The purpose of this document is to define the conversion approach to create Task List in S/4 HANA.
A Maintenance Task List in SAP PM is a predefined set of maintenance activities that can be reused across multiple work orders and maintenance plans. It standardizes recurring tasks, improves planning efficiency, and ensures consistency in execution.
Legacy Plant Maintenance Task list is using a diverse range of formats across the different systems. There are instances where the same Task list is duplicated within and/or across sources, with informal words. This results in data inconsistency. As per SyWay design, EAM Maintenance Task list will be standardized.
The scope of this document covers the approach for converting active Task List from Legacy Source Systems into S/4HANA following the Task List Master Data Design Standard.
SAP PM task lists are reusable templates that define the sequence of maintenance activities for equipment, functional locations, or general processes. They standardize maintenance operations by grouping operations, durations, and materials into a single master record. Task lists enhance consistency, simplify planning, and speed up order creation.
The data from legacy system includes:
The data from legacy system excludes:
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
PF2, WP2 | Active Task Lists will be extracted from PF2 and WP2. Enrichment of in-scope data may be required and will be added via transformation rules. | 61,000 | S/4HANA | 61,000 |
DCT |
| TBD | S/4 HANA | TBD |
Task List header and operation description does not support multi Language. Any change to the description text via any logon language will overwrite the existing description. Description text can be view in any logon language.
Not Applicable
Not Applicable
Not Applicable
The technical design of the target for this conversion approach.
1.Task List Header
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PLKO | PLNTY | PLNTY | Task List Type | CHAR | 1 | Mandatory |
| PLKO | PLNNR | PLNNR | Key for Task List Group | CHAR | 8 | Mandatory |
| PLKO | PLNAL | PLNAL | Group Counter | 2 | Mandatory | |
| PLKO | DATUV | DATUV | Valid-From Date | DATS | 8 | Mandatory |
| EAPL | EQUNR | EQUNR | Equipment Number | 18 | Mandatory | |
| TAPL | TPLNR | TPLNR | Functional Location | 30 | Mandatory | |
| PLKO | PROFIDNETZ | PROFID_STD | Profile | CHAR | 7 | Conditional |
| PLKO | KTEXT | PLANTEXT | Description | 40 | Mandatory | |
| PLKO | IWERK | IWERK | Planning Plant | CHAR | 4 | Mandatory |
| CRHD | ARBPL | ARBPL | Work Centre | NUMC | 8 | Mandatory |
| PLKO | WERKS | WERKS_D | Plant | CHAR | 4 | Mandatory |
| PLKO | VERWE | PLN_VERWE | Task List Usage | CHAR | 3 | Mandatory |
| PLKO | VAGRP | VAGRP | Planner Group | CHAR | 3 | Mandatory |
| PLKO | STATU | PLNST | Overall Status | CHAR | 3 | Mandatory |
| PLKO | ANLZU | ANLZU | System Condition | CHAR | 1 | Conditional |
| PLKO | STRAT | STRAT | Maintenance Strategy | 6 | Conditional | |
| PLKO | ISTRU | ISTRU | Assembly | 40 | Conditional | |
| PLKO | DELKZ | CP_DELKZ | Indicator: Delete completely in reorganization run | CHAR | 1 | Conditional |
| PLKO | ARBTY | CR_OBJTY | Object types of the CIM resource | CHAR | 2 | System |
| PLKO | FLG_CHK | FLG_CHKED | Ind: Task list was submitted for consistency check | CHAR | 1 | System |
2.Task List Header Long Text Header
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PLKO | PLNTY | PLNTY | Task List Type | CHAR | 1 | Mandatory |
| PLKO | PLNNR | PLNNR | Key for Task List Group | CHAR | 8 | Mandatory |
| PLKO | PLNAL | PLNAL | Group Counter | 2 | Mandatory | |
| STXH | TDOBJECT | TDOBJECT | Texts: application object | CHAR | 10 | Mandatory |
| STXH | TDNAME | TDOBNAME | Name | CHAR | 70 | Mandatory |
| STXH | TDID | TDID | Text ID | CHAR | 4 | Mandatory |
| STXH | TDSPRAS | SPRAS | Language Key | LANG | 1 | Mandatory |
3.Task List Header Long Text Line
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PLKO | PLNTY | PLNTY | Task List Type | CHAR | 1 | Mandatory |
| PLKO | PLNNR | PLNNR | Key for Task List Group | CHAR | 8 | Mandatory |
| PLKO | PLNAL | PLNAL | Group Counter | 2 | Mandatory | |
| STXH | TDOBJECT | TDOBJECT | Texts: application object | CHAR | 10 | Mandatory |
| STXH | TDNAME | TDOBNAME | Name | CHAR | 70 | Mandatory |
| STXH | TDID | TDID | Text ID | CHAR | 4 | Mandatory |
| STXH | TDSPRAS | SPRAS | Language Key | LANG | 1 | Mandatory |
| STXL | CLUSTD_TAG | TDFORMAT | Tag column | CHAR | 1 | Mandatory |
| STXL | CLUSTD_LINE | TDLINE | Text Line | CHAR | 72 | Mandatory |
Note:
2.Task List Operation
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PLPO | PLNTY | PLNTY | Task List Type | CHAR | 1 | Mandatory |
| PLPO | PLNNR | PLNNR | Key for Task List Group | CHAR | 8 | Mandatory |
| PLKO | PLNAL | PLNAL | Group Counter | 2 | Mandatory | |
| PLPO | VORNR | VORNR | Activity Number | CHAR | 4 | Mandatory |
| PLPO | PLNKN | PLNKN | Number of the Task List Node | 8 | System | |
| PLPO | ZAEHL | PLNKN | Internal counter | 8 | System | |
| CRHD | ARBPL | ARBPL | Work Centre | NUMC | 8 | Mandatory |
| PLPO | WERKS | WERKS_D | Plant | CHAR | 4 | Mandatory |
| PLPO | STEUS | STEUS | Control Key | CHAR | 4 | System |
| PLPO | LTXA1 | LTXA1 | Operation Description | CHAR | 40 | Mandatory |
| PLPO | TXTSP | SPRAS | Language Key | LANG | 1 | System |
| PLPO | ARBEI | ARBEIT | Work Involved in the Activity | QUAN | 7(1) | Mandatory |
| PLPO | ARBEH | ARBEITE | Unit for Work | UNIT | 3 | Mandatory |
| PLPO | ANZZL | ANZKAP | Number of Capacities Required | INT1 | 3 | Mandatory |
| PLPO | DAUNO | DAUNOR | Normal Duration of the Activity | QUAN | 5(1) | System |
| PLPO | DAUNE | DAUNORE | Normal Duration/Unit (ISO Format) | UNIT | 3 | System |
| PLPO | INDET | INDET | Key for calculation | CHAR | 1 | Mandatory |
| PLPO | PRZNT | APROZENT | Work Percentage | INT1 | 3 | Conditional |
| PLPO | VERTN | CR_VERTN | Distr.cap.reqmts (plant maint.,process order, network) | CHAR | 8 | Conditional |
| PLPO | AUFKT | AFAKT | Execution Factor | DEC | 3(0) | Conditional |
| PLPO | LARNT | LSTAR | Activity Type | CHAR | 6 | System |
| PLPO | ANLZU | ANLZU | System Condition | CHAR | 1 | Conditional |
| PLPO | EXECUTION_STAGE | EAM_PREMAINPOST | PRE MAIN POST | CHAR | 10 | Conditional |
| PLPO | BMVRG | BMVRG | Order Quantity | QUAN | 13(3) | Conditional |
| PLPO | BMEIH | BMEIH | Order Quantity Unit | UNIT | 3 | Conditional |
| PLPO | PREIS | IPREI | Price Per Unit | 11(2) | System | |
| PLPO | WAERS | WAERS | Currency | CUKY | 5 | System |
| PLPO | PEINH | EPEIN | Unit for Price | DEC | 5(0) | System |
| PLPO | PLIFZ | PLIFZ | Planned Delivery Time in Days | DEC | 3(0) | Conditional |
| PLPO | FRDLB | CO_FRDLB | Indicator: External Processing Operation with Subcontracting | CHAR | 1 | Conditional |
| PLPO | SAKTO | KSTAR | Cost Element | CHAR | 10 | Conditional |
| PLPO | MATKL | MATKL | Material Group | CHAR | 9 | Conditional |
| PLPO | EKGRP | VG_EKGRP | Purchasing Group | CHAR | 3 | Conditional |
| PLPO | LIFNR | LIFNR | Vendor | CHAR | 10 | Conditional |
| PLPO | EKORG | EKORG | Purchasing Organization | CHAR | 4 | Conditional |
| PLPO | EBELN | EBELN | Purchasing Agreement | CHAR | 10 | Conditional |
| PLPO | EBELP | EBELP | Purchasing Agreement Item | NUMC | 5 | Conditional |
| PLPO | INFNR | INFNR | Purchasing Info Record | CHAR | 10 | System |
| PLPO | ESOKZ | ESOKZ | Purchasing info record category | CHAR | 1 | System |
| PLPO | PACKNO | PACKNO | Package number | NUMC | 10 | System |
| PLPO | BUKRS | BUKRS | Company Code | CHAR | 4 | System |
| PLPO | KALID | WFCID | Factory Calendar | CHAR | 2 | System |
| PLPO | PLNKN | PLNKN | Node | NUMC | 8 | System |
| PLPO | ZAEHL | CIM_COUNT | Internal Counter | NUMC | 8 | System |
3.Task List Operation Long Text Header
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PLPO | PLNTY | PLNTY | Task List Type | CHAR | 1 | Mandatory |
| PLPO | PLNNR | PLNNR | Key for Task List Group | CHAR | 8 | Mandatory |
| PLPO | VORNR | VORNR | Activity Number | CHAR | 4 | Mandatory |
| PLPO | PLNKN | PLNKN | Number of the Task List Node | 8 | System | |
| PLPO | ZAEHL | PLNKN | Internal counter | 8 | System | |
| STXH | TDOBJECT | TDOBJECT | Texts: application object | CHAR | 10 | Mandatory |
| STXH | TDNAME | TDOBNAME | Name | CHAR | 70 | Mandatory |
| STXH | TDID | TDID | Text ID | CHAR | 4 | Mandatory |
| STXH | TDSPRAS | SPRAS | Language Key | LANG | 1 | Mandatory |
4.Task List Operation Long Text Line
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PLPO | PLNTY | PLNTY | Task List Type | CHAR | 1 | Mandatory |
| PLPO | PLNNR | PLNNR | Key for Task List Group | CHAR | 8 | Mandatory |
| PLPO | VORNR | VORNR | Activity Number | CHAR | 4 | Mandatory |
| PLPO | PLNKN | PLNKN | Number of the Task List Node | 8 | System | |
| PLPO | ZAEHL | PLNKN | Internal counter | 8 | System | |
| STXH | TDOBJECT | TDOBJECT | Texts: application object | CHAR | 10 | Mandatory |
| STXH | TDNAME | TDOBNAME | Name | CHAR | 70 | Mandatory |
| STXH | TDID | TDID | Text ID | CHAR | 4 | Mandatory |
| STXH | TDSPRAS | SPRAS | Language Key | LANG | 1 | Mandatory |
| STXL | CLUSTD_TAG | TDFORMAT | Tag column | CHAR | 1 | Mandatory |
| STXL | CLUSTD_LINE | TDLINE | Text Line | CHAR | 72 | Mandatory |
Note:
5.Task List Operation Lean Service
Note: If the Task List Operation Control Key is "External" AND "Lean Service" function is activated then Lean Service is mandatory.
