Purpose

The purpose of this document is to define the conversion approach to create Task List in S/4 HANA.

A Maintenance Task List in SAP PM is a predefined set of maintenance activities that can be reused across multiple work orders and maintenance plans. It standardizes recurring tasks, improves planning efficiency, and ensures consistency in execution.

Legacy Plant Maintenance Task list is using a diverse range of formats across the different systems. There are instances where the same Task list is duplicated within and/or across sources, with informal words. This results in data inconsistency. As per SyWay design, EAM Maintenance Task list will be standardized.

 


Conversion Scope

The scope of this document covers the approach for converting active Task List from Legacy Source Systems into S/4HANA following the Task List Master Data Design Standard.

SAP PM task lists are reusable templates that define the sequence of maintenance activities for equipment, functional locations, or general processes. They standardize maintenance operations by grouping operations, durations, and materials into a single master record. Task lists enhance consistency, simplify planning, and speed up order creation.

The data from legacy system includes:

  1. Task lists created (PLKO-ANDAT) on or after July 1, 2024 OR Task lists used within the past 3 years (with Active Maintenance Items Assigned or Open Notifications or Open Work Orders)
  2. Task List Type:
         A - General Maintenance Task List
         E - Equipment Task List
         T - Task List for Functional Location
  3. Assigned to a relevant Functional Location if its type T(Functional Location)
  4. Assigned to a relevant Equipment if its type E (Equipment)
  5. Has at least 1 operation
  6. Status = Released (PLKO-STATU = 2, 3, 4)
  7. Task list having Maintenance Plant (PLKO-WERKS) in scope - Refer to Value Mapping: Plant (Maintenance Plant = Yes)
  8. Task Lists in the Value Mapping: INC-Task List (What it contains: Task lists that have not been used in over 3 years (criteria: no active maintenance items assigned, no open notifications, and no open work orders) but are still part of a periodic plan (e.g., recurring every X period).

The data from legacy system excludes:

  1. Task lists not used over 3 years. (Definition: No Active Maintenance Items Assigned, No Open Notifications, No Open Work Orders)
  2. Task lists With Deletion Indicator or marked for deletion. Tables to check for deletion indicator (LOEKZ='X'): PLKO, PLAS, PLPO, PLMZ


List of source systems and approximate number of records
SourceScope

Source Approx No. of Records

Target SystemTarget Approx

No. of Records

PF2, WP2

Active Task Lists will be extracted from PF2 and WP2

Additional data/records may be required and these will be constructed via DCT.

Enrichment of in-scope data may be required and will be added via transformation rules

61,000

S/4HANA 

61,000

DCT

Long texts for selected sites for non-PF2/WP2 Task List Operation will be populated as target ready values in DCT.

TBD

S/4 HANA

TBD

Additional Information

Multi-language Requirement

Task List header and operation description does not support multi Language. Any change to the description text via any logon language will overwrite the existing description. Description text can be view in any logon language.

Document Management

Not Applicable

Legal Requirement

Not Applicable

Special Requirements

Not Applicable




Target Design

The technical design of the target for this conversion approach.

1.Task List Header

TableFieldData ElementField DescriptionData TypeLengthRequirement
PLKOPLNTYPLNTYTask List TypeCHAR1Mandatory
PLKOPLNNRPLNNRKey for Task List GroupCHAR8Mandatory
PLKOPLNALPLNALGroup Counter

CHAR

2

System
PLKODATUVDATUVValid-From DateDATS8Mandatory
EAPLEQUNREQUNR

Equipment Number

CHAR

18

Mandatory
TAPLTPLNRTPLNRFunctional Location

CHAR

30

Mandatory
PLKOPROFIDNETZPROFID_STDProfileCHAR7Conditional
PLKOKTEXTPLANTEXTDescription

CHAR

40

Mandatory
PLKOIWERK

IWERK

Planning PlantCHAR4Mandatory
PLKOARBIDIGEWERKWork Centre group with planning functionNUMC8Mandatory
PLKOWERKS

WERKS_D

PlantCHAR4Mandatory
PLKOVERWEPLN_VERWETask List UsageCHAR3Mandatory
PLKOVAGRPVAGRPPlanner GroupCHAR3Mandatory
PLKOSTATU

PLNST

Overall StatusCHAR3Mandatory
PLKOANLZUANLZUSystem ConditionCHAR1Conditional
PLKOSTRATSTRATMaintenance Strategy

CHAR

6

Conditional
PLKOISTRUISTRUAssemblyCHAR40Mandatory
PLKODELKZCP_DELKZIndicator: Delete completely in reorganization runCHAR1Conditional
PLKOPLNNR_ALTCP_PLNNR_AOld numberCHAR20Conditional
PLKOARBTYCR_OBJTYObject types of the CIM resourceCHAR2System
PLKOFLG_CHKFLG_CHKEDInd: Task list was submitted for consistency checkCHAR1System

*  EQUNR/TPLNR- Select the appropriate field depending on technical object

2.Task List Operation

TableFieldData ElementField DescriptionData TypeLengthRequirement
PLPOPLNTYPLNTYTask List TypeCHAR1Mandatory
PLPOPLNNRPLNNRKey for Task List GroupCHAR8Mandatory
PLPOVORNRVORNRActivity NumberCHAR4Mandatory
PLPOPLNKN

PLNKN

Number of the Task List Node

NUMC

8

System
PLPOZAEHL

PLNKN

Internal counter

NUMC

8

System
PLPOARBIDOBJEKTIDWork CentreNUMC8Mandatory
PLPOWERKSWERKS_DPlantCHAR4Mandatory
PLPOSTEUSSTEUSControl KeyCHAR4Mandatory
PLPOLTXA1LTXA1Operation DescriptionCHAR40Mandatory
PLPOTXTSPSPRASLanguage KeyLANG1System
PLPOARBEIARBEITWork Involved in the ActivityQUAN7(1)Mandatory
PLPOARBEHARBEITEUnit for WorkUNIT3Mandatory
PLPOANZZLANZKAPNumber of Capacities RequiredINT13Mandatory
PLPODAUNODAUNORNormal Duration of the ActivityQUAN5(1)System
PLPODAUNEDAUNORENormal Duration/Unit (ISO Format)UNIT3System
PLPOINDETINDETKey for calculationCHAR1Mandatory
PLPOPRZNTAPROZENTWork PercentageINT13Conditional
PLPOVERTNCR_VERTNDistr.cap.reqmts (plant maint.,process order, network)CHAR8Conditional
PLPOAUFKTAFAKTExecution FactorDEC3(0)Conditional
PLPOLARNTLSTARActivity TypeCHAR6System
PLPOANLZUANLZU

