The purpose of this document is to define the conversion approach to create Operative Project Definition in S/4 HANA.
In SAP PS, the project definition acts as a framework that provides a binding structure for organizational element of a project, such as Work Breakdown Structures. It serves as the top-level element for creating a project, defining default values for company code, plant, and responsible persons, and is essential for structuring, planning, and controlling all aspects of a project, from initiation to closure.
The scope of this document covers the approach for converting active Project Definition from Legacy Source Systems into S/4HANA following the Master Data Design Standard- Project Definition.
As per SyWay design, there are two ways to create an Operative Project definition based on the scenarios,
Scenario 1: PS Project definition with WBS element hierarchy (Level 1 & 2) can be automatically created from the approved PPM item once stage-gate 1 is approved. This process involves mapping the PPM item type to a predefined PS template project (created as per CVN-1019 Template Projects) with the Decision Flow Management settings in the SAP system.
A project definition is automatically created for the specified PPM item types, using the corresponding project profile and applicable project coding mask. The conversion approach is dealt with in CNV-1022 Portfolio Item.
| PPM Item Type | PS Project Profile | PRJID | PS Coding Mask | Description |
| Z001 Industrial Project with Qualification | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z002 Industrial Project | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z003 Industrial Project - Simple ? | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z004 New Product Introduction | ZPS0001 - CAPITAL/ Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
| Z005 Product & Process Improvement | ZPS0001 - CAPITAL/ Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
| Z006 Customer and business support | ZPS0001 - CAPITAL/ Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
| Z007 OPD Opportunity Development | ZPS0002 - Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
| Z008 IT Full Lifecycle Project | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z009 IT Small Project | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z010 Opex Project | ZPS0002 - Operational Expense | E | ||
| Z011 Turnaround Projects | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z012 Direct Asset Purchase | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z013 Capitalised Maintenance | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z014 Capital Lease | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z017-New Application Development | ZPS0001 - CAPITAL/ Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
All project definition (new project profile ZPS0001, ZPS0002) relevant to PPM item type linking will be created from PPM items and is excluded from this conversion scope.
Scenario 2: A project definition created manually independent of the PPM item, with the data being sourced using a DCT (Data Collection Template).
These projects are:
Conversion scope includes all projects that belong to Scenario 2.
The conversion will ensure all projects are aligned to the defined project coding mask and relevant Organizational Units as designed for the target S/4HANA landscape.
Below project profiles are configured to allow the creation of a project definition directly in the Project System, without requiring integration with a Portfolio and Project Management (PPM) item.
| PS Project Profile | PRJID | PS Coding Mask | PS Coding Mask Description |
ZPS0003 - Statistical Expense | F | -000000-00-00-XX-XX-XX | Statistical/ Recharge & Provision Projects |
ZPS0004 - Intercompany Recharges | F | -000000-00-00-XX-XX-XX | Statistical/ Recharge & Provision Projects |
ZPS0005 - Provisional Expense | F | -000000-00-00-XX-XX-XX | Statistical/ Recharge & Provision Projects |
Scope include:
The data from legacy system includes:
All the projects below will be migrated from legacy source systems (PF2 and WP2) into S/4HANA –
Active internal order with status created / Release.
The data from legacy system excludes:
Logic:
Table PROJ
Key in field "Company Code" in scope.
Field project profile not in excluded project profile.
Result: Object numbers of WBS that are in company codes in scope.
Table JEST:
Field "Object number" = Key in the object numbers of WBS (from Step A)
Field "Status Inactive" = blank
Then filter object number that do not have status I0046 (Closed)
These Project Profile need to be migrated dependent on project profile mapping.
2. Closed Project that have WBS element with cost in current year must also be migrated.
Logic:
Table PROJ
Field "Company Code" in scope.
Field project profile in scope project profile.
Result: Object numbers of WBS that are in company codes in scope.
Table JEST:
Field "Object number" = Key in the object numbers of Project
Field "Status Inactive" = blank
Then filter object number that has status I0046 (Closed).
Result closed projects.
Table PRPS
Field PSPHI For closed projects numbers
Result WBS numbers for
Table RPSCO:
Field "Object number" = Key in the object numbers of WBS
Field "Fiscal Year" = Current year
Field "Value Type" = 4
Result = Object numbers that have cost in current year.
These WBS needs to be migrated.
In addition to the migration of existing Project definitions from ECC there are also some internal orders in ECC which will be migrated to WBS elements in S4 Hana. As the project definition is a requirement for the creation of WBS elements, project definitions which does not exist in ECC will be required, these Project definitions will be defined in a DCT.
