Status

Owner
StakeholdersThe business stakeholders involved in making, reviewing, and endorsing this decision. Type @ to mention people by name

Purpose

The purpose of this document is to define the conversion approach to create the WBS - CAPEX, OPEX, Statistical

in S/4 HANA.

In SAP, a WBS element (Work Breakdown Structure element) is a key component in project structure. WBS elements are organized hierarchically and facilitates planning, execution, and control.


Conversion Scope

The scope of this document covers the approach for converting active WBS - CAPEX, OPEX, Statistical from Legacy Source Systems into S/4HANA following the WBS - CAPEX, OPEX, Statistical Master Data Design Standard. tems into S/4HANA: 


All Data Built in the DCT.
An initial extract of the relevant WBS, including suggested mapping to new strutures, will be provided in google sheet format to assist business in decision making on including any relevant WBS element from PF2 and WP2.

The data from legacy system to be included in the initial extract includes:

    1. WBS elements for Capital projects (eg. Industrial, Facility IT and R&I) open as at migration date with postings in the last 3 years or has AUC balance.
    2. WBS elements for Budgeted Operating projects (eg. Budgeted Maintenance, Demolition projects) open as at migration date with postings in the last 3 years.
    3. WBS elements for Closed Capital Projects with postings within the agreed timeframe (currently migration relevant is 2028).
    4. WBS elements for Closed Budgeted Operating Projects with postings within the agreed timeframe (currently migration relevant is 2028).
    5. Specifically also included are WBS elements for IT and R&I Projects with postings in the last 3 years.


The data from legacy system be included in the initial extract excludes:

  1. WBS elements for company codes out of scope
  2. WBS for out of scope Plants.
  3. WBS with no costs (no movement in past 3 years), Project created by mistake
  4. WBS which has deletion indicator set

Additionally WBS elements without any initial extract will be created using the DCT, this includes - 

  1. WBS elements with reference to PPM item and template project- 
    1. Capital Lease (One WBS per Company Code/Cost Centre)
    2. Direct Asset Purchases (One WBS per Company Code/Cost Centre)
  2. WBS elements with no reference to PPM items -
    1. Provisions (One WBS per Company code/GBU/ Plant),
    2. Intercompany recharge (One Level 1 WBS per Company Code, Level 2 WBS per Trading Partner)


The guiding principle is that we should only migrate data necessary to support ongoing business operations. This may also involve cleansing activities within the source systems to align with the migration criteria.

In terms of Historical Data, it will not be migrated except where specific records are required to support application functionality, meet legislative obligations or ensure regulatory compliance.


WBS from the legacy system to be used for the basis of the system include projects from PF2 and WP2.

The data from legacy system includes:

  1. WBS elements not in closed status
  2. Closed CAPEX WBS elements which has current year postings..
  3. The parent WBS elements included in the above.

The data from legacy system excludes:

  1. WBS elements for company codes out of scope


WBS elements can be referenced in transactional data conversions, the conversions which may require WBS elements are

  • Financial postings
    • CNV-9031 Project - Actual GL Line Items (PNL - WBS for AuC)
    • CNV-9032 GL Line Items (PNL - Internal Order, Statistical/ Opex WBS)
  • Maintenance processing
    • CNV-9005 Work Order
  • Procurement
    • CNV-9044 Purchase Requisition (Oos) 
    • CNV-9045 Open Purchase Orders


L

  



Predecessor Objects


CNV-1024 Project Definition

List of source systems and approximate number of records
SourceScope

Source Approx No. of Records

Target SystemTarget Approx

No. of Records

PF2

S/4 Hana
WP2

S/4 Hana










Logic:

  1. WBS elements not in closed status
  2. Table PRPS

Key in field "Company Code" in scope.

Result: Object numbers of WBS that are in company codes in scope.

  1. Table JEST:

Field "Object number" = Key in the object numbers of WBS (from Step A)

Field "Status Inactive" = blank

Then filter object number that do not have status I0046 (Closed) or IFO07 (Closed) 

These WBS need to be migrated.

  1. Closed CAPEX WBS element that have cost in current year must also be migrated.

Logic:

  1. Table PRPS

Key in field "Company Code" in scope.