System Condition

CHAR1Conditional
PLPOEXECUTION_STAGEEAM_PREMAINPOSTPRE MAIN POSTCHAR10Conditional
PLPOBMVRGBMVRGOrder QuantityQUAN13(3)Conditional
PLPOBMEIHBMEIHOrder Quantity UnitUNIT3Conditional
PLPOPREISIPREIPrice Per Unit

CURR

11(2)System
PLPOWAERSWAERSCurrencyCUKY5System
PLPOPEINHEPEINUnit for PriceDEC5(0)System
PLPOPLIFZPLIFZPlanned Delivery Time in DaysDEC3(0)Conditional
PLPOFRDLBCO_FRDLBIndicator: External Processing Operation with SubcontractingCHAR1Conditional
PLPOSAKTOKSTARCost ElementCHAR10Conditional
PLPOMATKLMATKLMaterial GroupCHAR9Conditional
PLPOEKGRPVG_EKGRPPurchasing GroupCHAR3Conditional
PLPOLIFNRLIFNRVendorCHAR10Conditional
PLPOEKORGEKORGPurchasing OrganizationCHAR4Conditional
PLPOEBELNEBELNPurchasing AgreementCHAR10Conditional
PLPOEBELPEBELPPurchasing Agreement ItemNUMC5Conditional
PLPOINFNRINFNRPurchasing Info RecordCHAR10System
PLPOESOKZESOKZPurchasing info record categoryCHAR1System
PLPOPACKNOPACKNOPackage numberNUMC10System
PLPOBUKRSBUKRSCompany CodeCHAR4System
PLPOKALIDWFCIDFactory CalendarCHAR2System
PLPOPLNKNPLNKNNodeNUMC8System
PLPOZAEHLCIM_COUNTInternal CounterNUMC8System

3.Task List Operation Long Text Header

TableFieldData ElementField DescriptionData TypeLengthRequirement
PLPOPLNTYPLNTYTask List TypeCHAR1Mandatory
PLPOPLNNRPLNNRKey for Task List GroupCHAR8Mandatory
PLPOVORNRVORNRActivity NumberCHAR4Mandatory
PLPOPLNKN

PLNKN

Number of the Task List Node

NUMC

8

System
PLPOZAEHL

PLNKN

Internal counter

NUMC

8

System
STXHTDOBJECTTDOBJECTTexts: application objectCHAR10Mandatory
STXHTDNAMETDOBNAMENameCHAR70Mandatory
STXH

TDID

TDID

Text IDCHAR4Mandatory
STXHTDSPRASSPRASLanguage KeyLANG1Mandatory

Note:

  1. Long Text is not mandatory, only load when there is data
  2. One Long Text Header must have at least 1 Long Text Line

4.Task List Operation Long Text Line

TableFieldData ElementField DescriptionData TypeLengthRequirement
PLPOPLNTYPLNTYTask List TypeCHAR1Mandatory
PLPOPLNNRPLNNRKey for Task List GroupCHAR8Mandatory
PLPOVORNRVORNRActivity NumberCHAR4Mandatory
PLPOPLNKN

PLNKN

Number of the Task List Node

NUMC

8

System
PLPOZAEHL

PLNKN

Internal counter

NUMC

8

System
STXHTDOBJECTTDOBJECTTexts: application objectCHAR10Mandatory
STXHTDNAMETDOBNAMENameCHAR70Mandatory
STXH

TDID

TDID

Text IDCHAR4Mandatory
STXHTDSPRASSPRASLanguage KeyLANG1Mandatory
STXLCLUSTD_TAGTDFORMAT

Tag column

CHAR1

Mandatory

STXLCLUSTD_LINETDLINE

Text Line

CHAR72Mandatory

5.Task List Operation Lean Service

TableFieldData ElementField DescriptionData TypeLengthRequirement
STPOIDNRKIDNRKMaterial Number

CHAR

40

Conditional
MAKTMAKTXMAKTXMaterial descriptionCHAR40System
STPOPOSTPPOSTP

Item category (bill of material)

CHAR

1

Conditional
PLMZWERK_STL

WERKS_D

Plant

CHAR

4

System
PLMZIMENGKMPMGComponent Quantity

CHAR

13

Conditional
PLMZIMEINKMPMEComponent Unit of Measure

UNIT

3

System
PLMZSERVICEDURATIONSERVICEDURATIONService Duration

QUAN

5

Conditional
PLMZSERVICEDURATIONUNITSERVICEDURATIONUNITService Duration Unit

UNIT

3

Conditional
STPOEKORGEKORG

Purchasing Organization

CHAR

4

System
STPOEKGRPEKGRP

Purchasing Group

CHAR

3

System
STPOMATKLMATKL

Material Group

CHAR

9

System

6.Task List Component

TableFieldData ElementField DescriptionData TypeLengthRequirement
PLMZPLNNRPLNNRTask List KeyCHAR8Mandatory
PLMZVORNRVORNRActivity NumberCHAR4System
PLPOPLNKN

PLNKN

Number of the Task List Node

NUMC

8

Mandatory
STPOIDNRKIDNRKMaterial Number

CHAR

40

Conditional
STPOMENGEKMPMGComponent Quantity

CHAR

1

Conditional
STPOMEINSKMPMEComponent Unit of Measure

UNIT

3

Conditional
PLMZRGEKZRGEKZ

Indicator: Backflush

CHAR

1

Conditional
PLMZDISPDISP_PLUS_1

Relevancy to Materials Planning/Generation of Purchase Req.

