The purpose of this document is to define the conversion approach to maintain the project status in S/4 HANA.
Project and WBS element status consists of System and user statuses which together controls business functions allowed on the object. In the SyWay solution there is integration between the status of the project in PS and the PPM Item.
The scope of this document covers the approach for converting active Project status from Legacy Source Systems into S/4HANA.
There are 2 group go-live as below:
Note: There is possibility to shift into 1 go live date, this option is currently still being considered.
Projects created in each group are treated separately.
Projects created for the go-live group in S/4 with Created status are to be released to allow WBS element to be used for financial posting, excludes template projects. Template project status changes are included in CNV-1019.
The status of Projects and WBS elements migrated from Legacy system is aligned with the status in Legacy system, where the status in the legacy system is not created or released.
The data from legacy system includes:
The data from legacy system excludes:
Before Posting Financials:
Release all projects in S/4 (Scenario 1).
This will allow the posting of actuals and the settlement of cost where relevant by
After Posting Financials :
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
| WP2 | Project Definitions with Reference to PPM Items | S/4 | ||
| WP2 | WBS elements with Mapping from CNV-1026 | S/4 | ||
| PF2 | Project Definitions with Reference to PPM Items | S/4 | ||
| PF2 | WBS elements with Mapping from CNV-1026 | S/4 | ||
| S/4 | Projects in S/4 with created status | S/4 |
Identification
Project Status
Select Object number from table PROJ for PSPID equals Legacy ID
Select Statuses from table JEST using Object Number
WBS Status
Select Object number from table PRPS for PSPHI equals Legacy ID
Select Statuses from table JEST using Object Number
S/4 Projects Status Created (excluding template projects)
Select Object number from table PROJ where PSPID <> T*
Select Statuses from table JEST using Object Number where status is Created (I0001)
And created by Migration User
Not Applicable
Not Applicable
Not Applicable
Not Applicable
With Functional input, document the technical design of the target fields that are in the scope of this document.
The technical design of the target for this conversion approach.
Project Level
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PROJ | PSPID | PS_PSPID | Project Definition | CHAR | 24 | Mandatory |
| PROJ | OBJNR | J_OBJNR | Project Object Number | CHAR | 22 | System Generated |
| TJ02T | TXT04 | J_TEXT_04 | System Status Text | CHAR | 4 | Optional |
| TJ30T | TXT04 | J_TEXT_04 | User Status Text | CHAR | 4 | Optional |
| JEST | OBJNR | J_OBJNR | Object Number | CHAR | 22 | System Generated |
| JEST | STAT | J_STATUS | Status | CHAR | 5 | System Generated |
| JEST | INACT | J_INACT | Indicator Status is inactive | CHAR | 1 | System Generated |
| JEST | CHGNR | J_CHGNR | Change Number | NUMC | 3 | System Generated |
WBS Level
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PRPS | POSID | PS_POSID | WBS ID | CHAR | 24 | Mandatory |
| PRPS | OBJNR | J_OBJNR | WBS Object Number | CHAR | 22 | System Generated |
| TJ02T | TXT04 | J_TEXT_04 | System Status Text | CHAR | 4 | Optional |
| TJ30T | TXT04 | J_TEXT_04 | User Status Text | CHAR | 4 | Optional |
| JEST | OBJNR | J_OBJNR | Object Number | CHAR | 22 | System Generated |
| JEST | STAT | J_STATUS | Status | CHAR | 5 | System Generated |
| JEST | INACT | J_INACT | Indicator Status is inactive | CHAR | 1 | System Generated |
| JEST | CHGNR | J_CHGNR | Change Number | NUMC | 3 | System Generated |
All cleansing requirements dealt with in CNV-1024 Project Definition and CNV-1026 WBS - CAPEX, OPEX, Statistical
If data cleansing is managed outside of the source system (e.g. Syniti Migrate, 3rd Party Vendor, DCT), the necessary documentation must be produced and appended to this deliverable for sign-off.