Definition:
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PLMZ | PLNTY | PLNTY | Task List Type | CHAR | 1 | Mandatory |
| PLMZ | PLNNR | PLNNR | Task List Key | CHAR | 8 | Mandatory |
| PLPO | VORNR | VORNR | Activity Number | CHAR | 4 | Mandatory |
| STPO | IDNRK | IDNRK | Service Product Number | CHAR | 40 | Mandatory |
| MAKT | MAKTX | MAKTX | Material description | CHAR | 40 | System |
| STPO | POSTP | POSTP | Item category (bill of material) | 1 | System | |
| PLMZ | WERK_STL | WERKS_D | Plant | 4 | System | |
| PLMZ | IMENG | KMPMG | Component Quantity | 13 | Conditional | |
| PLMZ | IMEIN | KMPME | Component Unit of Measure | 3 | Conditional | |
| PLMZ | SERVICEDURATION | SERVICEDURATION | Service Duration | 5 | Conditional | |
| PLMZ | SERVICEDURATIONUNIT | SERVICEDURATIONUNIT | Service Duration Unit | 3 | Conditional | |
| STPO | EKORG | EKORG | Purchasing Organization | 4 | System | |
| STPO | EKGRP | EKGRP | Purchasing Group | 3 | System | |
| STPO | MATKL | MATKL | Material Group | 9 | System |
6.Task List Component
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PLMZ | PLNTY | PLNTY | Task List Type | CHAR | 1 | Mandatory |
| PLMZ | PLNNR | PLNNR | Task List Key | CHAR | 8 | Mandatory |
| PLPO | VORNR | VORNR | Activity Number | CHAR | 4 | Mandatory |
| PLPO | PLNKN | PLNKN | Number of the Task List Node | 8 | System | |
| STPO | IDNRK | IDNRK | Material Number | CHAR | 40 | Mandatory |
| STPO | MENGE | KMPMG | Component Quantity | 1 | Conditional | |
| STPO | MEINS | KMPME | Component Unit of Measure | 3 | Conditional | |
| PLMZ | RGEKZ | RGEKZ | Indicator: Backflush | 1 | Conditional | |
| PLMZ | DISP | DISP_PLUS_1 | Relevancy to Materials Planning/Generation of Purchase Req. | 1 | Conditional | |
| MAKT | MAKTX | MAKTX | Component Description | 40 | System | |
| PLMZ | WERK_STL | WERKS_D | Plant | 4 | Conditional | |
| STPO | EKGRP | EKGRP | Purchasing Group | 3 | Conditional | |
| STPO | EKORG | EKORG | Purchasing Organization | 4 | Conditional | |
| STPO | WAERS | WAERS | Currency Key | 5 | System | |
| STPO | PEINH | PEINH | Price unit | 5 | System | |
| STPO | MATKL | MATKL | Material Group | 9 | System | |
| PLMZ | LGORT | LGORT_RES | Issue Location for Production Order | 4 | Conditional | |
| STPO | LIFNR | LIFNR | Account Number of Supplier | 10 | Conditional | |
| MARC | WEBAZ | WEBAZ | Goods receipt processing time in days | 3 | System |
7.Maintenance Package
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PLWP | PLNTY | PLNTY | Task List Type | CHAR | 1 | Mandatory |
| PLWP | PLNNR | PLNNR | Task List Key | CHAR | 8 | Mandatory |
| PLPO | VORNR | VORNR | Activity Number | CHAR | 4 | Mandatory |
| PLWP | PLNAL | PLNAL | Group Counter | 2 | Mandatory | |
| PLWP | STRAT | STRAT | Maintenance Strategy | CHAR | 6 | Mandatory |
| PLWP | PAKET | PAKETZAEHL | Maintenance Package Number | NUMC | 2 | Mandatory |
| T351X | KZYK1 | KTEXTZYK | Short text for the maintenance cycle (time/performance) | CHAR | 2 | System |
7.Task List Class & Classification
a. Asset Specific Equipment
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| KLAH | CLASS | KLASSE_D | Class | CHAR | 18 | Conditional |
| AUSP | ATINN | ATINN | Characteristic - Asset Specific Equipment | NUMC | 10 | System |
| AUSP | ATWRT | ATWRT | Characteristic Value- Asset Specific Equipment | CHAR | 30 | Conditional |
b. Asset Specific Functional Location
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| KLAH | CLASS | KLASSE_D | Class | CHAR | 18 | Conditional |
| AUSP | ATINN | ATINN | Characteristic - Asset Specific Functional Location | NUMC | 10 | System |
| AUSP | ATWRT | ATWRT | Characteristic Value- Asset Specific Functional Location | CHAR | 30 | Conditional |
c. Old Task List No.
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| KLAH | CLASS | KLASSE_D | Class | CHAR | 18 | Conditional |
| AUSP | ATINN | ATINN | Characteristic - Old Task List No. | NUMC | 10 | System |
| AUSP | ATWRT | ATWRT | Characteristic Value - Old Task List No. | CHAR | 30 | Conditional |
Task List Data strictly adheres to the Master Data Standard. The complete information of the key fields that hold the Task List information follows the Master Data Standard document that is located here.
All data cleansing should take place in the data source system as defined in this document, unless system limitations prevent it.
If data cleansing is managed outside of the source system (e.g. Syniti Migrate, 3rd Party Vendor, DCT), the necessary documentation must be produced and appended to this deliverable for sign-off.