CHAR

1

Conditional
STPOPOTX1POTX1

BOM Item Text (Line 1)

CHAR

40

System
PLMZSTLTY_WSTLTY

BOM category

CHAR

1

Conditional
PLMZWERK_STL

WERKS_D

Plant

CHAR

4

Conditional
STPOEKGRPEKGRP

Purchasing Group

CHAR

3

Conditional
STPOEKORGEKORG

Purchasing Organization

CHAR

4

Conditional
STPOWAERSWAERS

Currency Keya

CUKY

5

System
STPOPEINHPEINH

Price unit

DEC

5

System
STPOMATKLMATKL

Material Group

CHAR

9

System
PLMZLGORTLGORT_RES

Issue Location for Production Order

CHAR

4

Conditional
STPOLIFNRLIFNR

Account Number of Supplier

CHAR

10

Conditional
MARCWEBAZWEBAZ

Goods receipt processing time in days

DEC

3

System

7.Maintenance Package

TableFieldData ElementField DescriptionData TypeLengthRequirement
PLWPPLNTYPLNTYTask List TypeCHAR1Mandatory
PLWPPLNNRPLNNRTask List KeyCHAR8Mandatory
PLWPPLNALPLNALGroup Counter

CHAR

2

Mandatory
PLWPPLNKNPLNKN

Number of the Task List Node

NUMC

8

Mandatory
PLWPSTRATSTRATMaintenance StrategyCHAR6Mandatory
PLWPPAKETPAKETZAEHLMaintenance Package NumberNUMC2Mandatory
T351X

KZYK1

KTEXTZYK

Short text for the maintenance cycle (time/performance)

CHAR2Mandatory

Task List Data strictly adheres to the Master Data Standard. The complete information of the key fields that hold the Task List information follows the Master Data Standard document that is located here.


Data Cleansing

All data cleansing should take place in the data source system as defined in this document, unless system limitations prevent it.

If data cleansing is managed outside of the source system (e.g. Syniti Migrate, 3rd Party Vendor, DCT), the necessary documentation must be produced and appended to this deliverable for sign-off.

IDCriticalityError Message/Report DescriptionRuleOutputSource System

1005-001

C1

TL Header: Invalid, Inactive or no Operations attached to Active Task List Header 

Task List Header as per Relevancy Criteria assigned with no or inactive Task List Operation attached. 

Task List Operation

PF2, WP2

1005-002

C2

TL Header: Task lists not used within the last 3 years 

Task List as per Relevancy Criteria but are not used across:
1. Maintenance Items as per Relevancy Criteria
2. Notifications as per Relevancy Criteria
3. Work Order as per Relevancy Criteria 

Task List 

PF2, WP2

1005-003

C1 

TL Header-Description: Missing Task Lists Descriptions 

Task List as per Relevancy Criteria where there are blank Task List Descriptions. 

Task List Description 

PF2, WP2

1005-004

C2 

TL Header-Description: Task Lists Descriptions with Informal Words

Task List as per Relevancy Criteria which contain Informal Words in the Task List Description

Task List Description 

PF2, WP2

1005-005

C1

TL Header-Status: Created but not released

TL Header STATU <> 2, 3, 4

Status

PF2, WP2

1005-006

C1

TL Header-Valid-From Date: Valid-From Date is in the future

TL Header Valid-From Date > current date

Valid-From Date

PF2, WP2

1005-007

C1 

TL Header-Work Centre: Invalid, Inactive or no Work Centres

Task List as per Relevancy Criteria assigned with a Work Centre which does not belong below:
1. Work Centre as per Relevancy Criteria 

Work Centre 

PF2, WP2

1005-008

C1 

TL Header-Work Centre: Not mapped to new Work Centre

Task List as per Relevancy Criteria assigned with a Work Centre which is not mapped to new Work Centre

 Work Centre


1005-009

C1 

TL Operation: Active Task List Operations allocated to inactive Task List Headers 

Task List Operation as per Relevancy Criteria assigned with no or inactive Task List Headers attached. 

Task List Operation 

PF2, WP2

1005-010

C1

TL Operation-Work Centre: Invalid, Inactive or no Work Centresask List as per Relevancy Criteria assigned with a Work Centre which does not belong below:
1. Work Centre as per Relevancy Criteria 
Work CentrePF2, WP2

1005-011

C1 

TL Operation-Work Centre: Not mapped to new Work CentreTask List as per Relevancy Criteria assigned with a Work Centre which is not mapped to new Work Centre Work Centre

1005-012

C1

TL Operation: Active Task List Components allocated to inactive Task List Operation 

Task List Component as per Relevancy Criteria assigned with no or inactive Task List Operations attached. 

Task List Component 

PF2, WP2

1005-013

C1 

TL Operation-Vendor: Invalid or inactive Business Partner (Vendor) linked to Task List 

Task List as per Relevancy Criteria assigned with a Business Partner (Vendor) which does not belong below:
1. Business Partner / Vendor (S2P) as per Relevancy Criteria 

Business Partner (Vendor) 

PF2, WP2

1005-014

C1 

TL Component-MaterialInvalid, Inactive or no Material allocatedTask List as per Relevancy Criteria assigned with a Material which does not belong below:
1. Material Master (S2P) as per Relevancy Criteria
Material Number

PF2, WP2

1005-015

C1

TL Component-Construction Type: Invalid, Inactive or no Construction Type allocated

Task List as per Relevancy Criteria assigned with a Construction Type which does not belong below:
1. Construction Type as per Relevancy Criteria 

Construction Type 

PF2, WP2

 


Conversion Process

The high-level process is represented by the diagram below:

Collection will be done manually in the Data Collection Template for the following scenarios:

  • For sites not on SAP-PF2 or WP2 systems - Remove if not applicable
  • For new classes that need to be created to support the to-be design

The high-level process for DCT is represented by the diagram below:


Data Privacy and Sensitivity

Summarize Data Privacy and Sensitivity Requirements, if any


Extraction

Extract data from a source into Syniti Migrate. There are 2 possibilities:

  1. The data exists. Syniti Migrate connects to the source and loads the data into Syniti Migrate. There are 3 methods:
    1. Perform full data extraction from relevant tables in the source system(s).
    2. Perform extraction through the application layer.
    3. Only if Syniti Migrate; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
  2. The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate

The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads

Extraction Run Sheet

Req #Requirement DescriptionTeam Responsible
1

Extract data from source system based on relevancy rule

SyWay Data Team

2

Google Sheet report pre-populated with PF2 and WP2 information to be generated based on relevancy criteria.

SyWay Data Team


Selection Screen

If applicable, this section will give the details on any selection screen parameters, including the parameter type, that are required to be entered to ensure consistent data extracts.
Selection Ref ScreenParameter NameSelection TypeRequirementValue to be entered/set
Not Applicable




Data Collection Template (DCT)

Target Ready Data Collection Template will be created for Data Object data with exception of some fields which require transformation as mentioned in the transformation rule.

1.Task List Header Data Construction Rules

Field NameField DescriptionRule
zLegacyPLNTYLegacy Task List Type

Mandatory.

