Technology team will be using Jira project to manage and track the following tasks.
SyWay Technology Team Jira Project |
Tasks should not be raised for activities that has an established process. For example: |
For SAP note implementation, the requester will need to provide a SAP TR number in the description for the Basis team to use. It is the requester's responsibility to manage this TR and ensure it is transported to the subsequent systems.
Please contact the following reps for queries.
| Domain | Rep. |
|---|---|
| Basis/Infra | |
| Development/Integration | |
| Fiori/UI | |
| Security | |
| Reporting/Analytics |

| Field | Updated by | Details |
|---|---|---|
| Summary | Requester | Brief description of the Tasks |
| Description | Requester | Provide details on the requirements (more details and justification will speed up the completion time) |
| SyWay Release | Requester | Which release this is applicable for (R1, R2, etc.) |
| Workstream | Requester | Which workstream this is task for |
| Reporter | Auto | Tasks requester and tester (if required) |
| Technology Tasks | Requester | Please only choose Basis Tasks, SAP Note Implementation or SAP Security Roles & Authorization. Other tasks are meant for tech team's internal use. |
| Assignee | Auto | Auto assigned to based on the tasks selected. |
| Date Raised | Auto | Auto filled |
| Due Date | Requester | Target date task to be completed. |