The purpose of this document is to define the conversion approach to create WBS - CAPEX/OPEX Settlement Rule in S/4 HANA.
Settlement rule is a set of parameters that defines how costs are transferred from a project's sender like a WBS element to receivers, such as a General Ledger account, Cost Centre, Asset Under Construction, fixed Asset, Profitability Segment, Superior WBS element.
The scope of this document covers the approach for converting applicable active WBS - CAPEX/OPEX Settlement Rule from Legacy Source Systems into S/4HANA following the WBS - CAPEX/OPEX Settlement Rule Master Data Design Standard.
The data being sourced using DCT (Data Collection Template).
Relevancy criteria
The data from legacy system includes:
The data from legacy system excludes:
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
| DCT | All Records | S/4HANA | TBD |
Not applicable
Document Management
Not applicable
Legal Requirement
Not applicable
Special Requirements
Not applicable
The technical design of the target for this conversion approach.
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| COBRB | OBJNR | J_OBJNR | WBS element | CHAR | 22 | Mandatory |
| COBRB | KONTY | KONTY | Account Assignment Category | CHAR | 2 | Mandatory |
| DKOBR | EMPGE | ABR_EMP | Settlement Receiver | CHAR | 40 | Mandatory |
| COBRB | PROZS | BRGPROZS | Percent | DEC | 5 | Conditional |
| COBRB | BETRR | BETRR | Amount | CURR | 23 | Conditional |
| COBRB | PERBZ | PERBZ_LD | Settlement Type | CHAR | 3 | System Generated |
| COBRB | EXTNR | COBR_EXTNR | Distribution Rule No. | NUMC | 7 | System Generated |
| COBRB | SRSTRAT | SR_STRAT | Strategy | CHAR | 3 | System Generated |
| COBRB | GABPE | GABPE | From Period- Valid From Period | NUMC | 3 | Conditional |
| COBRB | GABJA | GABJA | From Fiscal Year- Valid From Year | NUMC | 4 | Conditional |
| COBRB | GBISJ | GBISJ | To Period- Valid To | NUMC | 4 | Conditional |
| COBRB | GBISP | GBISP | To Fiscal Year- Valid to Year | NUMC | 3 | Conditional |
| COBRA | APROF | APROF | Settlement Profile | CHAR | 6 | System Generated |
| COBRB- | KOSTL | BRGKOSTL | Settlement Receiver- Cost Center | CHAR | 10 | System Generated |
| COBRB | PAOBJNR | RKEOBJNR | Settlement Receiver- Profitability Segment | CHAR | 10 | System Generated |
| COBRB | HKONT | SAKNR | Settlement Receiver- G/L Account | CHAR | 10 | Mandatory |
| COBRB | EXTNR | COBR_EXTNR | Distribution Rule Number | NUMC | 3 | System Generated |
| Currency for the amount in the amount rule | CUKY | 5 | System Generated | |||
| COBRB | KOKRS | BRGKOKRS | Controlling Area of Receiver | CHAR | 4 | System Generated |
| COBRB | BUKRS | BUKRS | Company Code | CHAR | 4 | System Generated |
| COBRB | SRSTRAT | SR_STRAT | Strategy for automatic generation of settlement rules | CHAR | 3 | System Generated |
Data object WBS - Capex, Opex, Settlement Rule will be collected specifically for data migration.
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
| Not applicable |
The high-level process is represented by the diagram below:

The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate. The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
| Req # | Requirement Description | Team Responsible |
|---|---|---|
| 1 | Ensure DCT is collected | Data Team |
| 2 | Perform preliminary completeness check, data quality check. | Data Team |
| 3 | Raise issues as defects if Req # 1 to 2 are not met | Data Team |
| 4 | Repeat Req # 1 to 3 if required | Data Team |
Selection Screen
| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
| Not Applicable |
Data Collection Template (DCT)
Target Ready Data Collection Template will be created for WBS - Capex, Opex, Settlement Rule data with exception of some fields which require transformation as mentioned in the transformation rule.WBS - Capex, Opex, Settlement Rule DCT Rules
| Field Name | Field Description | Rule |
|---|---|---|
| OBJNR | WBS element | Sender WBS element that will have its costs settled. Rule: For WBS elements governed by CAPEX project profile ZPS0001, Account assignment element PRPS-BELKZ = active, WBS level PRPS-STUFE=3, with investment profile PRPS-IMPRF not blank and Capex flag PRPS-ZX01 b. G/L- G/L account - Account assignment category G/L specifies a receiver category of "G/L Account'. Rule: Provision WBS with project profile ZPS0005, WBS level PRPS-STUFE=2, Account assignment element PRPS-BELKZ = active It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template. |