Select one of the following: A = General TL, E = Equipment, T = Functional Location

zLegacyPLNNRLegacy Task List Group

Mandatory.

When PLNTY = A input PLNNR

When PLNTY = E input EQUNR

When PLNTY = T input TPLNR

zLegacyPLNALLegacy Group Counter

Mandatory.

Must be ascending sequential within the TLGRP. Eg: 01, 02 etc

zLegacyEQUNRLegacy Equipment Number

Mandatory if zLegacyPLNTY = 'E'

zLegacyTPLNRLegacy Functional Location

Mandatory if zLegacyPLNTY = 'T'

PROFIDNETZProfile

 Select profile to assign profile to task list else leave this field blank.

Must reference active TCA41-PROFIDNETZ

KTEXTDescription

Mandatory.

Restrict use of special characters. For list of restricted characters, refer to Appendix SR No 1 in :  DD-FUN- 050 Master Data Standard_Functional Location

WERKSPlant

Mandatory.

Must reference active plant in config (T001W)

ARBPLWork Centre group with planning function

Mandatory.

If PLNTY = A then select manually.
If PLNTY = E or T then this default to Plant of Technical Object.

Must reference active Work Centre (CRHD)

VAGRPPlanner Group

Mandatory.

If PLNTY = A then select manually.
If PLNTY = E or T then this default to Plant of Technical Object.

Must reference active Planner Group in config (T024A)

STATUOverall Status

Mandatory.

Must reference active Task List Status in config (T412)

ANLZUSystem Condition

Conditional.

Must reference active Machine Operating Condition in config (T357M).

Comments/Special handling notes:
This field is integrated with PPDS scheduling. If user want to block production capacity, please select "0-not in operation"; Otherwise, user could select "1-in operation".

STRATMaintenance Strategy

Conditional.

Must reference active Maintenance Strategy in config (T351)

ISTRUAssembly

Mandatory.

Must reference active Material (MARA) which are extended to Plant (MARC)

DELKZIndicator: Delete completely in reorganization run

Conditional.

Possible values: "X" or blank.

"X" to mark record for deletion

2.Task List Operation Data Construction Rules

Definition:

  1. External - (PLPO-STEUS=T430-STEUS, T430-LIEF is not blank)
  2. Lean Service - (PLPO-STEUS=T430-STEUS, T430-SERVICE is not blank)
Field NameField DescriptionRule
zLegacyPLNTYLegacy Task List Type

Mandatory.

Select one of the following: A = General TL, E = Equipment, T = Functional Location

zLegacyPLNNRLegacy Task List Group

Mandatory.

zLegacyPLNALLegacy Group Counter

Mandatory.

Must be ascending sequential within the same zLegacyPLNNR starting with "01". Eg: 01, 02 etc

zLegacyPLNKNNumber of the Task List Node

Mandatory.

Must be ascending sequential within the same zLegacyPLNNR starting with "00000001". Eg: 00000001, 00000002 etc

This field is used to link to Long Text

zLegacyZAEHLInternal counter

Mandatory.

Must be ascending sequential within the same zLegacyPLNNR starting with "00000001". Eg: 00000001, 00000002 etc

This field is used to link to Long Text

zLegacyVORNRLegacy Activity Number

Mandatory.

Must be ascending sequential within the same zLegacyPLNNR starting with "0010" Eg: 0010, 0020 etc

ARBPLWork Centre

Mandatory.

WERKSPlant

Mandatory.

Must match the Plant of the associated Task List Header

Must reference active plant in config (T001W)

STEUSControl Key

Mandatory.

Default to CRHD-STEUS

Must reference active Control Key in config (T430)

LTXA1Operation Description

Mandatory.

Restrict use of special characters. For list of restricted characters, refer to Appendix SR No 1 in :  DD-FUN- 050 Master Data Standard_Functional Location

AUFKTExecution Factor

Conditional.

Numeric values only

ARBEIWork Involved in the ActivityMandatory.
ANZZLNumber of Capacities Required

Mandatory.

Numeric values only

VERTNDistr.cap.reqmts

Conditional.

Must reference active Distribution Function in config (TC29)

ANLZU

System Condition

Conditional.

Must reference active Machine operating condition in config (T357M).

Comments/Special handling notes:
This field is integrated with PPDS scheduling. If user want to block production capacity, please select "0-not in operation"; Otherwise, user could select "1-in operation".

EXECUTION_STAGEPRE MAIN POST

Conditional.

Free text.

If blank then default to "MAIN" in Transformation Rules

BMVRGOrder Quantity

Conditional.

If the Control Key is "External", this field is required. Otherwise, leave blank.

BMEIHOrder Quantity Unit

Conditional.

If the Control Key is "External", this field is required. Otherwise, leave blank.

If not blank, must reference active Units of Measurement in config (T006)

PLIFZPlanned Delivery Time in Days

Conditional.

If the Control Key is "External", this field is optional. Otherwise, leave blank.

FRDLBIndicator: External Processing Operation with Subcontracting

Conditional.

If the Control Key is "External", this field is optional. Otherwise, leave blank.

SAKTOCost Element

Conditional.

If the Control Key is "External", this field is required. Otherwise, leave blank.

MATKLMaterial Group

Conditional.

If the Control Key is "External", this field is required. Otherwise, leave blank.

EKGRPPurchasing Group

Conditional.

If the Control Key is "External", this field is required. Otherwise, leave blank.

If not blank, must reference active Purchasing Groups in config (T024)

LIFNRVendor

Conditional.

If the Control Key is "External", this field is optional. Otherwise, leave blank.

If not blank, must reference active Vendor (LFA1)

EKORGPurchasing Organization

Conditional.

If the Control Key is "External", this field is required. Otherwise, leave blank.

If not blank, must reference active Purchasing Organizations in config (T024E)

EBELNPurchasing Agreement

Conditional.

1st If the operation control key is "External", this field is available. Otherwise, leave this field non editable.
2nd If the "Lean Service" function is activated, this field is generated by system. Otherwise, not used this field.

If the user provides a value, accept it. If not, leave the field blank.

If not blank, must reference active Purchasing Document Item (EKPO-EBELN)

EBELPPurchasing Agreement Item

Conditional.

1st If the operation control key is "External", this field is available. Otherwise, leave this field non editable.
2nd If the "Lean Service" function is activated, this field is generated by system. Otherwise, not used this field.

If the user provides a value, accept it. If not, leave the field blank.