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
| WP2 | 14500 | S/4HANA | ||
| PF2 | ||||
| DCT |
Project Definition description will be made available in English. Multi language is supported. Based on the user's login language, the project definition's description in that language will be displayed on the screen
Not Applicable
Not Applicable
Not Applicable
The technical design of the target for this conversion approach.
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PROJ | PSPID | PS_PSPID | Project definition | CHAR | 24 | Mandatory |
| PROJ | POST1 | PS_POST1 | Description | CHAR | 40 | Mandatory |
| PROJ | STSPR | PS_STSPR | WBS status profile | CHAR | 8 | System Generated |
| PROJ | VERNR | PS_VERNR | No. of Person Resp. | NUM | 8 | Mandatory |
| PROJ | ASTNR | PS_ASTNR | Applicant no. | CHAR | 25 | Mandatory |
| PROJ | VBUKR | PS_VBUKR | Company code | CHAR | 4 | Mandatory |
| PROJ | VKOKR | PS_VKOKR | Controlling area | CHAR | 4 | System Generated |
PROJ | PRCTR | PRCTR | Profit Center | CHAR | 10 | Mandatory |
| PROJ | PWHIE | PS_PWHIE | Project Currency | CHAR | 5 | System Generated |
| PROJ | PLFAZ | PS_PLFAZ_CHG | Start date | DATS | 8 | Mandatory |
| PROJ | PLSEZ | PS_PLSEZ_CHG | Finish date | DATS | 8 | Conditional |
| PROJ | WERKS | WERKS_D | Plant | CHAR | 4 | Conditional |
PROJ | KALID | FABKL | Factory Calendar | CHAR | 2 | System Generated |
| PROJ | PROFL | PROFIDPROJ | Project Profile | CHAR | 7 | Mandatory |
| PROJ | BPROF | BP_BPROFIL | Budget Profile | CHAR | 6 | System Generated |
| PROJ | BESTA | PS_BESTAND | Project stock | CHAR | 1 | System Generated |
| PROJ- | XSTAT | PS_XSTAT | Statistical | CHAR | 1 | Conditional |
| PROJ | PPROF | BP_PPROFIL | Planning Profile | CHAR | 6 | System generated |
| PROJ | PLINT | PLINT | Integrated Planning | CHAR | 1 | System generated |
| PROJ | FUNC_AREA | FKBER | Functional Area | CHAR | 16 | Mandatory |
| PROJ | USR00 | Legacy Project ID | CHAR | Conditional | ||
| PROJ | USR02 | Item Type | CHAR | Conditional |
Closing of projects
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
1024-001 | C1 | Active project in current year | Active projects in needs to be reflected in SAP S/4 | Active projects | WP2/PF2 |
1024-002 | C2 | Closed project that have cost in current year | |||
1024-003 | C3 | Old projects with no actuals / commitment | If the old projects do not have any actual (and/or) commitments in the past year, set the project to status CLSD (CJ20N) | Old project set to closed | WP2/PF2 |
1024-004 | C4 | Project with AUC that created <= 2017 there's no movement in FY2023 - FY2024 and haven't been capitalized for long period | - Review AUC asset that there's no movement (changes) for the year 2023-2024 - Review Project with WBS that linked to the asset. If there's no further cost expected, TECO WBS - Run settlement to capitalized AUC(CJ88) | Only genuine Project WBS with AUC is outstanding and no AUC not capitalized for closed/TECO Capex Project WBS | WP2/PF2 |
The high-level process is represented by the diagram below:

Data Privacy and Sensitivity
Summarize Data Privacy and Sensitivity Requirements, if anyExtract data from a source into Syniti Migrate.