| KONTY | Account Assignment Category | Account assignment category determine the type of settlement receiver type. a. FXA- Asset - Account assignment category FXA specifies a receiver category of "Fixed Asset". Required for AUC cost on Capex WBS to Settled to fixed asset. Rule - For WBS elements governed by CAPEX project profile ZPS0001, Account assignment element PRPS-BELKZ = active, WBS level PRPS-STUFE=3, with investment profile PRPS-IMPRF not blank and Capex flag PRPS-ZX01 not blank. It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template. b. G/L- G/L account - Account assignment category G/L specifies a receiver category of "G/L Account'. Rule - Provision WBS with project profile ZPS0005, WBS level PRPS-STUFE=2, Account assignment element PRPS-BELKZ = active It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template. Note: Account assignment category, CTR- Cost Center, PSG- Profitability Segment, WBS- WBS element are applicable for Automatic settlement rule |
| EMPGE | Settlement Receiver | Settlement receiver based on the account assignment category selected. For account assignment category - FXA- Asset, Capex WBS with project profile ZPS0001 as WBS per rule defined above, settlement receiver = Fixed asset For account assignment category - G/L- G/L account -Provision WBS with project profile ZPS0005 as per WBS rule defined above, settlement receiver = G/L Account It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template. |
| PROZS | Percent | This field specifies the percentage, at which costs collected in the sender object are distributed to the specified settlement receiver. Conditional field |
| BETRR | Amount | Fixed amount to be settled to settlement receiver. Conditional field |
| PERBZ | Settlement type | Settlement type determines whether costs are settled periodically or in a full settlement. Settlement rule with Account Assignment Category = FXA or G/L account, settlement type = FUL Full Settlement |
| GABPE | Valid From Period | Period value from which a distribution rule is applied to limit the validity duration of a distribution rule. Conditional field |
| GABJA | Valid From Year | Year value from which a distribution rule is applied to limit the validity duration of a distribution rule. Conditional field |
| GBISJ | To Period- Valid To | Period value up to which a distribution rule is applied to limit the validity duration of a distribution rule Conditional field |
| GBISP | To Fiscal Year- Valid to Year | Year value up to which a distribution rule is applied to limit the validity duration of a distribution rule. Conditional field |
| ANLN1 | Settlement Receiver- Fixed Asset | For account assignment category - FXA- Asset, Capex WBS with project profile ZPS0001 as per rule defined above. It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template. |
| HKONT | Settlement Receiver- G/L Account | For account assignment category - G/L- G/L account -Provision WBS with project profile ZPS0005 as per rule defined above. It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template. |
| Instance | Instance where the WBS Settlement Rule is to be loaded. (Field required in DCT) |
DCT Rule applicable for Settlement rule generated automatically in S/4 Hana with transaction code CJB1 / CJB2
| Field Name | Field Description | Rule |
|---|---|---|
| OBJNR | WBS element | Sender WBS element that will have its costs settled. Account assignment to be active. Rule applicable for Settlement rule generated automatically in S/4 Hana with transaction code CJB1 a. Automatic Settlement rule to PSG - For WBS elements governed by project profile ZPS0001 with WBS Project type PRPS-PRART = 17, 26, 27, 37. 38. 40 and project project = zsp0002 with WBS project type = 39, with Account assignment element PRPS-BELKZ = active, PRPS-ZX01 OPEX flag active. b. Automatic Settlement rule to Cost Centre - For WBS elements governed by project profile ZPS0001 with WBS Project type PRPS-PRART = 18 and project project = zsp0002 with WBS project type = 26, 27, 41, with Account assignment element PRPS-BELKZ = active, PRPS-ZX01 OPEX flag active. It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template. |
| Period | It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template. | |
| Fiscal year | It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template. |
No Dependencies for Extract
| Item # | Step Description | Team Responsible |
|---|---|---|
| Not applicable |
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Obtain DCT Sign-off from Business | Data Team |
2 | Execute and Load and perform Transformation | Data Team |
3 | Monitor the transformation progress and ensure performance and completion is within allowed timeframe | Data team |
4 | Review and Validate Error and Preload Reports | Data Team |
5 | Generate data load count. | Data team |
6 | Generate Load Files | Data Team |
7 | Log errors as defects, if any and address resolutions. Close defects. | Data team |
| 8 | Re-transform and re-validate the Pre-load reports if necessary. | Data team |
| 9 | Validate the transformed file as part of pre-load validation, raise data defects or provide the pre-load sign-off. | Business |
| 10 | Analyze and resolve any pre-load defects logged by business. | Data team |
| 11 | Repeat steps 7 to 10 if necessary | Data team |
| 12 | Proceed to pre-load validations | Data team |
Transformation Rules