Result: Object numbers of WBS that are in company codes in scope.

  1. Table JEST:

Field "Object number" = Key in the object numbers of WBS (from Step A)

Field "Status Inactive" = blank

Then filter object number that has status I0046 (Closed) or IFO07 (Closed).

Result: Object number with status I0046 (Closed) or IFO07 (Closed).

  1. Table RPSCO:

Field "Object number" = Key in the object numbers of WBS (from Step B) 

Field "Fiscal Year" = Current year

Field "Value Type" = 4

Result = Object numbers that have cost in current year.

These WBS needs to be migrated.

  1. Parent WBS elements

For each WBS element with closed status include all superior level WBS elements.  If status of element is not closed superior WBS elements will also be not closed.

  1. Table PRHI:

Field “WBS elements” (All PS_POSNR from PRPS)

IF “UP” is Null no superior objects

Result = Field “UP” additional WBS to be migrated

Repeat until “UP” is Null.



Additional Information

Multi-language Requirement

Summarize Multi-language Requirement/s, if any

Document Management

Summarize Document Management requirement, if any

Legal Requirement

Summarize Legal Requirement/s, if any

Special Requirements

Specify any special requirements or considerations that may impact the data conversion process based on specific locations, regulatory compliance or system limitations. Clearly outline any regional or localization requirements such as country-specific data formats, legal reporting obligations or industry standards that must be adhered to (e.g., localization rules for countries like China).

If the data conversion involves third-party systems or external data sources, such as Icertis, describe any additional requirements related to data mapping, transformation logic, validation rules or security measures that must be followed.




Target Design

With Functional input, document the technical design of the target fields that are in the scope of this document.

The technical design of the target for this conversion approach.

TableFieldData ElementField DescriptionData TypeLengthRequirement
PRPSPOSIDPS_POSIDWBS elementCHAR24Mandatory
PRPSPS_POSNRPS_POSNRWBS Element internal numberCHAR8Conditional
PRPSOBJNRJ_OBJNRObject NumberCHAR8Conditional
PRPSPOST1PS_POST1DescriptionCHAR40Mandatory
PRPSVERNRPS_VERNRNo. of Person Resp.NUMC8Mandatory
PRPSASTNRPS_ASTNRApplicant no.NUMC8Mandatory
PRPSPBUKRPS_PBUKRCompany codeCHAR4Mandatory
PRPSPKOKRPS_PKOKRControlling areaCHAR4Mandatory
PRPSPRCTRPRCTRProfit CenterCHAR10Mandatory
PRPSPRARTPS_PRARTProject TypeCHAR2Mandatory
PRPSPLAKZPS_PLAKZPlanning ElementCHAR1System
PRPSBELKZPS_BELKZAcct asst elem.CHAR1Mandatory
PRPSFAKKZPS_FAKKZBilling ElementCHAR1Conditional
PRPSFKSTLPS_FKSTLResponsible CCCHAR10Mandatory
PRPSFKOKRPS_FKOKRCA resp. cost centerCHAR4Mandatory
PRPSFABKLFABKLFactory CalendarCHAR2Mandatory
PRPSPWPOSPS_PWPOSCurrencyCUKY5Mandatory
PRPSWERKSWERKS_DPlantCHAR4Mandatory
PRPSSCOPESCOPE_CVObject classCHAR2

System Generated

PRPSXSTATPS_XSTATStatisticalCHAR1Conditional
PRPSKOSTLPS_KOSTLCCtr posted actualCHAR10Conditional
PRPSIMPRFIM_PROFILInvestment ProfileCHAR6Conditional
PRPSFUNC_AREAFKBERFunctional AreaCHAR16Mandatory
PRPSPSPHIPS_PSPIDProject DefinitionCHAR24Mandatory
PRPSSTUFEPS_STUFELevelCHAR3Mandatory
PRHILEFTPS_PHILEWBS_LEFTNUMC8Conditional
PRHIUPPS_PHIUPWBS_UPNUMC8Conditional
PRPSUSR08USR08User


PRPSUSR10USR10PRPSCross SystemCHAR1Conditional
PRPSZX01
CAPEX/ OPEXchar10Conditional
PRPSZX02
Maintenance event char40Conditional
PRPSZX03
Trading company codeCHAR4Conditional
PRTEPEINH
Unit of measure

System Generated
PRTEEEINH
Unit of measure

System Generated
PRTEIEINH
Unit of measure

System Generated


Data Cleansing

Data cleansing tasks are set out in CNV-1024 which deals with projects and also by definition includes the closing of WBS elements in those projects.