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
1005-001 | C1 | TL Header: Invalid, Inactive or no Operations attached to Active Task List Header | Task List Header as per Relevancy Criteria assigned with no or inactive Task List Operation attached. | Task List Type, Key for Task List Group, Activity Number | PF2, WP2 |
1005-002 | C2 | TL Header: Task lists not used within the last 3 years | Task List as per Relevancy Criteria but are not used across: | Task List Type, Key for Task List Group | PF2, WP2 |
1005-003 | C1 | TL Header-Description: Missing Task Lists Descriptions | Task List as per Relevancy Criteria where there are blank Task List Descriptions. | Task List Type, Key for Task List Group, Description | PF2, WP2 |
1005-004 | C2 | TL Header-Description: Task Lists Descriptions with Informal Words | Task List as per Relevancy Criteria which contain Informal Words in the Task List Description | Task List Type, Key for Task List Group, Description | PF2, WP2 |
1005-005 | C2 | TL Header-Task List Usage: Not '004'
| Task List as per Relevancy Criteria with Task List Usage <> '004' | Task List Type, Key for Task List Group, Task List Usage | PF2, WP2 |
1005-006 | C1 | TL Header-Status: Created but not released | TL Header STATU <> 2, 3, 4 | Task List Type, Key for Task List Group, Status | PF2, WP2 |
1005-007 | C1 | TL Header-Valid-From Date: Valid-From Date is in the future | TL Header Valid-From Date > current date | Task List Type, Key for Task List Group, Valid-From Date | PF2, WP2 |
1005-008 | C1 | TL Header-Work Centre: Invalid, Inactive or no Work Centres | Task List as per Relevancy Criteria assigned with a Work Centre which does not belong below: | Task List Type, Key for Task List Group, Work Centre | PF2, WP2 |
1005-009 | C1 | TL Header-Work Centre: Not mapped to new Work Centre | Task List as per Relevancy Criteria assigned with a Work Centre which is not mapped to new Work Centre | Task List Type, Key for Task List Group, Work Centre | PF2, WP2 |
1005-009 | C2 | TL Header: Long Text for cleansing | TL Header Long Text for cleansing | Task List Type, Key for Task List Group, | PF2, WP2 |
1005-010 | C1 | TL Operation: Active Task List Operations allocated to inactive Task List Headers | Task List Operation as per Relevancy Criteria assigned with no or inactive Task List Headers attached. | Task List Type, Key for Task List Group, Activity Number | PF2, WP2 |
1005-011 | C1 | TL Operation-Work Centre: Invalid, Inactive or no Work Centres | Task List as per Relevancy Criteria assigned with a Work Centre which does not belong below: 1. Work Centre as per Relevancy Criteria | Task List Type, Key for Task List Group, Activity Number, Work Centre | PF2, WP2 |
1005-012 | C1 | TL Operation-Work Centre: Not mapped to new Work Centre | Task List as per Relevancy Criteria assigned with a Work Centre which is not mapped to new Work Centre | Task List Type, Key for Task List Group, Activity Number, Work Centre | PF2, WP2 |
1005-013 | C1 | TL Operation-Unit for Work: Not 'H' | Task List Operation Unit for Work is not 'H'. This will need to convert to H as will be default to H in S4/HANA. | Task List Type, Key for Task List Group, Activity Number, Unit for Work | PF2, WP2 |
1005-014 | C1 | TL Operation: Active Task List Components allocated to inactive Task List Operation | Task List Component as per Relevancy Criteria assigned with no or inactive Task List Operations attached. | Task List Type, Key for Task List Group, Activity Number | PF2, WP2 |
1005-015 | C1 | TL Operation-Vendor: Invalid or inactive Business Partner (Vendor) linked to Task List | Task List as per Relevancy Criteria assigned with a Business Partner (Vendor) which does not belong below: | Task List Type, Key for Task List Group, Activity Number, Business Partner (Vendor) | PF2, WP2 |
| 1005-016 | C2 | TL Operation: Long Text for cleansing | TL Header Long Text for cleansing | Task List Type, Key for Task List Group, | PF2, WP2 |
| 1005-017 | C1 | TL Component-Material: Invalid, Inactive or no Material allocated | Task List as per Relevancy Criteria assigned with a Material which does not belong below: 1. Material Master (S2P) as per Relevancy Criteria | Task List Type, Key for Task List Group, Activity Number, Material Number | PF2, WP2 |
| 1005-018 | C1 | TL Component-Construction Type: Invalid, Inactive or no Construction Type allocated | Task List as per Relevancy Criteria assigned with a Construction Type which does not belong below: | Task List Type, Key for Task List Group, Activity Number, Construction Type | PF2, WP2 |
The high-level process is represented by the diagram below:

Collection will be done manually in the Data Collection Template for the following scenarios:
The high-level process for DCT is represented by the diagram below:

Extract data from a source into Syniti Migrate. There are 2 possibilities:
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
| Req # | Requirement Description | Team Responsible |
|---|---|---|
| 1 | Extract data from source system based on relevancy rule | SyWay Data Team |
| 2 | Google Sheet report pre-populated with PF2 and WP2 information to be generated based on relevancy criteria. | SyWay Data Team |
| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
| Not Applicable |
1.Task List Header Data Construction Rules
| Field Name | Field Description | Rule |
|---|---|---|
| zLegacyPLNNR | Legacy Task List Group | Mandatory. Key Field. |
| zLegacyPLNAL | Legacy Group Counter | Mandatory. Must be ascending sequential within the zLegacyPLNNR. Eg: 01, 02 etc |
| PROFIDNETZ | Profile | Conditional. Select profile to assign profile to task list else leave this field blank. Must reference active TCA41-PROFIDNETZ |
| KTEXT | Description | Mandatory. Description Rule:
Ensure that it does not include any of below characters: |
| IWERK | Planning Plant | Mandatory. Must reference Value Mapping: Plant (IWERK) |
| ARBPL | Work Centre group with planning function | Mandatory. Select manually the appropriate Work Centre |
| WERKS | Plant | Mandatory. Must reference Value Mapping: Plant (WERK, Where IWERK=IWERK) |
| VAGRP | Planner Group | Mandatory. Select manually the appropriate Planner Group |
| ANLZU | System Condition | Conditional. Must reference active Machine Operating Condition in config (T357M). Comments/Special handling notes: |
| STRAT | Maintenance Strategy | Conditional. For preventive task list, this field is required; select this field manually and activate the "Task List Maintenance Package Tab"; Must reference active Maintenance Strategy in config (T351) |
| ISTRU | Assembly | Conditional. If the task list is asset specific task list, this field should set to blank automatically. If not blank, must reference active Material (MARA) which are extended to Plant (MARC) |
| DELKZ | Indicator: Delete completely in reorganization run | Conditional. Mark "X" (checked) if Task List Header needs to be marked for deletion and will not be relevant to migration. |
2.Task List Header Long Text Line Data Construction Rules
| Field | Field Description | Rule |
|---|---|---|
| zSource | Source | Mandatory. Key Field. |
| zLegacyPLNNR | Legacy Key for Task List Group | Mandatory. Key to link to Task List Operation. |
| zLegacyPLNAL | Legacy Group Counter | Mandatory. Key to link to Task List Operation |
| TDSPRAS | Language Key | Mandatory Must be either one of the following: English(E) , French(F), Italian(I), Mandarin(1), Portuguese(including Brazilian Portuguese)(P), German(D) and Spanish(S) |
| CLUSTD_TAG | Tag column | Mandatory Free Text |
| CLUSTD_LINE | Text Line | Mandatory Free Text |
| Cleansed | Cleansing Done | Check box. Allowed values: Yes or No |
3.Task List Operation Data Construction Rules
| Field | Field Description | Rule |
|---|---|---|
| zSource | Source | Mandatory. Key Field. |
| zLegacyPLNNR | Legacy Key for Task List Group | Mandatory. Key to link to Task List Operation. |
| zLegacyPLNAL | Legacy Group Counter | Mandatory. Key to link to Task List Operation |
| zLegacyVORNR | Legacy Activity Number | Mandatory. Key to link to Task List Operation |
| TDSPRAS | Language Key | Mandatory Must be either one of the following: English(E) , French(F), Italian(I), Mandarin(1), Portuguese(including Brazilian Portuguese)(P), German(D) and Spanish(S) |
| CLUSTD_TAG | Tag column | Mandatory Free Text |
| CLUSTD_LINE | Text Line | Mandatory Free Text |
| Cleansed | Cleansing Done | Check box. Allowed values: Yes or No |
4.Task List Operation Data Construction Rules
Definition:
| Field Name | Field Description | Rule |
|---|---|---|
| zLegacyPLNNR | Legacy Task List Group | Mandatory. Key to link to Task List Header |
| zLegacyPLNAL | Legacy Group Counter | Mandatory. Key to link to Task List Header. Must be unique within the same zLegacyPLNNR. Eg: 01, 02 etc |
| zLegacyVORNR | Legacy Activity Number | Mandatory. Must be unique within the same zLegacyPLNNR Eg: 0010, 0020 etc |
| ARBPL | Work Centre | Mandatory. |
| WERKS | Plant | Mandatory. Must match the Plant of the associated Task List Header Must reference active plant in config (T001W) |
| LTXA1 | Operation Description | Mandatory. Ensure that it does not include any of below characters: |
| AUFKT | Execution Factor | Conditional. Numeric values only |
| ARBEI | Work Involved in the Activity | Mandatory. |
| ANZZL | Number of Capacities Required | Mandatory. Numeric values only |
| VERTN | Distr.cap.reqmts | Conditional. Must reference active Distribution Function in config (TC29) |
| ANLZU | System Condition | Conditional. Must reference active Machine operating condition in config (T357M). Comments/Special handling notes: |
| EXECUTION_STAGE | PRE MAIN POST | Conditional. Allowed value: "PRE", "MAIN", "POST" If the user does not select a value, this will be set to "MAIN" |
| BMVRG | Order Quantity | Conditional. If the Control Key is "External", this field is required. Otherwise, leave blank. |
| BMEIH | Order Quantity Unit | Conditional. If the Control Key is "External", this field is required. Otherwise, leave blank. If not blank, must reference active Units of Measurement in config (T006) |
| PLIFZ | Planned Delivery Time in Days | Conditional. If the Control Key is "External", this field is optional. Otherwise, leave blank. |
| FRDLB | Indicator: External Processing Operation with Subcontracting | Conditional. If the Control Key is "External", this field is optional. Otherwise, leave blank. |
| SAKTO | Cost Element | Conditional. If the Control Key is "External", this field is required. Otherwise, leave blank. |
| MATKL | Material Group | Conditional. If the Control Key is "External", this field is required. Otherwise, leave blank. |
| EKGRP | Purchasing Group | Conditional. If the Control Key is "External", this field is required. Otherwise, leave blank. If not blank, must reference active Purchasing Groups in config (T024) |
| LIFNR | Vendor | Conditional. If the Control Key is "External", this field is optional. Otherwise, leave blank. If not blank, must reference active Vendor (LFA1) |
| EKORG | Purchasing Organization | Conditional. If the Control Key is "External", this field is required. Otherwise, leave blank. If not blank, must reference active Purchasing Organizations in config (T024E) |
| EBELN | Purchasing Agreement | Conditional. 1st If the operation control key is "External", this field is available. Otherwise, leave this field non editable. If the user provides a value, accept it. If not, leave the field blank. If not blank, must reference active Purchasing Document Item (EKPO-EBELN) |
| EBELP | Purchasing Agreement Item | Conditional. 1st If the operation control key is "External", this field is available. Otherwise, leave this field non editable. If the user provides a value, accept it. If not, leave the field blank. If not blank, must reference active Purchasing Document Item (EKPO-EBELP) |
5.Task List Operation Long Text Line Data Construction Rules
| Field | Field Description | Rule |
|---|---|---|
| zSource | Source | Mandatory. Key Field. |
| zLegacyPLNNR | Legacy Key for Task List Group | Mandatory. Key to link to Task List Operation. |
| zLegacyPLNAL | Legacy Group Counter | Mandatory. Key to link to Task List Operation |
| zLegacyVORNR | Legacy Activity Number | Mandatory. Key to link to Task List Operation |
| TDSPRAS | Language Key | Mandatory Must be either one of the following: English(E) , French(F), Italian(I), Mandarin(1), Portuguese(including Brazilian Portuguese)(P), German(D) and Spanish(S) |
| CLUSTD_TAG | Tag column | Mandatory Free Text |
| CLUSTD_LINE | Text Line | Mandatory Free Text |
| Cleansed | Cleansing Done | Check box. Allowed values: Yes or No |
6.Task List Operation Lean Service Data Construction Rules
Note: If the Task List Operation Control Key is "External" AND "Lean Service" function is activated then Lean Service is mandatory.