. There are 2 possibilities:
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
| Req # | Requirement Description | Team Responsible |
|---|---|---|
1 | Confirm scope and extraction approach for each ECC source systems WP2, PF2 (direct DB or manual extract) | Data Team (I2M), Data Team (Syniti) |
2 | Establish and validate Syniti connectivity to both ECC source systems | Technical / Basis Team, Data Team (Syniti) |
3 | Perform full data extraction from relevant SAP PROJ from both source systems WP2, PF2 | Data Team (Syniti) |
4 | Extract Project Definition via the application layer for additional validations for Manual Data Collection using DCTs | Data Team (I2M) |
5 | Apply agreed Relevancy Criteria to filter only applicable Project records for S/4HANA | Data Team (I2M), Data Team (Syniti) |
6 | In case of restricted access or connectivity issues, receive pre-extracted reports/files from source system team and upload to Syniti Migrate manually | Data Team (I2M), Data Team (Syniti) |
7 | Perform data quality checks on extracted records (e.g., missing fields, invalid dates, incorrect formats) | Data Team (I2M), Data Team (Syniti) |
8 | Review and approve extracted data sample sets from each source system before transformation begins | Business / Functional Team |
| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
| Not applicable |
Data Collection Template (DCT)
Target Ready Data Collection Template will be created for Project DefinitionsProject Definition DCT Rules
| Field Name | Field Description | Rule |
|---|---|---|
| PSPID | Project definition | Unique Identifier for the Project, system generated number. In SyWay, Projects which are created without PPM item will have Prefix, "F" denotes Operational Expense Projects. Separate MDS for Project Templates. Ones created via PPM item will inherit its number from PPM item |
| POST1 | Description | Short description, Name of the Project If Created via PPM Item, this field will be copied from PPM item |
| STSPR | WBS status profile | Profile used to Control User Statuses. This will be derived from the Investment Profile configuration |
| VERNR | No. of Person Resp. | Project Owner Position number Refer configuration table field TCJ04-PS_VERNR for data validation. Inherited if created Project is created via PPM item field Person Responsible Position ID |
| ASTNR | Applicant no. | This field represent the position of the Project Financial Controller. Refer configuration table field TCJ05-ASTNR for data validation. Inherited if the project is created via PPM item field - Project Financial Controller Position ID. |
| VBUKR | Company code | Represents legal entity . Refer configuration table field T001-BURKS for data validation. Inherited if created Project is created via PPM item field Area |
| VKOKR | Controlling area | Controlling Area is a self-contained organizational unit used for internal cost accounting, Default from Project Profile |
| PRCTR | Profit Center | Profit Center represent a plant or a site or generic for GBU. Refer master data table field CEPC-PRCTR for allowed values. Inherited if Project is created via PPM item field Profit Centre |
| PWHIE | Project Currency | Currency of the Project derived from the Company code |
| PLFAZ | Start date | Planned Start date of the Project. Inherited if created Project is created via PPM item |
| PLSEZ | Finish date | Planned finish date of the Project, Entered if known. Inherited if created Project is created via PPM item |
| WERKS | Plant | Plant represent a site of Project. Not need for the groupwide expense projects Inherited if created Project is created via PPM item field Plant |
| KALID | Factory Calendar | Derived from the Plant. Refer configuration table field TFACD-IDENT for allowed values. |
| PROFL | Project Profile | The profiles contain default values and control parameters for processing objects and functions in the Project System. Below Project Profiles will be allowed for creation of Project definition directly without PPM item ZPS0003 ZPS0004 ZPS0005 Inherited from Template if created Project is created via PPM item |
| BPROF | Budget Profile | The budget profile brings together the control parameters for budgeting Such as Time horizon, Currency Translation, availability control. This will be inherited from the Project profile |
| BESTA | Project stock | This field determines the behavior of the stock for Project. The Field will be automatically determined from Project Profile. Once set it cannot be changed. No Project Stock will be used |
| XSTAT | Statistical | Indicator to specify whether a WBS element is only for statistical purposes or whether it may carry actual costs. Mandatory for Statistical Projects with Project profile ZPS0003 |
| PROFL | Planning Profile | Profile which control parameters for cost planning. This is derived from Project profile |
| PLINT | Integrated Planning | This indicator specifies whether an order/project participates in integrated planning or not. Derived from project profile. |
| FUNC_AREA | Functional Area | Functional Area will be maintained manually Refer configuration table field TFKB-FKBER for allowed values." Default from Template where applicable |
| USR00 | Legacy Project ID | Legacy system Project ID, updated for migrated Projects Otherwise must be blank Inherited if created Project is created via PPM item |