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|
The high-level process is represented by the diagram below:
Summarize High-Level Process. Include diagrams, where applicable. Include information supporting details of Extract, Transform and Load specific to the Data Object

Extract data from a source into Syniti Migrate. There are 2 possibilities:
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
| Req # | Requirement Description | Team Responsible |
|---|---|---|
| 1 | Extract data from source system based on relevancy rule | SyWay Data Team |
| 2 | Extract data from S/4 system based on relevancy rule | SyWay Data Team |
| 3 | Perform preliminary completeness check, data quality check. | SyWay Data Team |
| 4 | Raise issues as defects if Req # 1 to 2 are not met | SyWay Data Team |
| 5 | Repeat Req # 1 to 3 if required | SyWay Data Team |
| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|
| Field Name | Field Description | Rule |
|---|
List the steps that need to occur before extraction can commence
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1 | Successful Load of CNV-1022 Portfolio Items | SyWay Data Team |
| 2 | Successful load of CNV-1024 Project Definitions | SyWay Data Team |
| 3 | Successful load of CNV-1026 WBS CAPEX, OPEX, Statistical | SyWay Data Team |
The Target fields are mapped to the applicable Legacy field that will be its source. This identifies the transformation activity required to allow Syniti Migrate
to make the data Target ready:
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1 | Execute Load and perform Transformation | Data team |
| 2 | Monitor the transformation progress and ensure performance and completion is within allowed timeframe | Data team |
| 3 | Review and Validate Error and Preload Reports | Data Team |
| 4 | Generate data load count. | Data team |
| 5 | Generate Load Files | Data Team |
| 6 | Log errors as defects, if any and address resolutions. Close defects. | Data team |
| 7 | Re-transform and re-validate the Pre-load reports if necessary. | Data team |
| 8 | Validate the transformed file as part of pre-load validation, raise data defects or provide the pre-load sign-off. | Business |
| 9 | Analyze and resolve any pre-load defects logged by business. | Data team |
| 10 | Repeat steps 7 to 10 if necessary | Data team |
| 11 | Proceed to pre-load validations | Data team |
Transformation Rules
The transformation is done in 3 Scenarios.
Scenario 1.
Update the status of projects in S/4 in Created Status- the below transformation assumes BAPI_BUS2001_SET_STATUS or transaction CNMASSSTATUS
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| S/4 | PROJ | PSPID | Project Definition | S/4 Hana | PROJ | PSPID | Project Definition | Copy from Source | |
| S/4 Hana | TJ02T | TXT04 | Status | Default to "REL" |
Scenario 2
Align the status of WBS elements migrated through CNV-1026 with the status of the wbs element in legacy system. The below transformation assumes BAPI_BUS2054_SET_STATUS or transaction CNMASSSTATUS
The status from legacy may be mapped to either a system or a user status in S/4 Hana
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| PF2/WP2 | PRPS | POSID | WBS Element | S/4 Hana | PRPS | PSPID | WBS Element | Mapping Table Old WBS Element to New WBS | |
| PF2/WP2 | JEST | STATUS | Status | S/4 Hana | TJ02T | TXT04 | System Status | Mapping: Legacy_PRPS_Status where Legacy status has Hana_System_Status | |
| PF2/WP2 | JEST | STATUS | Status | S/4 Hana | TJ30T | TXT04 | User Status | Mapping: Legacy_PRPS_Status where Legacy status has Hana_User_Status |
Scenario 3
Align the status of Project Definition, with Legacy ID's, with status of Project Definition in legacy system. The below transformation assumes BAPI_BUS2001_SET_STATUS or transaction CNMASSSTATUS
The status from legacy may be mapped to either a system or a user status in S/4 Hana
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| PF2/WP2 | PROJ | PSPID | Project Definition | S/4 Hana | PROJ | PSPID | Project Definition | Mapping Table Old WBS Element to New WBS | |
| PF2/WP2 | JEST | STATUS | Status | S/4 Hana | TJ02T | TXT04 | System Status | Mapping: Legacy_PRPS_Status where Legacy status has Hana_System_Status | |
| PF2/WP2 | JEST | STATUS | Status | S/4 Hana | TJ30T | TXT04 | User Status | Mapping: LLegacy_PRPS_Status where Legacy status has Hana_User_Status |
| Mapping Table Name | Mapping Table Description |
|---|---|
| Legacy_PRPS_Status | Mapping System and User Status from Legacy Systems to S/4 Status Source System, Object Type (PD or WBS), Legacy Status (Number), Hana_System_Status (TXT04), Hana_User_Status (TXT04) |
WBS Elements | POSID: Old WBS Elements to New WBS Elements |
Status Mapping
| Source | Object Type | Legacy Status | System Status Description | S4_System_Status | System Status Description | S4_User_Status |
| PF2 | Project | I0045 | Technically completed | TECO | Technically completed | |
| PF2 | Project | I0046 | Closed | CLSD | Closed | |
| PF2 | Project | I0065 | Master data locked | MDLK | Master data locked | |
| WP2 | Project | I0045 | Technically completed | TECO | Technically completed | |
| WP2 | Project | I0065 | Master data locked | MDLK | Master data locked | |