Definition:
| Field Name | Field Description | Rule |
|---|---|---|
| zLegacyPLNNR | Legacy Task List Group | Mandatory. Key to link to Task List Operation |
| zLegacyPLNAL | Legacy Group Counter | Mandatory. Key to link to Task List Operation |
| zLegacyVORNR | Legacy Activity Number | Mandatory. Key to link to Task List Operation |
| IDNRK | Service Product Number | Mandatory.
Must reference active Material (MARA) which are extended to Plant (MARC) |
| MAKTX | Material description | Not editable. Automatically populated (Derive from MARA-MAKTX where IDNRK=MARA-MATNR) |
| IMENG | Component Quantity | Mandatory. Positive numeric values only |
| SERVICEDURATION | Service Duration | If the user provides a value, accept it. If not, leave the field blank. |
| SERVICEDURATIONUNIT | Service Duration Unit | If the user provides a value, accept it. If not, leave the field blank. |
7.Task List Component Data Construction Rules
| Field Name | Field Description | Rule |
|---|---|---|
| zLegacyPLNNR | Legacy Task List Group | Mandatory. Key to link to Task List Operation |
| zLegacyPLNAL | Legacy Group Counter | Mandatory. Key to link to Task List Operation |
| zLegacyVORNR | Legacy Activity Number | Mandatory. Key to link to Task List Operation |
| IDNRK | Material Number | Mandatory.
Must reference active Material (MARA) which are extended to Plant (MARC) |
| MENGE | Component Quantity | Mandatory. Positive numeric values only |
| MEINS | Component Unit of Measure | Non Editable. Derive from MARA-MEINS where IDNRK=MARA-MATNR *This field is needed for MENGE to make sense |
| RGEKZ | Indicator: Backflush |
8.Maintenance Package Data Construction Rules
| Field Name | Field Description | Rule |
|---|---|---|
| zLegacyPLNNR | Legacy Task List Group | Mandatory. Key to link to Task List Operation |
| zLegacyPLNAL | Legacy Group Counter | Mandatory. Key to link to Task List Operation |
| zLegacyVORNR | Legacy Activity Number | Mandatory. Key to link to Task List Operation |
| STRAT | Maintenance Strategy | Non editable. Direct Mapping from Task List Header: STRAT field |
| PAKET | Maintenance Package Number | Mandatory. ) where STRAT= |
KZYK1 | Short text for the maintenance cycle (time/performance) |
9.Task List Class & Classification Data Construction Rules
a. Asset Specific Functional Location
| Field Name | Field Description | Rule |
|---|---|---|
| zLegacyPLNNR | Legacy Task List Group | Mandatory. Key to link to Task List Operation |
| zLegacyPLNAL | Legacy Group Counter | Mandatory. Key to link to Task List Operation |
| CLASS | Class |
|
| ATNAM | Characteristic - Asset Specific Equipment | Default characteristic with description "Asset Specific Equipment" |
| ATWRT | Characteristic Value- Asset Specific Equipment | If the task list is equipment specific, this field is required. If not, leave this field blank. For asset specific task list, if this equipment value is blank, the functional location value should not be blank. |
b. Asset Specific Functional Location
| Field Name | Field Description | Rule |
|---|---|---|
| zLegacyPLNNR | Legacy Task List Group | Mandatory. Key to link to Task List Operation |
| zLegacyPLNAL | Legacy Group Counter | Mandatory. Key to link to Task List Operation |
| CLASS | Class |
|
| ATNAM | Characteristic - Asset Specific Functional Location | Default characteristic with description "Asset Specific Functional Location" |
| ATWRT | Characteristic Value- Asset Specific Functional Location | If the task list is functional location specific, this field is required. If not, leave this field blank. For asset specific task list, if this functional location value is blank, the equipment value should not be blank. |
c. Old Task List No.
| Field Name | Field Description | Rule |
|---|---|---|
| zLegacyPLNNR | Legacy Task List Group | Mandatory. Key to link to Task List Operation |
| zLegacyPLNAL | Legacy Group Counter | Mandatory. Key to link to Task List Operation |
| CLASS | Class |
|
| ATNAM | Characteristic - Asset Specific Functional Location | Default characteristic with description "Old Task List No." |
| ATWRT | Characteristic Value- Asset Specific Functional Location | For legacy data migration, this field is Required. For new data, this field is Not Used. |
Reference for Characteristics here.