If data cleansing is managed outside of the source system (e.g. Syniti Migrate, 3rd Party Vendor, DCT), the necessary documentation must be produced and appended to this deliverable for sign-off.

IDCriticalityError Message/Report DescriptionRuleOutputSource System

1026-001

C3

Old projects with no actuals / commitment

If the old projects do not have any actual (and/or) commitments in the past year, set the project to status CLSD (CJ20N)

Old project set to closed

WP2/PF2





















Conversion Process

The high-level process is represented by the diagram below:

Summarize High-Level Process. Include diagrams, where applicable. Include information supporting details of Extract, Transform and Load specific to the Data Object


Data Privacy and Sensitivity

Summarize Data Privacy and Sensitivity Requirements, if any


Extraction

Extract data from a source into Syniti Migrate
. There are 2 possibilities:

  1. The data exists. Syniti Migrate connects to the source and loads the data into Syniti Migrate. There are 3 methods:
    1. Perform full data extraction from relevant tables in the source system(s).
    2. Perform extraction through the application layer.
    3. Only if Syniti Migrate; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
  2. The data does not exist (or cannot be converted from its current state).  The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate

The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads

Extraction Run Sheet

Req #Requirement DescriptionTeam Responsible

1

Confirm scope and extraction approach for each ECC source systems WP2, PF2 (direct DB or manual extract)

Data Team (I2M), Data Team (Syniti)

2

Establish and validate Syniti connectivity to both ECC source systems

Technical / Basis Team, Data Team (Syniti)

3

Perform full data extraction from relevant SAP WBS elements from both source systems WP2, PF2

Data Team (Syniti)

4

Extract WBS via the application layer for additional validations for Manual Data Collection using DCTs

Data Team (I2M)

5

Apply agreed Relevancy Criteria to filter only applicable WBS records for S/4HANA

Data Team (I2M), Data Team (Syniti)

6

In case of restricted access or connectivity issues, receive pre-extracted reports/files from source system team and upload to Syniti Migrate manually

Data Team (I2M), Data Team (Syniti)

8

Perform data quality checks on extracted records (e.g., missing fields, invalid dates, incorrect formats)

Data Team (I2M), Data Team (Syniti)

9

Review and approve extracted data sample sets from each source system before transformation begins

Business / Functional Team


Selection Screen

If applicable, this section will give the details on any selection screen parameters, including the parameter type, that are required to be entered to ensure consistent data extracts.
Selection Ref ScreenParameter NameSelection TypeRequirementValue to be entered/set





















Data Collection Template (DCT)

Target Ready Data Collection Template will be created for Data Object data with exception of some fields which require transformation as mentioned in the transformation rule.