| USR02 | Item Type | This field automatically inherits the PPM Item Type from the associated PPM Item. It remains blank when the PS project is created manually for Project Profiles ZPS0003, ZPS0004 & ZPS0005 Blank. |
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Ensure DCT is collected for Project Definition | Data Team |
2 | Perform preliminary completeness check | Data Team |
3 | Raise issues as defects if Req # 1 to 2 are not met | Data Team |
4 | Repeat Req # 1 to 3 if required | Data Team |
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Obtain DCT Sign-off from Business | Data Team |
2 | Execute and Load and perform Transformation | Data Team |
3 | Monitor the transformation progress and ensure performance and completion is within allowed timeframe | Data team |
4 | Review and Validate Error and Preload Reports | Data Team |
5 | Generate data load count. | Data team |
6 | Generate Load Files | Data Team |
7 | Log errors as defects, if any and address resolutions. Close defects. | Data team |
| 8 | Re-transform and re-validate the Pre-load reports if necessary. | Data team |
| 9 | Validate the transformed file as part of pre-load validation, raise data defects or provide the pre-load sign-off. | Business |
| 10 | Analyze and resolve any pre-load defects logged by business. | Data team |
| 11 | Repeat steps 7 to 10 if necessary | Data team |
| 12 | Proceed to pre-load validations | Data team |
Transformation Rules
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| DCT | PSPID | Project definition | S/4 | PROJ | PSPID | Project definition | Copy from source | ||
| DCT | POST1 | Description | S/4 | PROJ | POST1 | Description | Copy from source | ||
| DCT | S/4 | PROJ | STSPR | WBS status profile | Inherit from Project Profile | ||||
| DCT | VERNR | No. of Person Resp. | S/4 | PROJ | VERNR | No. of Person Resp. | Copy from source | ||
| DCT | ASTNR | Applicant no. | S/4 | PROJ | ASTNR | Applicant no. | Copy from source | ||
| DCT | VBUKR | Company code | S/4 | PROJ | VBUKR | Company code | Mapping from source: Company Code Old to new | ||
| DCT | S/4 | PROJ | VKOKR | Controlling area | Default to | ||||
| DCT | PRCTR | Profit Center | S/4 | PROJ | PRCTR | Profit Center | Mapping from source: Profit Center Old to new | ||
| DCT | S/4 | PROJ | PWHIE | Project Currency | Mapping from Company Code | ||||
| DCT | PLFAZ | Start date | S/4 | PROJ | PLFAZ | Start date | Copy from source | ||
| DCT | PLSEZ | Finish date | S/4 | PROJ | PLSEZ | Finish date | Copy from source | ||
| DCT | WERKS | Plant | S/4 | PROJ | WERKS | Plant | Mapping from Source: Plant Old to new | ||
| DCT | S/4 | PROJ | KALID | Factory Calendar | Mapping from Plant | ||||
| DCT | PROFL | Project Profile | S/4 | PROJ | PROFL | Project Profile | Copy from source | ||
| DCT | S/4 | PROJ | BPROF | Budget Profile | Inherit from Project Profile | ||||
| DCT | S/4 | PROJ | BESTA | Project stock | Default to blank | ||||
| DCT | S/4 | PROJ- | XSTAT | Statistical | Inherit from Project Profile | ||||
| DCT | S/4 | PROJ | PPROF | Planning Profile | Inherit from Project Profile | ||||
| DCT | PLINT | Integrated Planning | S/4 | PROJ | PLINT | Integrated Planning | Copy from source | ||
| DCT | FUNC_AREA | Functional Area | S/4 | PROJ | FUNC_AREA | Functional Area | Copy from source | ||
| DCT | ZLEGACYID | Legacy Project ID | S/4 | PROJ | ZLEGACYID | Legacy Project ID | Copy from source |
| Mapping Table Name | Mapping Table Description |
|---|---|
| Item # | Step Description | Team Responsible |
|---|---|---|
| Task | Action |
|---|---|
| title | specific details of what and how the task needs to be performed e.g. which reports are being used etc. |
| Task | Action |
|---|---|
| title | specific details of what and how the task needs to be performed e.g. which reports are being used etc. |
| Task | Action |
|---|---|
| title | specific details of what and how the task needs to be performed e.g. which reports are being used etc. |
| Task | Action |
|---|---|
| title | specific details of what and how the task needs to be performed e.g. which reports are being used etc. |
The load process includes:
| Item # | Step Description | Team Responsible |
|---|---|---|
Load Phase and Dependencies
Identify the phase as to “when” the load for this object will occur. <Pre-Cutover, Cutover, Post Cutover> and list the steps that need to occur before the load can commence
List the Configurations required before loading can commence
| Item # | Configuration Item |
|---|---|
| Object # | Preceding Object Conversion Approach |
|---|---|
| list the exact title of the conversion object of only the immediate predecessor – this will then confirm the DDD (Data Dependency Diagram) | |
The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management
| Error Type | Error Description | Action Taken |
|---|---|---|
| Task | Action |
|---|---|
| title | specific details of what and how the task needs to be performed e.g. which reports are being used etc. |
| Task | Action |
|---|---|
| title | specific details of what and how the task needs to be performed e.g. which reports are being used etc. |
| Task | Action |
|---|---|
| title | specific details of what and how the task needs to be performed e.g. which reports are being used etc. |
| Task | Action |
|---|---|
| title | specific details of what and how the task needs to be performed e.g. which reports are being used etc. |
Any additional key assumptions.
Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.