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| 1 | DCT | COBRB | OBJNR | WBS element | S/4 Hana | COBRB | OBJNR | WBS element | Copy from source to target system |
| 2 | DCT | COBRB | KONTY | Account Assignment Category | S/4 Hana | COBRB | KONTY | Account Assignment Category | Copy from source to target system |
| 3 | DCT | COBRB | ANLN1 (Fixed Asset) HKONT (G/L Account) | Settlement Receiver | S/4 Hana | DKOBR | EMPGE | Settlement Receiver | Value Mapping: Old to new Fixed Asset for Account Assignment Category = FXA Value Mapping: Old to new G/L Account for Account Assignment Category = G/L |
| 4 | DCT | COBRB | PROZS | Percent | S/4 Hana | COBRB | PROZS | Percent | Copy from source to target system |
| 5 | DCT | COBRB | BETRR | Amount | S/4 Hana | COBRB | BETRR | Amount | Copy from source to target system |
| 6 | DCT | COBRB | PERBZ | Settlement Type | S/4 Hana | COBRB | PERBZ | Settlement Type | Copy from source to target system |
| 7 | DCT | COBRB | GABPE | From Period- Valid From Period | S/4 Hana | COBRB | GABPE | From Period- Valid From Period | Copy from source to target system |
| 8 | DCT | COBRB | GABJA | From Fiscal Year- Valid From Year | S/4 Hana | COBRB | GABJA | From Fiscal Year- Valid From Year | Copy from source to target system |
| 9 | DCT | COBRB | GBISJ | To Period- Valid To | S/4 Hana | COBRB | GBISJ | To Period- Valid To | Copy from source to target system |
| 10 | DCT | COBRB | GBISP | To Fiscal Year- Valid to Year | S/4 Hana | COBRB | GBISP | To Fiscal Year- Valid to Year | Copy from source to target system |
| 11 | Controlling area of receiver | S/4 Hana | COBRB | Default from the Receiver | |||||
| 12 | Company Code | S/4 Hana | COBRB | Default |
Transformation Mapping
| Mapping Table Name | Mapping Table Description |
|---|---|
| Controlling Area | Value Mapping: Old to New Controlling Area |
| Cost Centre | Value Mapping: Old to New Cost Centre |
| Fixed Asset | Value Mapping: Old to New Fixed Asset |
| Controlling Area | |
| Company Code |
| Item # | Step Description | Team Responsible |
|---|---|---|
| Ensure all the fields that require value mapping, as stipulated. Mapping tables, have the correct values mapped and imported into tool. | Syway Data Team |
| Task | Action |
|---|---|
Verify Record Count | SyWay I2M Data Team to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets. |
| Task | Action |
|---|---|
Conversion Accuracy | SyWay I2M Data Team to verify that all fields below meet pass the checks:
|
Review Error Reports | Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source (DCT) data. |
| Task | Action |
|---|---|
Verify Record Count | Business Data Owner/s to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets. |
| Task | Action |
|---|---|
Conversion Accuracy | Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules (and signed-off DCT data). |
The load process includes:
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Load using transaction custom upload / custom fiori app | Data Team |
2 | Load 3 records for < > to validate if data is loaded successfully without errors | Data Team |
3 | Load 3 records for < > to validate if data is loaded successfully without errors | Data Team |
4 | Proceed with full load if steps 2 and 3 are validated | Data Team |
5 | Validate few records loaded by accessing | Data Team |
6 | Generate post load report if step 5 is validated | Data Team |
Load Phase and Dependencies
Configuration
| Item # | Configuration Item |
|---|---|
| 1 | Controlling Area |
| 2 | Operating Concern |
| 3 | Project Profile |
| 4 | Determine Strategy for Settlement Rule |
| 5 | Settlement Profile |
| 6 | Assign Strategy to Project Profile |
| 7 | Create Allocation Structure |
| Object # | Preceding Object Conversion Approach |
|---|---|
| 1067 | GL Operational |
| 1070 | Fixed Asset |
| 1026 | WBS - Capex, Opex, Statistical |
| Error Type | Error Description | Action Taken |
|---|---|---|
| 1 | Receiver missing for distribution rule | Correct upload data, Enter the missing receiver |
| 2 | WBS element does not exist | Correct upload data, |
| 3 | Asset not in company Code | Correct upload data |
| 4 | G/L Account not in chart of account | Correct upload data |
| 5 | Cost Centre does not exist | Correct upload data |
| Task | Action |
|---|---|
Verify Count | SyWay I2M Data Team to verify the record count created in target S/4 HANA by accessing post load reports from S/4 HANA. |
Verify Logs | Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.). |
| Task | Action |
|---|---|
Conversion Accuracy | Verify that the tables in target S/4 HANA were loaded correctly via SE16 download |
| Task | Action |
|---|---|
| Verify Count | Extract data in S/4 Hana via fiori tile and verify the count |
| Task | Action |
|---|---|
| Verify Count | Extract data in S/4 Hana via fiori tile and verify the count |
Any additional key assumptions.
Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.