List the steps that need to occur before extraction can commence
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1 | Ensure Syniti has the necessary connection and access to legacy servers | SyWay A2D Data Team |
| 2 | Ensure that the necessary cleansing activities in legacy sources are complete | SyWay A2D Data Team / Business |
| 3 | Ensure that create, change and deletion of master data is freeze in legacy Production system | Legacy IT |
| 4 | Ensure that extraction for the following objects are completed: Bill of Material, Equipment, Functional Location, Construction Types/Assemblies, Maintenance Plan and Item, Maintenance Strategy, Material Master and Vendors, Work Order | SyWay A2D Data Team |
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1 | Obtain DCT Sign-off from Business | SyWay A2D Data Team |
| 2 | In dspMigrate, select the wave – S4/HANA – Plant Maintenance | Syniti |
| 3 | Go to Process Area Launch and Process the Object – Task List | Syniti |
| 4 | Review and Validate Error and Preload Reports | Syniti |
| 5 | Execute the transformation to prepare the target tables | Syniti |
| 6 | Validate data from pre-load and error reports | Business/Data owner |
| 7 | Generate load files | SyWay Data Team |
Transformation Rules
1.Task List Header Transformation Rule (ECC)
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | PF2, WP2 | PLKO | PLNTY | Task List Type | S/4HANA | PLKO | zLegacyPLNTY | Legacy Task List Type | Direct Mapping |
| 2 | PF2, WP2 | PLKO | PLNNR | Key for Task List Group | S/4HANA | PLKO | zLegacyPLNNR | Legacy Key for Task List Group | Direct Mapping |
| 3 | PF2, WP2 | PLKO | PLNAL | Group Counter | S/4HANA | PLKO | zLegacyPLNAL | Legacy Group Counter | Direct Mapping |
| 4 | PF2, WP2 | PLKO | DATUV | Valid-From Date | S/4HANA | PLKO | DATUV | Valid-From Date | Derive the date as per Value Mapping: OTH_Migration_Date Relevant Values A2D (using Object ID "1005" and Field Name = "PLKO-DATUV". |
| 5 | PF2, WP2 | PLKO | KTEXT | Description | S/4HANA | PLKO | KTEXT | Description | Direct Mapping. |
| 6 | PF2, WP2 | PLKO | IWERK | Planning Plant | S/4HANA | PLKO | WERKS | Planning Plant | Value Mapping: Plant |
| 7 | DCT | PLKO | IWERK | Planning Plant | S/4HANA | PLKO | WERKS | Planning Plant | Direct Mapping |
| 8 | PF2, WP2 | CRHD | ARBPL | Work Centre | S/4HANA | PLKO | ARBPL | Work Centre | Value Mapping: Work Centre |
| 9 | PF2, WP2 | PLKO | VERWE | Task List Usage | S/4HANA | PLKO | VERWE | Task List Usage | Default to "004" |
| 10 | PF2, WP2 | PLKO | VAGRP | Planner Group | S/4HANA | PLKO | VAGRP | Planner Group | Value Mapping: Planner Group |
| 11 | PF2, WP2 | PLKO | STATU | Overall Status | S/4HANA | PLKO | STATU | Overall Status | Default to 4 |
| 12 | PF2, WP2 | PLKO | ANLZU | System Condition | S/4HANA | PLKO | ANLZU | System Condition | Value Mapping: System Condition |
| 13 | PF2, WP2 | PLKO | STRAT | Maintenance Strategy | S/4HANA | PLKO | STRAT | Maintenance Strategy | Value Mapping: Maintenance Strategy |
| 14 | PF2, WP2 | PLKO | ISTRU | Assembly | S/4HANA | PLKO | ISTRU | Assembly |
|
| 15 | PF2, WP2 | CRHD | ARBPL | Work Centre | S/4HANA | CRHD | ARBPL | Work Centre | Value Mapping: Work Centre |
| 16 | PF2, WP2 | PLKO | WERKS | Plant | S/4HANA | PLPO | WERKS | Plant | Direct Mapping |
| 17 | |||||||||
| 18 | |||||||||
| 19 | |||||||||
| 20 | |||||||||
| 21 | |||||||||
| 22 | |||||||||
| 23 | |||||||||
| 24 | |||||||||
| 25 | |||||||||
| 26 | |||||||||
| 27 | |||||||||
| 28 | PF2, WP2 | PLWP | PLNTY | Task List Type | S/4HANA | PLWP | PLNTY | Task List Type | Direct Mapping |
| 29 | PF2, WP2 | PLWP | PLNNR | Task List Key | S/4HANA | PLWP | PLNNR | Task List Key | Direct Mapping |
| 30 | PF2, WP2 | PLWP | PLNAL | Group Counter | S/4HANA | PLWP | PLNAL | Group Counter | Direct Mapping |
| 31 | PF2, WP2 | PLWP | PLNKN | Number of the Task List Node | S/4HANA | PLWP | PLNKN | Number of the Task List Node | Direct Mapping |
| 32 | PF2, WP2 | PLWP | STRAT | Maintenance Strategy | S/4HANA | PLWP | STRAT | Maintenance Strategy | Value Mapping: Maintenance Strategy |
| 33 | PF2, WP2 | PLWP | PAKET | Maintenance Package Number | S/4HANA | PLWP | PAKET | Maintenance Package Number | Value Mapping: Maintenance Package |
| 34 | PF2, WP2 | T351X | KZYK1 | Short text for the maintenance cycle (time/performance) | S/4HANA | T351X | KZYK1 | Short text for the maintenance cycle (time/performance) | Direct Mapping |
1.Task List Header Transformation Rule (DCT)
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | DCT | PLKO | zLegacyPLNTY | Legacy Task List Type | S/4HANA | PLKO | zLegacyPLNTY | Legacy Task List Type | Default to 'A' |
| 2 | DCT | PLKO | zLegacyPLNNR | Legacy Key for Task List Group | S/4HANA | PLKO | zLegacyPLNNR | Legacy Key for Task List Group | Direct Mapping |
| 3 | DCT | PLKO | KTEXT | Description | S/4HANA | PLKO | KTEXT | Description | Direct Mapping |
| 4 | DCT | PLKO | ARBPL | Work Centre | S/4HANA | PLKO | ARBPL | Work Centre | Direct Mapping |
| 5 | DCT | PLKO | VERWE | Task List Usage | S/4HANA | PLKO | VERWE | Task List Usage | Default to "004" |
| 6 | DCT | PLKO | VAGRP | Planner Group | S/4HANA | PLKO | VAGRP | Planner Group | Direct Mapping |
| 7 | DCT | PLKO | STATU | Overall Status | S/4HANA | PLKO | STATU | Overall Status | Default to 4 |
| 8 | DCT | PLKO | ANLZU | System Condition | S/4HANA | PLKO | ANLZU | System Condition | Direct Mapping |
| 9 | DCT | PLKO | STRAT | Maintenance Strategy | S/4HANA | PLKO | STRAT | Maintenance Strategy | Direct Mapping |
| 10 | DCT | PLKO | ISTRU | Assembly | S/4HANA | PLKO | ISTRU | Assembly | Direct Mapping |
2.Task List Operation Transformation Rule (ECC)
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | PF2, WP2 | PLPO | PLNTY | Task List Type | S/4HANA | PLPO | zLegacyPLNTY | Legacy Task List Type | Direct Mapping |
| 2 | PF2, WP2 | PLPO | PLNNR | Key for Task List Group | S/4HANA | PLPO | zLegacyPLNNR | Legacy Key for Task List Group | Direct Mapping |
| 3 | PF2, WP2 | PLPO | VORNR | Activity Number | S/4HANA | PLPO | zLegacyVORNR | Legacy Activity Number | Direct Mapping |
| 4 | PF2, WP2 | CRHD | ARBPL | Work Centre | S/4HANA | CRHD | ARBPL | Work Centre | Value Mapping: Work Centre |
| 5 | - | - | - | - | S/4HANA | PLPO | STEUS | Control Key | Derive from CRHD-STEUS based on the associated Work Centre |
| 6 | PF2, WP2 | PLPO | LTXA1 | Operation Description | S/4HANA | PLPO | LTXA1 | Operation Description | Direct Mapping |
| 7 | PF2, WP2 | PLPO | ARBEI | Work Involved in the Activity | S/4HANA | PLPO | ARBEIT | Work Involved in the Activity | Direct Mapping |
| 8 | PF2, WP2 | PLPO | ARBEH | Unit for Work | S/4HANA | PLPO | ARBEH | Unit for Work | Default to "H" |
| 9 | PF2, WP2 | PLPO | ANZZL | Number of Capacities Required | S/4HANA | PLPO | ANZZL | Number of Capacities Required | Direct Mapping |
| 10 | PF2, WP2 | PLPO | INDET | Key for calculation | S/4HANA | PLPO | INDET | Key for calculation | Default to "1" |
| 11 | PF2, WP2 | PLPO | PRZNT | Work Percentage | S/4HANA | PLPO | PRZNT | Work Percentage | Default to "100" |
| 12 | PF2, WP2 | PLPO | VERTL | Distribution function for capacity requirements | S/4HANA | PLPO | VERTL | Distribution function for capacity requirements | Direct Mapping |
| 13 | PF2, WP2 | PLPO | AUFKT | Execution Factor | S/4HANA | PLPO | AUFKT | Execution Factor | Direct Mapping |
| 14 | PF2, WP2 | PLPO | ANLZU | System Condition | S/4HANA | PLPO | ANLZU | System Condition | Value Mapping: System Condition |
| 15 | PF2, WP2 | PLPO | EXECUTION_STAGE | PRE MAIN POST | S/4HANA | PLPO | EXECUTION_STAGE | PRE MAIN POST | Direct Mapping. Default to "MAIN" if blank |
| 16 | PF2, WP2 | PLPO | BMVRG | Order Quantity | S/4HANA | PLPO | BMVRG | Order Quantity | Direct Mapping |
| 17 | PF2, WP2 | PLPO | BMEIH | Order Quantity Unit | S/4HANA | PLPO | BMEIH | Order Quantity Unit | Direct Mapping |
| 18 | PF2, WP2 | PLPO | PLIFZ | Planned Delivery Time in Days | S/4HANA | PLPO | PLIFZ | Planned Delivery Time in Days | Direct Mapping |
| 19 | PF2, WP2 | PLPO | FRDLB | Indicator: External Processing Operation with Subcontracting | S/4HANA | PLPO | FRDLB | Indicator: External Processing Operation with Subcontracting | Direct Mapping |