If not blank, must reference active Purchasing Document Item (EKPO-EBELP)

3.Task List Operation Long Text Line Data Construction Rules

FieldField DescriptionRule
zLegacyPLNTYLegacy Task List Type

Mandatory.

Key to link to Task List Operation

zLegacyPLNNRLegacy Key for Task List Group

Mandatory.

Key to link to Task List Operation

zLegacyPLNALLegacy Group Counter

Mandatory.

Key to link to Task List Operation

zLegacyPLNKNNumber of the Task List Node

Mandatory.

Key to link to Task List Operation

zLegacyZAEHLInternal counter

Mandatory.

Key to link to Task List Operation

zLegacyVORNRLegacy Activity Number

Mandatory.

Key to link to Task List Operation

TDSPRASLanguage Key

Mandatory

Must be either one of the following: English(E) , French(F), Italian(I), Mandarin(1), Portuguese(including Brazilian Portuguese)(P), German(D) and Spanish(S)

CLUSTD_TAG

Tag column

Mandatory

Free Text

CLUSTD_LINE

Text Line

Mandatory

Free Text

4.Task List Operation Lean Service Data Construction Rules

Note: If the Task List Operation Control Key is "External"  AND "Lean Service" function is activated then Lean Service is mandatory.

Definition:

  1. External - (PLPO-STEUS=T430-STEUS, T430-LIEF is not blank)
  2. Lean Service - (PLPO-STEUS=T430-STEUS, T430-SERVICE is not blank)
Field NameField DescriptionRule
zLegacyPLNTYLegacy Task List Type

Mandatory.

Key to link to Task List Operation

zLegacyPLNNRLegacy Task List Group

Mandatory.

Key to link to Task List Operation

zLegacyPLNALLegacy Group Counter

Mandatory.

Key to link to Task List Operation

zLegacyVORNRLegacy Activity Number

Mandatory.

Key to link to Task List Operation

IDNRKMaterial Number

Mandatory.

Must reference active Material (MARA) which are extended to Plant

MAKTXMaterial description

Automatically populated

IMENGComponent Quantity

If the user provides a value, accept it. If not, leave the field blank.

SERVICEDURATIONService Duration

If the user provides a value, accept it. If not, leave the field blank.

SERVICEDURATIONUNITService Duration UnitIf the user provides a value, accept it. If not, leave the field blank.

5.Task List Component Data Construction Rules

Field NameField DescriptionRule
zLegacyPLNTYLegacy Task List Type

Mandatory.

Key to link to Task List Operation

zLegacyPLNNRLegacy Task List Group

Mandatory.

Key to link to Task List Operation

zLegacyPLNALLegacy Group Counter

Mandatory.

Key to link to Task List Operation

zLegacyVORNRLegacy Activity Number

Mandatory.

Key to link to Task List Operation

IDNRKMaterial Number

Mandatory.

Must reference active Material (MARA) which are extended to Plant

MENGEComponent Quantity

Positive numeric values only

MEINSComponent Unit of Measure

Must reference active Units of Measurement in config (T006)

RGEKZ

Indicator: Backflush

Allowed values: 'X' or blank

6.Maintenance Package Data Construction Rules

Field NameField DescriptionRule
zLegacyPLNTYLegacy Task List Type

Mandatory.

Key to link to Task List Operation

zLegacyPLNNRLegacy Task List Group

Mandatory.

Key to link to Task List Operation

zLegacyPLNALLegacy Group Counter

Mandatory.

Key to link to Task List Operation

zLegacyVORNRLegacy Activity Number

Mandatory.

Key to link to Task List Operation

STRATMaintenance Strategy

Non Editable.

Direct Mapping from Task List Header: STRAT field

PAKETMaintenance Package Number

Mandatory.

Must reference active Maintenance packages in config (T351P)

KZYK1

Short text for the maintenance cycle (time/performance)

Auto populated from T351X.

Must reference active Maintenance strategy package texts in config (T351X).

Just for clarity in the DCT and will not be used in load file

Extraction Dependencies

List the steps that need to occur before extraction can commence

Item #Step DescriptionTeam Responsible
1

Ensure Syniti has the necessary connection and access to legacy servers 

SyWay A2D Data Team

2

Ensure that the necessary cleansing activities in legacy sources are complete 

SyWay A2D Data Team / Business 

3

Ensure that create, change and deletion of master data is freeze in legacy Production system 

Legacy IT 


Transformation

The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:

  1. Perform value mapping and data transformation rules.
    1. Legacy values are mapped to the to-be values (this could include a default value)
    2. Values are transformed according to the rules defined in Syniti Migrate
  2. Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation

Transformation Run Sheet

Item #Step DescriptionTeam Responsible
1

Obtain DCT Sign-off from Business

SyWay A2D Data Team

2

In dspMigrate, select the wave – S4/HANA – Plant Maintenance

Syniti

3

Go to Process Area Launch and Process the Object – Task List

Syniti

4

Review and Validate Error and Preload Reports

Syniti

5

Execute the transformation to prepare the target tables

Syniti

6

Validate data from pre-load and error reports

Business/Data owner

7

Generate load files

SyWay Data Team


Transformation Rules

1.Task List Header Transformation Rule

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic
1PF2, WP2PLKOPLNTYTask List TypeS/4HANA PLKOPLNTYTask List Type

Direct Mapping

A-General Maintenance Task List
E-Equipment Task List
T-Task List for Functional Location

2PF2, WP2PLKOPLNNRKey for Task List GroupS/4HANA PLKOPLNNRKey for Task List Group

Direct Mapping

3PF2, WP2EAPLEQUNREquipment NumberS/4HANA EAPLEQUNREquipment NumberDirect Mapping
4PF2, WP2TAPLTPLNRFunctional LocationS/4HANA TAPLTPLNRFunctional LocationDirect Mapping
5PF2, WP2PLKODATUVValid-From DateS/4HANA PLKODATUVValid-From DateDefault to current date
6PF2, WP2PLKOKTEXTDescription S/4HANA PLKOKTEXTDescription

Direct Mapping.