<Object> DCT Rules

Field NameField DescriptionRule
POSIDWBS elementUnique Identifier for the WBS Element as per project coding mask.
POST1Description40 character description of the WBSE
VERNRNo. of Person Resp.This field represents the position of the Person Responsible for a WBS Element and is mandatory field. It will be derived from the Project Definition and can be overwritten. Refer configuration table field TCJ04-PS_VERNR for data validation.
ASTNRApplicant no.This field represent the position of the Project Financial Controller. It will be derived from the Project Definition and can be overwritten. Refer configuration table field TCJ05-ASTNR for data validation.
PBUKRCompany codeRepresents legal entity and inherited from the Project Definition. Refer configuration table field T001-BURKS for data validation.
PKOKRControlling areaControlling Area is a self-contained organizational unit used for internal cost accounting, this will be default from configuration.
PRCTRProfit CenterIn Syway, Profit Center represent a plant or a site or generic for GBU. This field will be inherited from the Project Definition, if required it can be overwritten. Refer master data table field CEPC-PRCTR for allowed values.
PRARTProject TypeIt is an attribute that serve as classification field that help to define the nature, purpose, and governance of a WBS element. They are useful for reporting, controlling, and compliance alignment.
Refer configuration table field TCJ1-PRART for allowed values.
PLAKZPlanning ElementPlanning element checkbox is used to flag if WBS element is relevant for cost planning. This indicator will be default from configuration.
BELKZAcct asst elem.This indicator enables financial posting on the WBS element. It will be checked in below conditions-
1. For WBS elements governed by CAPEX project profiles, activation of this checkbox is mandatory for all elements at level 3 and subordinate levels.
2. For WBS elements governed by Operational, Statistical & Recharge project profiles, activation of this checkbox is mandatory for all WBS elements.
FAKKZBilling ElementThis indicator enables WBS element to record revenue against it. Required for Recharge WBSE only.
ABUKRRequesting co. codeIn Syway design this field will not be used
FKSTLResponsible CCCost Center responsible for delivery of work. Required for WBS elements of Expense Project (Budget-managed) only. Refer master data table field KOSTL-KOSTL for allowed values.
FKOKRCA resp. cost centerThis is automatically derived from the Responsible Cost Center
FABKLFactory CalendarFactory Calendar defines year wise working and non-working days for a specific plant or business unit. It plays a crucial role in scheduling & planning. Derived from the Plant maintained on the WBS element. Refer configuration table field TFACD-IDENT for allowed values.
PWPOSCurrencyCurrency at WBS element refers to the local currency used to record, process, and report financial transactions. Currency derived from WBS element's Company Code
WERKSPlantPlant represent a site of the WBS element. Mandatory for all WBS elements.
USR08Exp Capital'ionExpected Capitalization date marks the anticipated execution of the AUC final settlement, restricted to WBS elements that include an Investment Profile.
USR10Cross SystemThis checkbox field, will be selected when intercompany services are needed for a WBS element.
XSTATStatisticalThis field checkbox will be inactive for all projects except for WBS elements of project with Project Profile "ZPS0003" i.e. Statistical Expense.
KOSTLCCtr posted actualThis field represents the receiver Cost Center of actual cost for any actual financial posting on the WBS element. This field will be mandatory for all statistical WBS element
IMPRFInvestment ProfileInvestment Profile on WBS element is used to enable auto generation of AuC w.r.t. predefined asset class. Applicable for CAPEX projects (with Project Profile ZPS0001) at Level 3 WBS elements if the CAPEX field is selected. It can not be changed once WBSE is released. Refer configuration table field TAPRF-IVPRO for allowed values.
FUNC_AREAFunctional AreaFunctional Area is an organizational unit used to classify expenses based on their purpose or function e.g. IS, IT & R&I.
Project created via PPM Item: Functional Area will be derived from the project template, new WBS element under the hierarchy will inherit the Functional Area of the parent WBS element/ Project Definition.
Project created manually i.e. without PPM Item: Functional Area will be maintained manually by the GBS.
Refer configuration table field TFKB-FKBER for allowed values.
PSPHIProject DefinitionProject ID assigned to the WBS elements. The Project ID is automatically assigned to WBS elements that are created through a PPM Item. Projects will be created manually also without PPM Item where project profile is ZPS0003, ZPS0004 or ZPS0005.
STUFELevelIn a project, WBS elements are structured across multiple levels to form a tree-like hierarchy for better project contolling and monitoring.
LEFTWBS_LEFTThis field represents the left-adjacent WBS element in the same hierarchy level required for navigating sibling relationships within a WBS hierarchy.
UPWBS_UPThis field represents the immediate superior WBS element (parent node) required for establishing parent-child relationships in the WBS hierarchy.
ZX01CAPEX/ OPEXThis field identifies expense is CAPEX or OPEX.
- For project profile ZPS0001 this field will be mandatory for all WBS elements L3 onwards.
- For project profiles ZPS0002 & ZPS0003 this field will be default to OPEX.
ZX02Maintenance eventThis field is used to determine the settlement rule receiver for the relevant maintenance Work Order. This field will be applicable when Project Type = Turnaround Projects at level 3 WBS element
ZX03Trading company codeThis field will be applicable when Project Type = Inetrcompany Recharge. Mandatory at Level 2 WBS to determine the trading company for intercompany recharges
T001-BURKS for data validation.