| 20 | PF2, WP2 | PLPO | SAKTO | Cost Element | S/4HANA | PLPO | SAKTO | Cost Element | Value Mapping: Cost Element |
| 21 | PF2, WP2 | PLPO | MATKL | Material Group | S/4HANA | PLPO | MATKL | Material Group | Value Mapping: Material Group |
| 22 | DCT | PLPO | MATKL | Material Group | S/4HANA | PLPO | MATKL | Material Group | Direct Mapping |
| 23 | PF2, WP2 | PLPO | EKGRP | Purchasing Group | S/4HANA | PLPO | EKGRP | Purchasing Group | Value Mapping: Purchasing Group |
| 24 | PF2, WP2 | PLPO | LIFNR | Vendor | S/4HANA | PLPO | LIFNR | Vendor | Value Mapping: Vendor Number |
| 25 | PF2, WP2 | PLPO | EKORG | Purchasing Organization | S/4HANA | PLPO | EKORG | Purchasing Organization | Value Mapping: Purchasing Organization |
| 26 | PF2, WP2 | PLPO | EBELN | Purchasing Agreement | S/4HANA | PLPO | EBELN | Purchasing Agreement | Direct Mapping |
| 27 | PF2, WP2 | PLPO | EBELP | Purchasing Agreement Item | S/4HANA | PLPO | EBELP | Purchasing Agreement Item | Direct Mapping |
2.Task List Operation Transformation Rule (DCT)
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | DCT | PLPO | zLegacyPLNTY | Legacy Task List Type | S/4HANA | PLPO | zLegacyPLNTY | Legacy Task List Type | Direct Mapping |
| 2 | DCT | PLPO | zLegacyPLNNR | Legacy Key for Task List Group | S/4HANA | PLPO | zLegacyPLNNR | Legacy Key for Task List Group | Direct Mapping |
| 3 | DCT | PLMZ | zLegacyVORNR | Legacy Activity Number | S/4HANA | PLMZ | zLegacyVORNR | Legacy Activity Number | Direct Mapping |
| 4 | DCT | CRHD | ARBPL | Work Centre | S/4HANA | CRHD | ARBPL | Work Centre | Direct Mapping |
| 5 | DCT | PLKO | WERKS | Plant | S/4HANA | PLPO | WERKS | Plant | Direct Mapping |
| 6 | - | - | - | - | S/4HANA | PLPO | STEUS | Control Key | Derive from CRHD-STEUS based on the associated Work Centre |
| 7 | DCT | PLPO | LTXA1 | Operation Description | S/4HANA | PLPO | LTXA1 | Operation Description | Direct Mapping |
| 8 | DCT | PLPO | ARBEI | Work Involved in the Activity | S/4HANA | PLPO | ARBEIT | Work Involved in the Activity | Direct Mapping |
| 9 | DCT | PLPO | ARBEH | Unit for Work | S/4HANA | PLPO | ARBEH | Unit for Work | Default to "H" |
| 10 | DCT | PLPO | ANZZL | Number of Capacities Required | S/4HANA | PLPO | ANZZL | Number of Capacities Required | Direct Mapping |
| 11 | DCT | PLPO | INDET | Key for calculation | S/4HANA | PLPO | INDET | Key for calculation | Default to "1" |
| 12 | DCT | PLPO | PRZNT | Work Percentage | S/4HANA | PLPO | PRZNT | Work Percentage | Default to "100" |
| 13 | DCT | PLPO | VERTL | Distribution function for capacity requirements | S/4HANA | PLPO | VERTL | Distribution function for capacity requirements | Direct Mapping |
| 14 | DCT | PLPO | AUFKT | Execution Factor | S/4HANA | PLPO | AUFKT | Execution Factor | Direct Mapping |
| 15 | DCT | PLPO | ANLZU | System Condition | S/4HANA | PLPO | ANLZU | System Condition | Value Mapping: System Condition |
| 16 | DCT | PLPO | EXECUTION_STAGE | PRE MAIN POST | S/4HANA | PLPO | EXECUTION_STAGE | PRE MAIN POST | Direct Mapping. Default to "MAIN" if blank |
| 17 | DCT | PLPO | BMVRG | Order Quantity | S/4HANA | PLPO | BMVRG | Order Quantity | Direct Mapping |
| 18 | DCT | PLPO | BMEIH | Order Quantity Unit | S/4HANA | PLPO | BMEIH | Order Quantity Unit | Direct Mapping |
| 19 | DCT | PLPO | PLIFZ | Planned Delivery Time in Days | S/4HANA | PLPO | PLIFZ | Planned Delivery Time in Days | Direct Mapping |
| 20 | DCT | PLPO | FRDLB | Indicator: External Processing Operation with Subcontracting | S/4HANA | PLPO | FRDLB | Indicator: External Processing Operation with Subcontracting | Direct Mapping |
| 21 | DCT | PLPO | SAKTO | Cost Element | S/4HANA | PLPO | SAKTO | Cost Element | Value Mapping: Cost Element |
| 22 | DCT | PLPO | MATKL | Material Group | S/4HANA | PLPO | MATKL | Material Group | Value Mapping: Material Group |
| 23 | DCT | PLPO | MATKL | Material Group | S/4HANA | PLPO | MATKL | Material Group | Direct Mapping |
| 24 | DCT | PLPO | EKGRP | Purchasing Group | S/4HANA | PLPO | EKGRP | Purchasing Group | Value Mapping: Purchasing Group |
| 25 | DCT | PLPO | LIFNR | Vendor | S/4HANA | PLPO | LIFNR | Vendor | Value Mapping: Vendor Number |
| 26 | DCT | PLPO | EKORG | Purchasing Organization | S/4HANA | PLPO | EKORG | Purchasing Organization | Value Mapping: Purchasing Organization |
| 27 | DCT | PLPO | EBELN | Purchasing Agreement | S/4HANA | PLPO | EBELN | Purchasing Agreement | Direct Mapping |
| 28 | DCT | PLPO | EBELP | Purchasing Agreement Item | S/4HANA | PLPO | EBELP | Purchasing Agreement Item | Direct Mapping |
3.Task List Operation Long Text Header Transformation Rule
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | DCT | PLPO | PLNTY | Task List Type | S/4HANA | PLPO | PLNTY | Task List Type | Direct Mapping |
| 2 | DCT | PLPO | PLNNR | Key for Task List Group | S/4HANA | PLPO | PLNNR | Key for Task List Group | Direct Mapping |
| 3 | DCT | PLPO | VORNR | Activity Number | S/4HANA | PLPO | VORNR | Activity Number | Direct Mapping |
| 4 | DCT | STXH | TDOBJECT | Texts: application object | S/4HANA | STXH | TDOBJECT | Texts: application object | Direct Mapping |
| 5 | DCT | STXH | TDOBNAME | Name | S/4HANA | STXH | TDOBNAME | Name | Direct Mapping |
| 6 | DCT | STXH | TDID | Text ID | S/4HANA | STXH | TDID | Text ID | Direct Mapping |
| 7 | DCT | STXH | SPRAS | Language Key | S/4HANA | STXH | SPRAS | Language Key | Direct Mapping |
4.Task List Operation Long Text Line Transformation Rule
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | DCT | PLPO | PLNTY | Task List Type | S/4HANA | PLPO | PLNTY | Task List Type | Direct Mapping |
| 2 | DCT | PLPO | PLNNR | Key for Task List Group | S/4HANA | PLPO | PLNNR | Key for Task List Group | Direct Mapping |
| 3 | DCT | PLPO | VORNR | Activity Number | S/4HANA | PLPO | VORNR | Activity Number | Direct Mapping |
| 4 | - | - | - | - | S/4HANA | STXH | TDOBJECT | Texts: application object | Default to 'ROUTING' |
| 5 | - | - | - | - | S/4HANA | STXH | TDOBNAME | Name | Character 1-3: Direct Mapping to Client Number (eg 100) Character 4: Direct Mapping to zLegacyPLNTY (eg A, E or T) Character 5-12: Direct Mapping to zLegacyPLNNR (eg 00000001, 00000002) Character 13-20: Direct Mapping to zLegacyPLNKN (eg 00000001, 00000002) Character 21-28: Direct Mapping to zLegacyZAEHL (eg 00000001, 00000002) Example: "100A000000010000000100000001" , "100A000000010000000200000002" |
| 6 | - | - | - | - | S/4HANA | STXH | TDID | Text ID | Default to 'LTXT' |
| 7 | DCT | STXH | SPRAS | Language Key | S/4HANA | STXH | SPRAS | Language Key | Direct Mapping |
| 8 | DCT | STXL | CLUSTD_TAG | Tag column | S/4HANA | STXL | CLUSTD_TAG | Tag column | Direct Mapping |
| 9 | DCT | STXL | CLUSTD_LINE | Text Line | S/4HANA | STXL | CLUSTD_LINE | Text Line | Direct Mapping |
5.Task List Operation Lean Service Transformation Rule (ECC)
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | PF2, WP2 | PLKO | PLNTY | Task List Type | S/4HANA | PLKO | zLegacyPLNTY | Legacy Task List Type | Direct Mapping |
| 2 | PF2, WP2 | STPO | IDNRK | Service Product Number | S/4HANA | STPO | IDNRK | Service Product Number | Direct Mapping |
| 3 | PF2, WP2 | MAKT | MAKTX | Material Description | S/4HANA | MAKT | MAKTX | Material Description | Direct Mapping |
| 4 | PF2, WP2 | - | - | - | S/4HANA | STPO | POSTP | Item category (bill of material) | Default to 'N' |
| 5 | PF2, WP2 | PLMZ | IMENG | Component Quantity | S/4HANA | PLMZ | IMENG | Component Quantity | Direct Mapping |
| 6 | PF2, WP2 | PLMZ | SERVICEDURATION | Service Duration | S/4HANA | PLMZ | SERVICEDURATION | Service Duration | Direct Mapping |
| 7 | PF2, WP2 | PLMZ | SERVICEDURATIONUNIT | Service Duration Unit | S/4HANA | PLMZ | SERVICEDURATIONUNIT | Service Duration Unit | Direct Mapping |
5.Task List Operation Lean Service Transformation Rule (DCT)
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | DCT | PLPO | zLegacyPLNTY | Legacy Task List Type | S/4HANA | PLPO | zLegacyPLNTY | Legacy Task List Type | Direct Mapping |