| WP2 | Project | I0046 | Closed | CLSD | Closed | |
| WP2 | WBS | I0045 | Technically completed | TECO | Technically completed | |
| WP2 | WBS | I0046 | Closed | CLSD | Closed | |
| WP2 | WBS | I0065 | Master data locked | MDLK | Master data locked | |
| PF2 | WBS | I0045 | Technically completed | TECO | Technically completed | |
| PF2 | WBS | I0046 | Closed | CLSD | Closed | |
| PF2 | WBS | I0065 | Master data locked | MDLK | Master data locked |
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1 | Ensure all the fields that require value mapping, as stipulated in Section "Mapping tables", have the correct values mapped. | SyWay Data Team |
| Task | Action |
|---|---|
Verify Counts | Data team to verify the load count is the same as per identified identified from JEST. |
| Task | Action |
|---|---|
| Conversion Accuracy | SyWay I2M Data Team to verify that all fields below meet pass the checks:
|
Review Error Reports | Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data. |
| Task | Action |
|---|---|
Verify Record Count | Business Data Owner/s to verify that the total number of relevant records is equal to the total number of records in the Preload and Load Sheets. |
| Task | Action |
|---|---|
Conversion Accuracy | Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules. |
The load process includes:
| Item # | Step Description | Team Responsible |
|---|---|---|
| 1 | Load Scenario 1 using transaction using load tool | SyWay Data Team |
| 2 | Load 3 records for < > to validate if data is loaded successfully without errors | SyWay Data Team |
| 3 | Load 3 records for < > to validate if data is loaded successfully without errors | SyWay Data Team |
| 4 | Proceed with full load if steps 2 and 3 are validated | SyWay Data Team |
| 5 | Validate few records loaded by accessing Project Report | SyWay Data Team |
| 6 | Load Scenario 2 using transaction using load tool | SyWay Data Team |
| 7 | Load 3 records for < > to validate if data is loaded successfully without errors | SyWay Data Team |
| 8 | Load 3 records for < > to validate if data is loaded successfully without errors | SyWay Data Team |
| 9 | Proceed with full load if steps 7 and 8 are validated | SyWay Data Team |
| 10 | Validate few records loaded by accessing WBS Report | SyWay Data Team |
| 11 | Load Scenario 3 using transaction using load tool | SyWay Data Team |
| 12 | Load 3 records for < > to validate if data is loaded successfully without errors | SyWay Data Team |
| 13 | Load 3 records for < > to validate if data is loaded successfully without errors | SyWay Data Team |
| 14 | Proceed with full load if steps 12 and 13 are validated | SyWay Data Team |
| 15 | Validate few records loaded by accessing Project Report | SyWay Data Team |
| 16 | Generate post load report if step 18 is validated | SyWay Data Team |
| 17 | Business to validate the post load files as part of post-load validation, raise data defects or provide the post-load sign-off. | SyWay Data Team |
Load Phase and Dependencies
The project status update may be required to be executed before and after the financial postings i
Generation of the Load file to consider the Project Definitions loaded to S/4 based on the Go-Live Group.
There are 2 group go-live as below:
Note: There is possibility to shift into 1 go live date, this option is currently still being considered.
List the Configurations required before loading can commence
| Item # | Configuration Item |
|---|---|
| 1 | WBS User Status |
| 2 | Project Profile |
| Object # | Preceding Object Conversion Approach |
|---|---|
| 1 | 1026 - WBS CAPEX, OPEX, STATISTICAL |
| 2 | 9031 - Project - Actual GL Line Items (PNL - WBS for AuC) |
| 3 | 9032 - GL Line Items (PNL - Internal Order, Statistical/ Opex WBS) |
The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management
| Error Type | Error Description | Action Taken |
|---|---|---|
| Invalid Data | Project Definition has not been created in S/4HANA hence status cannot be set | Review load of CNV-1022 |
| Invalid Data | WBS has not been created in S/4HANA hence WBS hence status cannot be set | Review load of CNV-1026 |
| System validation | Setting of new status not allowed due to active System / User Status | Correct upload data, review mapping rules |
| Task | Action |
|---|---|
Verify Count | SyWay I2M Data Team to verify the record count created in target S/4 HANA by accessing post load reports or standard reports (CN41n) from S/4 HANA. |
Verify Logs | Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.). |
| Task | Action |
|---|---|
Conversion Accuracy | Verify that the Project Definition in target S/4 HANA were loaded correctly via Project Builder display and Reports like CN41N |
| Task | Action |
|---|---|
| Verify Project data - Project Definition | Extract data from PS report CN41N in S/4 Hana and compare with expected record counts |
| Task | Action |
|---|---|
| Verify Project data - Project Definition | Extract data from PS report CN41N in S/4 Hana |
| Reconcile | Post load report for projects with legacy project id's containing ECC Project and WBS System and User Status with S/4 Hana Project WBS element System and User Status |
Any additional key assumptions.
Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.