Restrict use of special characters. For list of restricted characters, refer to Appendix SR No 1 in :  DD-FUN- 050 Master Data Standard_Functional Location

7PF2, WP2PLKOWERKS Planning Plant S/4HANA PLKOWERKSPlanning PlantDirect Mapping
8PF2, WP2PLKOARBIDWork Centre group with planning function S/4HANA PLKOARBIDWork Centre group with planning functionDirect Mapping
9PF2, WP2PLKOVERWETask List Usage S/4HANA PLKOVERWETask List UsageDefault to "004"
10PF2, WP2PLKOVAGRPPlanner Group S/4HANA PLKOVAGRPPlanner Group

Direct Mapping

11PF2, WP2PLKOSTATUOverall StatusS/4HANA PLKOSTATUOverall StatusDirect Mapping
12PF2, WP2PLKOANLZUSystem ConditionS/4HANA PLKOANLZUSystem ConditionDirect Mapping
13PF2, WP2PLKOSTRATMaintenance StrategyS/4HANA PLKOSTRATMaintenance StrategyDirect Mapping
14PF2, WP2PLKOISTRUAssemblyS/4HANA PLKOISTRUAssemblyDirect Mapping
15PF2, WP2PLPOPLNTYTask List TypeS/4HANA PLPOPLNTYTask List Type

Direct Mapping

A-General Maintenance Task List
E-Equipment Task List
T-Task List for Functional Location

16PF2, WP2PLPOPLNNRKey for Task List GroupS/4HANA PLPOPLNNRKey for Task List Group

Direct Mapping

17PF2, WP2PLPOVORNRActivity NumberS/4HANA PLPOVORNRActivity NumberDirect Mapping
18PF2, WP2PLKOARBIDWork CentreS/4HANA PLPOARBIDWork CentreDefault to PLKO-ARBID
19PF2, WP2PLKOWERKSPlantS/4HANA PLPOWERKSPlantDefault to PLKO-WERKS
20








21PF2, WP2ESLLSRVPOSActivity NumberS/4HANA ESLLSRVPOSActivity NumberDirect Mapping
22PF2, WP2ESLLMENGEQuantity with SignS/4HANA ESLLMENGEQuantity with SignDirect Mapping
23PF2, WP2ESLLMEINSBase Unit of MeasureS/4HANA ESLLMEINSBase Unit of MeasureDirect Mapping
24PF2, WP2PLMZPLNNRTask List KeyS/4HANA PLMZPLNNRTask List KeyDirect Mapping
25PF2, WP2PLMZVORNRActivity NumberS/4HANA PLMZVORNRActivity NumberDirect Mapping
26PF2, WP2PLMZGP_MATNRMaterial NumberS/4HANA PLMZGP_MATNRMaterial NumberDirect Mapping
27PF2, WP2PLMZIMENGComponent QuantityS/4HANA PLMZIMENGComponent QuantityDirect Mapping
28PF2, WP2PLMZIMEINComponent Unit of MeasureS/4HANA PLMZIMEINComponent Unit of MeasureDirect Mapping
29PF2, WP2PLMZRGEKZIndicator: Backflush

S/4HANA 

PLMZRGEKZIndicator: BackflushDirect Mapping
30PF2, WP2PLMZDISPRelevancy to Materials Planning/Generation of Purchase Req.

S/4HANA 

PLMZDISPRelevancy to Materials Planning/Generation of Purchase Req.Direct Mapping
31PF2, WP2PLMZSTLTY_WBOM categoryS/4HANA PLMZSTLTY_WBOM categoryDirect Mapping
32PF2, WP2PLMZWERK_STL

Plant

S/4HANA 

PLMZWERK_STL

Plant

Direct Mapping
33PF2, WP2STPOEKGRP

Purchasing Group

S/4HANA STPOEKGRP

Purchasing Group

Direct Mapping
34PF2, WP2STPOEKORG

Purchasing Organization

S/4HANA STPOEKORG

Purchasing Organization

Direct Mapping
35PF2, WP2PLMZLGORTIssue Location for Production Order

S/4HANA 

PLMZLGORTIssue Location for Production OrderDefault to MARC-LGPRO
36PF2, WP2STPOLIFNRAccount Number of Supplier

S/4HANA 

STPOLIFNRAccount Number of SupplierDirect Mapping
37PF2, WP2PLWPPLNTYTask List TypeS/4HANA PLWPPLNTYTask List TypeDirect Mapping
38PF2, WP2PLWPPLNNRTask List KeyS/4HANA PLWPPLNNRTask List KeyDirect Mapping
39PF2, WP2PLWPPLNALGroup CounterS/4HANA PLWPPLNALGroup CounterDirect Mapping
40PF2, WP2PLWPPLNKN

Number of the Task List Node

S/4HANA PLWPPLNKN

Number of the Task List Node

Direct Mapping
41PF2, WP2PLWPSTRATMaintenance StrategyS/4HANA PLWPSTRATMaintenance StrategyDirect Mapping
42PF2, WP2PLWPPAKETMaintenance Package NumberS/4HANA PLWPPAKETMaintenance Package NumberDirect Mapping
43PF2, WP2T351X

KZYK1

Short text for the maintenance cycle (time/performance)

S/4HANA T351X

KZYK1

Short text for the maintenance cycle (time/performance)

Direct Mapping

2.Task List Operation

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic
1PF2, WP2PLPOSTEUSControl KeyS/4HANA PLPOSTEUSControl KeyDirect Mapping
2PF2, WP2PLPOLTXA1Operation DescriptionS/4HANA PLPOLTXA1Operation Description

Direct Mapping.

Restrict use of special characters. For list of restricted characters, refer to Appendix SR No 1 in :  DD-FUN- 050 Master Data Standard_Functional Location