| 2 | DCT | PLPO | zLegacyPLNNR | Legacy Task List Group | S/4HANA | PLPO | zLegacyPLNNR | Legacy Task List Group | Direct Mapping |
| 3 | DCT | PLPO | zLegacyPLNAL | Legacy Group Counter | S/4HANA | PLPO | zLegacyPLNAL | Legacy Group Counter | Direct Mapping |
| 4 | DCT | PLPO | zLegacyVORNR | Legacy Activity Number | S/4HANA | PLPO | zLegacyVORNR | Legacy Activity Number | Direct Mapping |
| 5 | DCT | STPO | IDNRK | Service Product Number | S/4HANA | STPO | IDNRK | Service Product Number | Direct Mapping |
| 6 | DCT | MAKT | MAKTX | Material Description | S/4HANA | MAKT | MAKTX | Material Description | Direct Mapping |
| 7 | - | - | - | - | S/4HANA | STPO | POSTP | Item category (bill of material) | Default to 'N' |
| 8 | DCT | PLMZ | IMENG | Component Quantity | S/4HANA | PLMZ | IMENG | Component Quantity | Direct Mapping |
| 9 | DCT | PLMZ | SERVICEDURATION | Service Duration | S/4HANA | PLMZ | SERVICEDURATION | Service Duration | Direct Mapping |
| 10 | DCT | PLMZ | SERVICEDURATIONUNIT | Service Duration Unit | S/4HANA | PLMZ | SERVICEDURATIONUNIT | Service Duration Unit | Direct Mapping |
6.Task List Component Transformation Rule (ECC)
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | PF2, WP2 | PLMZ | PLNTY | Task List Type | S/4HANA | PLMZ | zLegacyPLNTY | Legacy Task List Type | Direct Mapping |
| 2 | PF2, WP2 | PLMZ | PLNNR | Task List Group | S/4HANA | PLMZ | zLegacyPLNNR | Legacy Task List Group | Direct Mapping |
| 3 | PF2, WP2 | PLMZ | PLNAL | Group Counter | S/4HANA | PLMZ | zLegacyPLNAL | Legacy Group Counter | Direct Mapping |
| 4 | PF2, WP2 | PLMZ | VORNR | Activity Number | S/4HANA | PLMZ | zLegacyVORNR | Legacy Activity Number | Direct Mapping |
| 5 | PF2, WP2 | STPO | IDNRK | Material Number | S/4HANA | STPO | IDNRK | Material Number | |
| 6 | PF2, WP2 | PLMZ | IMENG | Component Quantity | S/4HANA | PLMZ | IMENG | Component Quantity | |
| 7 | PF2, WP2 | PLMZ | IMEIN | Component Unit of Measure | S/4HANA | PLMZ | IMEIN | Component Unit of Measure | |
| 8 | PF2, WP2 | PLMZ | RGEKZ | Indicator: Backflush | S/4HANA | PLMZ | RGEKZ | Indicator: Backflush | |
| 9 | PF2, WP2 | PLMZ | VORNR | Activity Number | Direct Mapping | PLMZ | VORNR | Activity Number | |
| 10 | PF2, WP2 | PLMZ | IMENG | Component Quantity | S/4HANA | PLMZ | IMENG | Component Quantity | Direct Mapping |
| 11 | PF2, WP2 | PLMZ | IMEIN | Component Unit of Measure | S/4HANA | PLMZ | IMEIN | Component Unit of Measure | Direct Mapping |
| 12 | PF2, WP2 | PLMZ | RGEKZ | Indicator: Backflush | S/4HANA | PLMZ | RGEKZ | Indicator: Backflush | Direct Mapping |
| 13 | PF2, WP2 | PLMZ | DISP | Relevancy to Materials Planning/Generation of Purchase Req. | S/4HANA | PLMZ | DISP | Relevancy to Materials Planning/Generation of Purchase Req. | Direct Mapping |
| 14 | PF2, WP2 | PLMZ | WERK_STL | Plant | S/4HANA | PLMZ | WERK_STL | Plant | Value Mapping: Plant Mapping |
| 15 | DCT | PLMZ | WERK_STL | Plant | S/4HANA | PLMZ | WERK_STL | Plant | Direct Mapping |
| 16 | PF2, WP2 | STPO | EKGRP | Purchasing Group | S/4HANA | STPO | EKGRP | Purchasing Group | Value Mapping: Purchasing Group |
| 17 | DCT | STPO | EKGRP | Purchasing Group | S/4HANA | STPO | EKGRP | Purchasing Group | Direct Mapping |
| 18 | PF2, WP2 | STPO | EKORG | Purchasing Organization | S/4HANA | STPO | EKORG | Purchasing Organization | Value Mapping: Purchasing Organization |
| 19 | PF2, WP2 | PLMZ | LGORT | Issue Location for Production Order | S/4HANA | PLMZ | LGORT | Issue Location for Production Order | Default to MARC-LGPRO |
| 20 | PF2, WP2 | STPO | LIFNR | Account Number of Supplier | S/4HANA | STPO | LIFNR | Account Number of Supplier | Value Mapping: Vendor Number |
6.Task List Component Transformation Rule (DCT)
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | DCT | PLMZ | zLegacyPLNTY | Legacy Task List Type | S/4HANA | PLPO | PLNTY | Task List Type | Direct Mapping |
| 2 | DCT | PLMZ | zLegacyPLNNR | Legacy Task List Group | S/4HANA | PLPO | PLNNR | Task List Group | Direct Mapping |
| 3 | DCT | PLMZ | zLegacyPLNAL | Legacy Group Counter | S/4HANA | PLPO | PLNAL | Group Counter | Direct Mapping |
| 4 | DCT | PLMZ | zLegacyVORNR | Legacy Activity Number | S/4HANA | PLPO | VORNR | Activity Number | Direct Mapping |
| 5 | DCT | STPO | IDNRK | Material Number | S/4HANA | STPO | IDNRK | Material Number | Direct Mapping |
| 6 | DCT | PLMZ | IMENG | Component Quantity | S/4HANA | PLMZ | IMENG | Component Quantity | Direct Mapping |
| 7 | DCT | PLMZ | IMEIN | Component Unit of Measure | S/4HANA | PLMZ | IMEIN | Component Unit of Measure | Direct Mapping |
| 8 | DCT | PLMZ | RGEKZ | Indicator: Backflush | S/4HANA | PLMZ | RGEKZ | Indicator: Backflush | Direct Mapping |
| 9 | DCT | PLMZ | DISP | Relevancy to Materials Planning/Generation of Purchase Req. | S/4HANA | PLMZ | DISP | Relevancy to Materials Planning/Generation of Purchase Req. | Direct Mapping |
| 10 | DCT | PLMZ | WERK_STL | Plant | S/4HANA | PLMZ | WERK_STL | Plant | Direct Mapping |
| 11 | DCT | PLMZ | WERK_STL | Plant | S/4HANA | PLMZ | WERK_STL | Plant | Direct Mapping |
| 12 | DCT | STPO | EKGRP | Purchasing Group | S/4HANA | STPO | EKGRP | Purchasing Group | Direct Mapping |
| 13 | DCT | STPO | EKGRP | Purchasing Group | S/4HANA | STPO | EKGRP | Purchasing Group | Direct Mapping |
| 14 | DCT | STPO | EKORG | Purchasing Organization | S/4HANA | STPO | EKORG | Purchasing Organization | Direct Mapping |
| 15 | DCT | PLMZ | LGORT | Issue Location for Production Order | S/4HANA | PLMZ | LGORT | Issue Location for Production Order | Direct Mapping |
| 16 | DCT | STPO | LIFNR | Account Number of Supplier | S/4HANA | STPO | LIFNR | Account Number of Supplier | Direct Mapping |
7.Task List Package Transformation Rule (ECC)
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | PF2, WP2 | PLWP | PLNTY | Task List Type | S/4HANA | PLKO | zLegacyPLNTY | Legacy Task List Type | Direct Mapping |
| 2 | PF2, WP2 | PLWP | PLNNR | Key for Task List Group | S/4HANA | PLPO | zLegacyPLNNR | Legacy Key for Task List Group | Direct Mapping |
| 3 | PF2, WP2 | PLWP | PLNAL | Group Counter | S/4HANA | PLKO | zLegacyPLNAL | Legacy Group Counter | Direct Mapping |
| 4 | PF2, WP2 | PLPO | VORNR | Activity Number | S/4HANA | PLPO | zLegacyVORNR | Legacy Activity Number | Direct Mapping |
| 5 | PF2, WP2 | STPO | IDNRK | Material Number | S/4HANA | STPO | IDNRK | Material Number | Direct Mapping |
| 6 | PF2, WP2 | PLMZ | IMENG | Component Quantity | S/4HANA | PLMZ | IMENG | Component Quantity | Direct Mapping |
| 7 | PF2, WP2 | PLMZ | IMEIN | Component Unit of Measure | S/4HANA | PLMZ | IMEIN | Component Unit of Measure | Direct Mapping |
| 8 | PF2, WP2 | PLMZ | RGEKZ | Indicator: Backflush | S/4HANA | PLMZ | RGEKZ | Indicator: Backflush | Direct Mapping |
7.Task List Package Transformation Rule (DCT)
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | DCT | PLWP | zLegacyPLNTY | Legacy Task List Type | Mandatory. Key to link to Task List Operation | PLWP | zLegacyPLNTY | Legacy Task List Type | Direct Mapping |
| 2 | DCT | PLWP | zLegacyPLNNR | Legacy Task List Group | Mandatory. Key to link to Task List Operation | PLWP | zLegacyPLNNR | Legacy Task List Group | Direct Mapping |
| 3 | DCT | PLWP | zLegacyPLNAL | Legacy Group Counter | Mandatory. Key to link to Task List Operation | PLWP | zLegacyPLNAL | Legacy Group Counter | Direct Mapping |
| 4 | DCT | PLWP | zLegacyVORNR | Legacy Activity Number | Mandatory. Key to link to Task List Operation | PLWP | zLegacyVORNR | Legacy Activity Number | Direct Mapping |
| 5 | DCT | PLWP | STRAT | Maintenance Strategy | Non Editable. Direct Mapping from Task List Header: STRAT field | PLWP | STRAT | Maintenance Strategy | Direct Mapping |
| 6 | DCT | PLWP | PAKET | Maintenance Package Number | Mandatory. ) | PLWP | PAKET | Maintenance Package Number | Direct Mapping |
| 7 | DCT | PLWP | KZYK1 | Short text for the maintenance cycle (time/performance) | ). | PLWP | KZYK1 | Short text for the maintenance cycle (time/performance) | Direct Mapping |
List of Custom Target Reports for this object is maintained here: Conversion Specification - Custom Reports Register.