Extraction Dependencies

List the steps that need to occur before extraction can commence

Item #Step DescriptionTeam Responsible













Transformation

The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:

  1. Perform value mapping and data transformation rules.
    1. Legacy values are mapped to the to-be values (this could include a default value)
    2. Values are transformed according to the rules defined in Syniti Migrate
  2. Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation

Transformation Run Sheet

Item #Step DescriptionTeam Responsible













Transformation Rules

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic
1PF2/WP2PRPSPOSIDWBS elementS/4 HanaPRPSPOSIDWBS elementOld to new: Conversion Exit
2PF2/WP2PRPSPOST1DescriptionS/4 HanaPRPSPOST1DescriptionCopy from source to target system
3PF2/WP2PRPSVERNRNo. of Person Resp.S/4 HanaPRPSVERNRNo. of Person Resp.Value Mapping Responsible Person to new Person Responsible Position ID
4PF2/WP2PRPSASTNRApplicant no.S/4 HanaPRPSASTNRApplicant no.Value Mapping Applicant to new Applicant Position ID
5PF2/WP2PRPSPBUKRCompany codeS/4 HanaPRPSPBUKRCompany codeValue Mapping: Old to New Company Code
6PF2/WP2PRPSPKOKRControlling areaS/4 HanaPRPSPKOKRControlling areaValue Mapping:  Old to New Controlling Area
7PF2/WP2PRPSPRCTRProfit CenterS/4 HanaPRPSPRCTRProfit CenterValue Mapping:  Old to New Profit Centre
8PF2/WP2PRPSPRARTProject TypeS/4 HanaPRPSPRARTProject TypeOld to new
9PF2/WP2PRPSPLAKZPlanning ElementS/4 HanaPRPSPLAKZPlanning ElementCopy from source to target system
10PF2/WP2PRPSBELKZAcct asst elem.S/4 HanaPRPSBELKZAcct asst elem.Copy from source to target system
11PF2/WP2PRPSFAKKZBilling ElementS/4 HanaPRPSFAKKZBilling ElementCopy from source to target system
12PF2/WP2PRPSFKSTLResponsible CCS/4 HanaPRPSFKSTLResponsible CCValue Mapping:  Old to New Cost Centre
13PF2/WP2PRPSFKOKRCA resp. cost centerS/4 HanaPRPSFKOKRCA resp. cost centerValue Mapping:  Old to New Cost Centre
14PF2/WP2PRPSFABKLFactory CalendarS/4 HanaPRPSFABKLFactory CalendarCopy from Project Definition
15PF2/WP2PRPSPWPOSCurrencyS/4 HanaPRPSPWPOSCurrencyCopy from Project Definition
16PF2/WP2PRPSWERKSPlantS/4 HanaPRPSWERKSPlantValue Mapping:  Old to New Plant
17PF2/WP2PRPSXSTATStatisticalS/4 HanaPRPSXSTATStatisticalCopy from source to target system
18PF2/WP2PRPSKOSTLCCtr posted actualS/4 HanaPRPSKOSTLCCtr posted actualValue Mapping:  Old to New Cost Centre
19PF2/WP2PRPSIMPRFInvestment ProfileS/4 HanaPRPSIMPRFInvestment ProfileOld to new
20
PROJFUNC_AREAFunctional AreaS/4 HanaPRPSFUNC_AREAFunctional AreaCopy from Project Definition PROJ-FUNC_AREA
21PF2/WP2PRPSPSPHIProject DefinitionS/4 HanaPRPSPSPHIProject Definition

Load Dependent: PSPID: Old Project to new project mapping


22PF2/WP2PRPSSTUFELevelS/4 HanaPRPSSTUFELevelCopy from source to target system
23PF2/WP2PRHILEFTWBS_LEFTS/4 HanaPRPSPRHI-LEFTWBS_LEFTWBS Element Mapping
24PF2/WP2PRHIUPWBS_UPS/4 HanaPRPSPRHI-UPWBS_UPWBS Element Mapping
25PF2/WP2PRPSIMPRFInvestment ProfileS/4 HanaPRPSZX01CAPEX/ OPEX