3PF2, WP2PLPOARBEIWork Involved in the ActivityS/4HANA PLPOARBEITWork Involved in the ActivityDirect Mapping
4PF2, WP2PLPOARBEHUnit for WorkS/4HANA PLPOARBEHUnit for WorkDefault to "H"
5PF2, WP2PLPOANZZLNumber of Capacities RequiredS/4HANA PLPOANZZLNumber of Capacities RequiredDirect Mapping
6PF2, WP2PLPOINDETKey for calculationS/4HANA PLPOINDETKey for calculationDefault to "1"
7PF2, WP2PLPOPRZNTWork PercentageS/4HANA PLPOPRZNTWork PercentageDefault to "100"
8PF2, WP2PLPOVERTLDistribution function for capacity requirementsS/4HANA PLPOVERTLDistribution function for capacity requirementsDirect Mapping
9PF2, WP2PLPOAUFKTExecution FactorS/4HANA PLPOAUFKTExecution FactorDirect Mapping
10PF2, WP2PLPOANLZUSystem ConditionS/4HANA PLPOANLZUSystem ConditionDirect Mapping
11PF2, WP2PLPOEXECUTION_STAGEPRE MAIN POSTS/4HANA PLPOEXECUTION_STAGEPRE MAIN POSTDirect Mapping. Default to "MAIN" if blank
12PF2, WP2PLPOBMVRGOrder QuantityS/4HANA PLPOBMVRGOrder QuantityDirect Mapping
13PF2, WP2PLPOBMEIHOrder Quantity UnitS/4HANA PLPOBMEIHOrder Quantity UnitDirect Mapping
14PF2, WP2PLPOPLIFZPlanned Delivery Time in DaysS/4HANA PLPOPLIFZPlanned Delivery Time in DaysDirect Mapping
15PF2, WP2PLPOFRDLBIndicator: External Processing Operation with SubcontractingS/4HANA PLPOFRDLBIndicator: External Processing Operation with SubcontractingDirect Mapping
16PF2, WP2PLPOSAKTOCost ElementS/4HANA PLPOSAKTOCost ElementDirect Mapping
17PF2, WP2PLPOMATKLMaterial GroupS/4HANA PLPOMATKLMaterial GroupDirect Mapping
18PF2, WP2PLPOEKGRPPurchasing GroupS/4HANA PLPOEKGRPPurchasing GroupDirect Mapping
19PF2, WP2PLPOLIFNRVendorS/4HANA PLPOLIFNRVendorDirect Mapping
20PF2, WP2PLPOEKORGPurchasing OrganizationS/4HANA PLPOEKORGPurchasing OrganizationDirect Mapping
21PF2, WP2PLPOEBELNPurchasing AgreementS/4HANA PLPOEBELNPurchasing AgreementDirect Mapping
22PF2, WP2PLPOEBELPPurchasing Agreement ItemS/4HANA PLPOEBELPPurchasing Agreement ItemDirect Mapping

3.Task List Operation Long Text Header

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic
1DCTPLPOPLNTYTask List TypeS/4HANA PLPOPLNTYTask List TypeDirect Mapping
2DCTPLPOPLNNRKey for Task List GroupS/4HANA PLPOPLNNRKey for Task List GroupDirect Mapping
3DCTPLPOVORNRActivity NumberS/4HANA PLPOVORNRActivity NumberDirect Mapping
4DCTSTXHTDOBJECTTexts: application objectS/4HANA STXHTDOBJECTTexts: application objectDirect Mapping
5DCTSTXHTDOBNAMENameS/4HANA STXHTDOBNAMENameDirect Mapping
6DCTSTXH

TDID

Text IDS/4HANA STXH

TDID

Text IDDirect Mapping
7DCTSTXHSPRASLanguage KeyS/4HANA STXHSPRASLanguage KeyDirect Mapping

4.Task List Operation Long Text Line

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic
1DCTPLPOPLNTYTask List TypeS/4HANA PLPOPLNTYTask List TypeDirect Mapping
2DCTPLPOPLNNRKey for Task List GroupS/4HANA PLPOPLNNRKey for Task List GroupDirect Mapping
3DCTPLPOVORNRActivity NumberS/4HANA PLPOVORNRActivity NumberDirect Mapping
4DCTSTXHTDOBJECTTexts: application objectS/4HANA STXHTDOBJECTTexts: application objectDefault to 'ROUTING'
5DCTSTXHTDOBNAMENameS/4HANA STXHTDOBNAMEName

Character 1-3: Direct Mapping to Client Number (eg 100)

Character 4: Direct Mapping to zLegacyPLNTY (eg A, E or T)

Character 5-12: Direct Mapping to zLegacyPLNNR (eg 00000001, 00000002)

Character 13-20: Direct Mapping to zLegacyPLNKN (eg 00000001, 00000002)

Character 21-28: Direct Mapping to zLegacyZAEHL (eg 00000001, 00000002)

Example: "100A000000010000000100000001" , "100A000000010000000200000002"

6DCTSTXH

TDID

Text IDS/4HANA STXH

TDID

Text IDDefault to 'LTXT'
7DCTSTXHSPRASLanguage KeyS/4HANA STXHSPRASLanguage KeyDirect Mapping
8DCTSTXLCLUSTD_TAGTag columnS/4HANA STXLCLUSTD_TAGTag columnDirect Mapping
9DCTSTXLCLUSTD_LINEText LineS/4HANA STXLCLUSTD_LINEText LineDirect Mapping

 5.Task List Operation Lean Service

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic
1DCT
zLegacyPLNTY
S/4HANA
zLegacyPLNTY
Direct Mapping
2DCT
zLegacyPLNNR
S/4HANA
zLegacyPLNNR
Direct Mapping
3DCT
zLegacyPLNAL
S/4HANA
zLegacyPLNAL
Direct Mapping
4DCT
zLegacyVORNR
S/4HANA
zLegacyVORNR
Direct Mapping
5DCTSTPOIDNRK
S/4HANASTPOIDNRK
Direct Mapping
6DCTMAKTMAKTX
S/4HANAMAKTMAKTX
Direct Mapping
7----S/4HANASTPOPOSTP
Default to 'N'
8DCTPLMZIMENG
S/4HANAPLMZIMENG
Direct Mapping
9DCTPLMZSERVICEDURATION
S/4HANAPLMZSERVICEDURATION
Direct Mapping
10DCTPLMZSERVICEDURATIONUNIT
S/4HANAPLMZSERVICEDURATIONUNIT
Direct Mapping

6.Task List Component

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic
1 
zLegacyPLNTYLegacy Task List TypeS/4HANA PLPOPLNTYTask List Type

Direct Mapping

2

zLegacyPLNNRLegacy Task List GroupS/4HANA PLPO

Direct Mapping

3

zLegacyPLNALLegacy Group CounterS/4HANA PLPO

Direct Mapping

4

zLegacyVORNRLegacy Activity NumberS/4HANA PLPO

Direct Mapping

5DCTSTPOIDNRKMaterial NumberS/4HANA STPOIDNRKMaterial Number

Direct Mapping

6DCTPLMZIMENGComponent QuantityS/4HANA PLMZIMENGComponent Quantity

Direct Mapping

7DCTPLMZIMEINComponent Unit of MeasureS/4HANA PLMZIMEINComponent Unit of Measure

Direct Mapping

8---

-

S/4HANA PLMZRGEKZIndicator: Backflush

Allowed values: 'X' or blank



List of Custom Target Reports for this object is maintained here: Conversion Specification - Custom Reports Register.