| Mapping Table Name | Mapping Table Description |
|---|---|
| Informal Characters | List of Informal Characters and New Translation |
INC-Task List | Task List inclusion list |
ENR-Task List Operation Lean Service | Task List Operation Lean Service enrichment to assign service details |
Task List | Old to new Task List |
Functional Location | Old to new Functional Location |
Equipment Number | Old to new Equipment Number |
Maintenance item | Old to new Maintenance item |
Plant | Old to new Plant |
Planner Group | Old to new Planner Group |
Work Centre | Old to new Work Centre |
Maintenance Plan | Old to new Maintenance Plan |
Maintenance Strategy | Old to new Maintenance Strategy |
Maintenance Package | Old to new Maintenance Package |
Material Number | Old to new Material Number |
Value Mapping: | Old to New Material No. |
Assembly and Construction Type | Mapping of legacy Assembly / Construction Type to new Assembly / Construction Type |
System Condition | Old to new System Condition |
Purchasing Organization | Old to new Purchasing Organization |
Vendor Number | Old Vendor Code to New Vendor Code |
Purchasing Group | Old Purchasing Group to New Purchasing Group |
Cost Elements (Data Dependent on Chart of Accounts) | Old to new Cost Elements |
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1 | Ensure DCT tables completeness | Syniti |
| 2 | Ensure all Transformation mappings are up to date. | Syniti |
| Task | Action |
|---|---|
Verify Record Count | SyWay A2D Data Team to verify that the total number of relevant records from legacy systems and DCTs (if any) is equal to the total number of records in the Preload and Load Sheets. |
Verify Data Integrity | SyWay A2D Data Team to verify that the total number of Operations per Work Oder header extracted from legacy systems and DCTs (if any) should be equal to the total number of operations identified in the Preload and Load Sheets |
| Task | Action |
|---|---|
Conversion Accuracy | SyWay A2D Data Team to verify that all fields below meet pass the checks:
|
Review Error Reports | Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data. |
| Task | Action |
|---|---|
Verify Record Count | Business Data Owner/s to verify that the total number of relevant records from legacy systems and DCTs (if any) is equal to the total number of records in the Preload and Load Sheets. |
| Task | Action |
|---|---|
Conversion Accuracy | Business Data Owner/s to verify that all fields below meet pass the checks:
|
The load process includes:
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1 | Obtain DCT Sign-off from Business | SyWay A2D Data Team |
| 2 | Ensure Pre-load sign-offs are obtained | SyWay A2D Data Team |
| 3 | Proceed with Data load. | SyWay A2D Data Team |
| 4 | Validate few records loaded by accessing standard transactions. | SyWay A2D Data Team |
| 5 | Generate the post load reports in the tool. | SyWay A2D Data Team |
| 6 | Log errors as defects, if any and address resolutions. Close defects. | SyWay A2D Data Team |
| 7 | Generate post load report if step 6 is validated | SyWay A2D Data Team |
| 8 | Business to validate the post load files as part of post-load validation, raise data defects or provide the post-load sign-off. | Business |
| 9 | Repeat steps 5 to 7 if necessary. | SyWay A2D Data Team |
Load Phase and Dependencies
Identify the phase as to “when” the load for this object will occur. <Pre-Cutover, Cutover, Post Cutover> and list the steps that need to occur before the load can commence
List the Configurations required before loading can commence
| Item # | Configuration Item |
|---|---|
| 1 | T399I-Planning Plant |
| 2 | T001W-Plant |
| 3 | NRIV -Number Ranges for Task List Group |
| 4 | T416-Task List Usage |
| 5 | T024A-Planner Groups |
| 6 | TQ72-Task List Status |
| 7 | T357M-System Condition |
| 8 | T430-Control Key |
| 9 | T006-Unit of Measure |
| 10 | T498-Distribution function |
| 11 | CSLA-Activity Type |
| 12 | CSKA-Cost Element |
| 13 | T024-Purchasing Group |
| 14 | T023-Material Group |
| 15 | LFA1-Supplier |
| 16 | T024E-Purchasing Organization |
| 17 | T430-Operation/Activity control key |
| 18 | T399X-Parameters dependent on order type |
| 19 | TCA41-Default values for standard networks and profiles |
| Object # | Preceding Object Conversion Approach |
|---|---|
1001 | Bill of Material |
1002 | Equipment |
1003 | Functional Location |
1010 | Construction Types/Assemblies |
1016 | Maintenance Plan and Item |
1017 | Maintenance Strategy |
2019 | Material Master |
3018 | Vendors |
9005 | Work Order |
The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management
| Error Type | Error Description | Action Taken |
|---|---|---|
Configuration | Invalid Control Key | Engage Functional team to expedite and fix the error in the system |
Configuration | Invalid Planner Group | Engage Functional team to expedite and fix the error in the system |
Configuration | Invalid Plant | Engage Functional team to expedite and fix the error in the system |
Configuration | Invalid Planning Plant | Engage Functional team to expedite and fix the error in the system |
Configuration | Invalid System Condition | Engage Functional team to expedite and fix the error in the system |
Configuration | Invalid Purchasing Group | Engage Functional team to expedite and fix the error in the system |
Configuration | Invalid Material Group | Engage Functional team to expedite and fix the error in the system |
Configuration | Invalid Purchasing Org | Engage Functional team to expedite and fix the error in the system |
Invalid Data | Invalid Maintenance Strategy | Expedite whether the master data is changed in the system |
Invalid Data | Invalid Activity Type | Expedite whether the master data is changed in the system |
Invalid Data | Invalid Assembly | Expedite whether the master data is changed in the system |
Invalid Data | Invalid Work Centre | Expedite whether the master data is changed in the system |
Invalid Data | Invalid Material Number | Expedite whether the master data is changed in the system |
Invalid Data | Invalid Service Number | Expedite whether the master data is changed in the system |
Invalid Data | Invalid Cost Element | Expedite whether the master data is changed in the system |
Invalid Data | Invalid Vendor | Expedite whether the master data is changed in the system |
Invalid Data | Invalid Outline Agreement | Expedite whether the master data is changed in the system |
Invalid Data | Invalid Maintenance BOM | Expedite whether the master data is changed in the system |
| Task | Action |
|---|---|
Verify Count | SyWay A2D Data Team to verify the record count created in target S/4 HANA by accessing post load reports in dspMigrate or standard reports from S/4 HANA. |
Verify Logs | Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.). |
| Task | Action |
|---|---|
Conversion Accuracy | SyWay A2D Data Team to verify that the Work order data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA. |
| Task | Action |
|---|---|
Verify Count | Download Post Load Reports from dspMigrate and verify that the record count loaded in the target S/4 HANA is the same count as of the endorsed load file. |
| Task | Action |
|---|---|
Conversion Accuracy | Verify that the EAM Work order data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA. |
Any additional key assumptions.
Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.