If Investment Profile "" then "Opex"

Else "Capex"

26DCTPRPSPOSIDWBS elementS/4 HanaPRPSPOSIDWBS elementCopy from source to target system
27DCTPRPSPOST1DescriptionS/4 HanaPRPSPOST1DescriptionCopy from source to target system
28DCTPRPSVERNRNo. of Person Resp.S/4 HanaPRPSVERNRNo. of Person Resp.Copy from source to target system
29DCTPRPSASTNRApplicant no.S/4 HanaPRPSASTNRApplicant no.Copy from source to target system
30DCTPRPSPBUKRCompany codeS/4 HanaPRPSPBUKRCompany codeCopy from Project Definition
31DCTPRPSPKOKRControlling areaS/4 HanaPRPSPKOKRControlling areaCopy from Project Definition
32DCTPRPSPRCTRProfit CenterS/4 HanaPRPSPRCTRProfit CenterCopy from source to target system
33DCTPRPSPRARTProject TypeS/4 HanaPRPSPRARTProject TypeCopy from source to target system
34DCTPRPSPLAKZPlanning ElementS/4 HanaPRPSPLAKZPlanning ElementCopy from source to target system
35DCTPRPSBELKZAcct asst elem.S/4 HanaPRPSBELKZAcct asst elem.Copy from source to target system
36DCTPRPSFAKKZBilling ElementS/4 HanaPRPSFAKKZBilling ElementCopy from source to target system
37DCTPRPSFKSTLResponsible CCS/4 HanaPRPSFKSTLResponsible CCCopy from source to target system
38DCTPRPSFKOKRCA resp. cost centerS/4 HanaPRPSFKOKRCA resp. cost centerCopy from source to target system
39DCTPRPSWERKSPlantS/4 HanaPRPSWERKSPlantCopy from source to target system
40DCTPRPSXSTATStatisticalS/4 HanaPRPSXSTATStatisticalCopy from source to target system
41DCTPRPSKOSTLCCtr posted actualS/4 HanaPRPSKOSTLCCtr posted actualCopy from source to target system
42DCTPRPSIMPRFInvestment ProfileS/4 HanaPRPSIMPRFInvestment ProfileCopy from source to target system
43DCTPRPS

S/4 HanaPRPSFUNC_AREAFunctional AreaCopy from source to target system
44DCTPRPSPSPHIProject DefinitionS/4 HanaPRPSPSPHIProject DefinitionCopy from source to target system
45DCTPRPS

S/4 HanaPRPSSTUFELevelCopy from source to target system
46DCTPRPSLEFTWBS_LEFTS/4 HanaPRPSPRHI-LEFTWBS_LEFTCopy from source to target system
47DCTPRPSUPWBS_UPS/4 HanaPRPSPRHI-UPWBS_UPCopy from source to target system
48DCTPRPSUSR08Exp Capital'ionS/4 HanaPRPSUSR08Exp Capital'ionCopy from source to target system
49DCTPRPSUSR10Cross SystemS/4 HanaPRPSUSR10Cross SystemCopy from source to target system
50DCTPRPSIMPRFCAPEX/ OPEXS/4 HanaPRPSZX01CAPEX/ OPEXCopy from source to target system
51DCTPRPSZX02Maintenance event S/4 HanaPRPSZX02Maintenance event Copy from source to target system
52DCTPRPSZX03Trading company codeS/4 HanaPRPSZX03Trading company codeCopy from source to target system
53DCT


S/4 HanaPRPSPS_POSNRWBS Element internal numberSystem Generated
54DCT


S/4 HanaPRPSOBJNRObject NumberSystem Generated
55DCT


S/4 HanaPRPSFABKLFactory CalendarCopy from Project Definition
56DCT


S/4 HanaPRPSPWPOSCurrencyCopy from Project Definition
57DCT


S/4 HanaPRPSSCOPEObject classCopy from Project Definition

List of Custom Target Reports for this object is maintained here: Conversion Specification - Custom Reports Register.