Transformation Mapping

Use the exact name and reference this section in the “Transformation rules” above
Mapping Table NameMapping Table Description
Informal CharactersList of Informal Characters and New Translation

INC-Task List

Task List inclusion list

ENR-Task List Operation Lean Service

Task List Operation Lean Service enrichment to assign service details

Functional Location

Old to new Functional Location

Equipment Number

Old to new Equipment Number

Maintenance item

Old to new Maintenance item

Plant

Old to new Plant

Work Centre

Old to new Work Centre

Cost Centre

Old to new Cost Centre

Maintenance Plan

Old to new Maintenance Plan

Maintenance Strategy

Old to new Maintenance Strategy

Maintenance Package

Old to new Maintenance Package

Material Number

Old to new Material Number

Transformation Dependencies

List the steps that need to occur before transformation can commence
Item #Step DescriptionTeam Responsible
1

Ensure DCT tables completeness

Syniti

2

Ensure all Transformation mappings are up to date.

Syniti


Pre-Load Validation

Project Team

The following pre-load validations will be performed by the Project Team.

Completeness

TaskAction

Verify Record Count

SyWay A2D Data Team to verify that the total number of relevant records from legacy systems and DCTs (if any) is equal to the total number of records in the Preload and Load Sheets.

Verify Data Integrity

SyWay A2D Data Team to verify that the total number of Operations per Work Oder header extracted from legacy systems and DCTs (if any) should be equal to the total number of operations identified in the Preload and Load Sheets


Accuracy

TaskAction

Conversion Accuracy

SyWay A2D Data Team to verify that all fields below meet pass the checks:

  1. Mandatory Fields
  2. Field and Value Mapping Correctness
  3. Null Checks
  4. Text Length Checks

Review Error Reports

Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data.


Business

The following pre-load validations will be performed by the business.

Completeness

TaskAction

Verify Record Count

Business Data Owner/s to verify that the total number of relevant records from legacy systems and DCTs (if any) is equal to the total number of records in the Preload and Load Sheets.


Accuracy

TaskAction

Conversion Accuracy

Business Data Owner/s to verify that all fields below meet pass the checks:

  1. Mandatory Fields
  2. Field and Value Mapping Correctness
  3. Null Checks
  4. Text Length Checks


Load

The load process includes:

  1. Execute the automated data load into target system using load tool or product the load file if the load must be done manually
  2. Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation

Load Run Sheet

Item #Step DescriptionTeam Responsible
1

Obtain DCT Sign-off from Business

SyWay A2D Data Team

2Ensure Pre-load sign-offs are obtainedSyWay A2D Data Team
3Proceed with Data load.SyWay A2D Data Team
4Validate few records loaded by accessing standard transactions.SyWay A2D Data Team
5Generate the post load reports in the tool.SyWay A2D Data Team
6Log errors as defects, if any and address resolutions. Close defects.SyWay A2D Data Team
7Generate post load report if step 6 is validatedSyWay A2D Data Team
8Business to validate the post load files as part of post-load validation, raise data defects or provide the post-load sign-off.Business
9Repeat steps 5 to 7 if necessary.SyWay A2D Data Team


Load Phase and Dependencies

Identify the phase as to “when” the load for this object will occur. <Pre-Cutover, Cutover, Post Cutover> and list the steps that need to occur before the load can commence

Configuration

List the Configurations required before loading can commence

Item #Configuration Item
1T399I-Planning Plant
2T001W-Plant
3NRIV -Number Ranges for Task List Group
4T416-Task List Usage
5T0241-Planner Groups
6TQ72-Task List Status
7T357M-System Condition
8T430-Control Key
9T006-Unit of Measure
10T498-Distribution function
11CSLA-Activity Type
12CSKA-Cost Element
13T024-Purchasing Group
14T023-Material Group
15LFA1-Supplier
16T024E-Purchasing Organization
17T430-Operation/Activity control key
18T399X-Parameters dependent on order type
19TCA41-Default values for standard networks and profiles

Conversion Objects

Object #Preceding Object Conversion Approach

1001

Bill of Material

1002

Equipment

1003

Functional Location

1010

Construction Types/Assemblies

1011

Documents/DIR

1016

Maintenance Plan and Item

1017

Maintenance Strategy

2019

Material Master

3018

Vendors

Error Handling

The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management

Error TypeError DescriptionAction Taken

Configuration

Invalid Control Key

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Planner Group

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Plant

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Planning Plant

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid System Condition

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Purchasing Group

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Material Group

Engage Functional team to expedite and fix the error in the system

Configuration

Invalid Purchasing Org

Engage Functional team to expedite and fix the error in the system

Invalid Data

Invalid Maintenance Strategy

Expedite whether the master data is changed in the system

Invalid Data

Invalid Activity Type

Expedite whether the master data is changed in the system

Invalid Data

Invalid Assembly

Expedite whether the master data is changed in the system

Invalid Data

Invalid Work Centre

Expedite whether the master data is changed in the system

Invalid Data

Invalid Material Number

Expedite whether the master data is changed in the system

Invalid Data

Invalid Service Number

Expedite whether the master data is changed in the system

Invalid Data

Invalid Cost Element

Expedite whether the master data is changed in the system

Invalid Data 

Invalid Vendor

Expedite whether the master data is changed in the system

Invalid Data

Invalid Outline Agreement

Expedite whether the master data is changed in the system

Invalid Data

Invalid Maintenance BOM

Expedite whether the master data is changed in the system


Post-Load Validation

Project Team

The following post-load validations will be performed by the Project Team.

Completeness

TaskAction

Verify Count

SyWay A2D Data Team to verify the record count created in target S/4 HANA by accessing post load reports in dspMigrate or standard reports from S/4 HANA.

Verify Logs

Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.).


Accuracy

TaskAction

Conversion Accuracy

SyWay A2D Data Team to verify that the Work order data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA.


Business

The following post-load validations will be performed by the business.

Completeness

TaskAction

Verify Count

Download Post Load Reports from dspMigrate and verify that the record count loaded in the target S/4 HANA is the same count as of the endorsed load file.


Accuracy

TaskAction

Conversion Accuracy

Verify that the EAM Work order data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA.


Key Assumptions

  • Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
  • Task List is in scope based on data design and any exception requested by business.
  • All data cleansing and preparation has been completed.

Any additional key assumptions.


See also

Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.

Change log

Workflow history