameSelection TypeRequirementValue to be entered/set





















Data Collection Template (DCT)

Target Ready Data Collection Template will be created for Data Object data with exception of some fields which require transformation as mentioned in the transformation rule.

<Object> DCT Rules

Field NameField DescriptionRule
PSPIDProject definitionUnique Identifier for the Project, system generated number.  In SyWay,  Projects which are created without PPM item will have Prefix, "F" denotes Operational Expense Projects.
Separate MDS for Project Templates. Ones created via PPM item will inherit its number from PPM item 
 POST1DescriptionShort description, Name of the Project
If Created via PPM Item, this field will be copied from PPM item
STSPRWBS status profileProfile used to Control User Statuses. This will be derived from the configuration
VERNRNo. of Person Resp.Project Owner Position number Refer configuration table field TCJ04-PS_VERNR for data validation.
Inherited if created Project is created via PPM item field Person Responsible Position ID
ASTNRApplicant no.This field represent the position of the Project Financial Controller. Refer configuration table field TCJ05-ASTNR for data validation.
Inherited if the project is created via PPM item field - Project Financial Controller Position ID.
VBUKRCompany codeRepresents legal entity . Refer configuration table field T001-BURKS for data validation.
Inherited if created Project is created via PPM item field Area
VKOKRControlling areaControlling Area is a self-contained organizational unit used for internal cost accounting, Default from Project Profile
PRCTRProfit CenterProfit Center represent a plant or a site or generic for GBU. Refer master data table field CEPC-PRCTR for allowed values.
Inherited if Project is created via PPM item field Profit Centre
PWHIEProject CurrencyCurrency of the Project derived from the Company code
PLFAZStart datePlanned Start date of the Project. Inherited if created Project is created via PPM item
PLSEZFinish datePlanned finish date of the Project, Entered if known. Inherited if created Project is created via PPM item
WERKSPlantPlant represent a site of Project.  Not need for the groupwide expense projects
Inherited if created Project is created via PPM item field Plant
KALIDFactory CalendarDerived from the Plant. Refer configuration table field TFACD-IDENT for allowed values.
PROFLProject ProfileThe profiles contain default values and control parameters for processing objects and functions in the Project System. Below Project Profiles will be allowed for creation of Project definition directly without PPM item
ZPS0003
ZPS0004
ZPS0005
Inherited from Template if created Project is created via PPM item
BPROFBudget ProfileThe budget profile brings together the control parameters for budgeting Such as Time horizon, Currency Translation, availability control. This will be inherited from the Project profile
BESTAProject stock

This field determines the behavior of the stock for Project. The Field will be automatically determined from Project Profile. Once set it cannot be changed.

No Project Stock will be used

XSTATStatisticalIndicator to specify whether a WBS element is only for statistical purposes or whether it may carry actual costs. Mandatory for Statistical Projects with Project profile ZPS0003
PROFLPlanning ProfileProfile which control parameters for cost planning. This is derived from Project profile
PLINTIntegrated PlanningThis indicator specifies whether an order/project participates in integrated planning or not. Derived from project profile. 
FUNC_AREAFunctional AreaFunctional Area will be maintained manually
Refer configuration table field TFKB-FKBER for allowed values."
Default from Template where applicable
ZLEGACYIDLegacy Project IDLegacy system Project ID, updated for migrated Projects Otherwise must be blank
Inherited if created Project is created via PPM item

Extraction Dependencies

List the steps that need to occur before extraction can commence

Item #Step DescriptionTeam Responsible













Transformation

The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:

  1. Perform value mapping and data transformation rules.
    1. Legacy values are mapped to the to-be values (this could include a default value)
    2. Values are transformed according to the rules defined in Syniti Migrate
  2. Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation

Transformation Run Sheet

Item #Step DescriptionTeam Responsible













Transformation Rules

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic









































Transformation Mapping

Use the exact name and reference this section in the “Transformation rules” above
Mapping Table NameMapping Table Description








Transformation Dependencies

List the steps that need to occur before transformation can commence
Item #Step DescriptionTeam Responsible













Pre-Load Validation

Project Team

The following pre-load validations will be performed by the Project Team.

Completeness

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Accuracy

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Business

The following pre-load validations will be performed by the business.

Completeness

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Accuracy

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Load

The load process includes:

  1. Execute the automated data load into target system using load tool or product the load file if the load must be done manually
  2. Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation

Load Run Sheet

Item #Step DescriptionTeam Responsible













Load Phase and Dependencies

Identify the phase as to “when” the load for this object will occur. <Pre-Cutover, Cutover, Post Cutover> and list the steps that need to occur before the load can commence

Configuration

List the Configurations required before loading can commence

Item #Configuration Item






Conversion Objects

Object #Preceding Object Conversion Approach

list the exact title of the conversion object of only the immediate predecessor – this will then confirm the DDD (Data Dependency Diagram)




Error Handling

The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management

Error TypeError DescriptionAction Taken










Post-Load Validation

Project Team

The following post-load validations will be performed by the Project Team.

Completeness

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Accuracy

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Business

The following post-load validations will be performed by the business.

Completeness

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Accuracy

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Key Assumptions

  • Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
  • Data Object is in scope based on data design and any exception requested by business.

Any additional key assumptions.


See also

Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.