Transformation Mapping

Use the exact name and reference this section in the “Transformation rules” above
Mapping Table NameMapping Table Description
T001Value Mapping: Currency From Company Code
Company CodeValue Mapping: BUKRS: Old Company Code to New Company Code
Controlling AreaValue Mapping:  Old to New Controlling Area
Cost CentreValue Mapping:  Old to New Cost Centre
PlantValue Mapping:  Old Plant to New Plant
Profit CenterValue Mapping:  Old to New Profit Centre
ApplicantValue Mapping: Applicant to new Applicant Position ID
Person ResponsibleValue Mapping Responsible Person to new Person Responsible Position ID
Investment ReasonValue Mapping: Investment Reason Old to New

Transformation Dependencies

List the steps that need to occur before transformation can commence
Item #Step DescriptionTeam Responsible

Ensure all the fields and values are imported into ADM Construction page correctlySyway Data Team


Pre-Load Validation

Project Team

The following pre-load validations will be performed by the Project Team.

Completeness

TaskAction
Generation of
Pre-load report
Check all the required fields

Verify Record Count

SyWay I2M Data Team to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets.


Accuracy

TaskAction

Conversion Accuracy

SyWay I2M Data Team to verify that all fields below meet pass the checks:

  1. Mandatory Fields
  2. Field and Value Mapping Correctness
  3. Null Checks
  4. Text Length Checks

Review Error Reports

Review and correct the errors.  Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source (DCT) data.


Business

The following pre-load validations will be performed by the business.

Completeness

TaskAction

Verify Record Count

Business Data Owner/s to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets


Accuracy

TaskAction

Conversion Accuracy

Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules (and signed-off DCT data).


Load

The load process includes:

  1. Execute the automated data load into target system using load tool or product the load file if the load must be done manually
  2. Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation

Load Run Sheet

Item #Step DescriptionTeam Responsible

1

Load using transaction CNMASSCREATE or Migration cockpit

Data Team

2

Load 3 records for < > to validate if data is loaded successfully without errors

Data Team

3

Load 3 records for < > to validate if data is loaded successfully without errors

Data Team

4

Proceed with full load if steps 2 and 3 are validated

Data Team

5

Validate few records loaded by accessing CN41N report

Data Team

6

Generate post load report if step 5 is validated

Data Team


Load Phase and Dependencies

Identify the phase as to “when” the load for this object will occur. <Pre-Cutover, Cutover, Post Cutover> and list the steps that need to occur before the load can commence

Configuration

List the Configurations required before loading can commence

Item #Configuration Item
1Project Coding Mask
2Company Code
3Controlling Area
4Project Type
5Factory Calendar
6Currency Code
7Plant
8Investment Profile
9Functional Area
10Trading company code
11Define Tolerance Limits
12WBS Status Profile
13Validation
14Substitution
15Settlement Rules

Conversion Objects

Object #Preceding Object Conversion Approach
1024Project Definition
1074Cost Centre
1070Profit Centre

Error Handling

The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management

Error TypeError DescriptionAction Taken

Project Definition does not existCorrect upload data, review load of CNV-1024 

WBS Element already existCorrect upload data.




Post-Load Validation

Project Team

The following post-load validations will be performed by the Project Team.

Completeness

TaskAction

Verify Count

SyWay I2M Data Team to verify the record count created in target S/4 HANA by accessing post load reports or standard reports from S/4 HANA.

Verify Logs

Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.).




Accuracy

TaskAction

Conversion Accuracy

Verify that the Project Definition in target S/4 HANA were loaded correctly via Project Builder display and table PROJ 


Business

The following post-load validations will be performed by the business.

Completeness

TaskAction
Verify template Project data - Project Definition Extract data from PS report CN41N in S/4 Hana

Accuracy

TaskAction
Verify template Project data - Project Definition Extract data from PS report CN41N in S/4 Hana


Key Assumptions

  • Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
  • WBS - CAPEX, OPEX, Statistical is in scope based on data design and any exception requested by business.

Any additional key assumptions.


See also

Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.

Change log