Purpose

The purpose of this document is to define the conversion approach to create Safety Certificate Template in S/4 HANA.

SAP Safety Certificate Templates are standardized forms used in SAP S/4HANA to manage workplace safety requirements. They allow planners to define safety precautions, link certificates to work permits, and ensure compliance with plant safety regulations. Templates streamline certificate creation by providing reusable structures tailored to specific activities or plants

In Syensqo’s SAP S/4HANA landscape a work permit template provides a predesigned structure that can be used to create work permits in a consistent format. Creating work permits using a template allows you to simplify and streamline the work permit generation process.

The governance of this object shall be managed through tier 2.

Conversion Scope

The scope of this document covers the approach for creating Safety Certificate Template into S/4HANA following the Safety Certificate Template Master Data Design Standard. 

All Data for Safety Certificate Template are fully construted in the DCT.

The data from legacy system includes:

  1. Not applicable

The data from legacy system excludes:

  1. Not applicable

Note: There are no tables to extract from the source systems


List of source systems and approximate number of records
SourceScope

Source Approx No. of Records

Target SystemTarget Approx

No. of Records

DCTAll Permit to Work data will be fully constructed, as it does not currently exist in the source systems and represents a new design in the to-be Syensqo landscape.300S/4 HANA300

Additional Information

Multi-language Requirement

Based on the plant the language will be localized.

Document Management

Not Applicable

Legal Requirement

Not Applicable

Special Requirements

Not Applicable




Target Design

With Functional input, document the technical design of the target fields that are in the scope of this document.

The technical design of the target for this conversion approach.

1.General information

TableFieldData ElementField DescriptionData TypeLengthRequirement
ISFTYCERTTMPL

NumberCHAR12System
ISFTYCERTTMPL

DescriptionCHAR40Mandatory
ISFTYCERTTMPL

Maintenance Planning PlantCHAR4Mandatory
ISFTYCERTTMPL

Safety Certificate Template typeCHAR3Mandatory
ISFTYCERTTMPL

Valid FromDATS8Mandatory
ISFTYCERTTMPL

Valid-From TimeTIMS6Mandatory
ISFTYCERTTMPL

Valid toDATS8Mandatory
ISFTYCERTTMPL

Valid-To TimeTIMS6Mandatory
ISFTYCERTTMPL

Main Work CenterCHAR8Mandatory
ISFTYCERTTMPL

Main Work Center PlantCHAR4Mandatory

2.Safety Precautions

TableFieldData ElementField DescriptionData TypeLengthRequirement
PTWSFTYRQMTGRP

Safety Precautions CategoryCHAR3Mandatory
PTWSFTYRQMTTXT  Safety Precautions DescriptionCHAR3Mandatory

3.Approvals

TableFieldData ElementField DescriptionData TypeLengthRequirement
ISFCMAPPROVAL

Approval typeCHAR10Mandatory
ISFCMAPPROVAL

Approval Description

System
ISFCMAPPROVAL

Approval Requirement  System
ISFCMAPPROVAL

Approval Information  System
ISFCMAPPROVAL

Approval statusCHAR1Mandatory

Safety Certificate Template Data strictly adheres to the Master Data Standard. The complete information of the key fields that hold the Permit to Work Template information follows the Master Data Standard document that is located here.

Data Cleansing

Safety Certificate Template not exist in the legacy system. Therefore, data cleansing is not applicable.

Data for the Safety Certificate Templat  will be captured directly in the Data Collection Template (DCT) and any required refinement will be carried out during the data construction activity.

IDCriticalityError Message/Report DescriptionRuleOutputSource System


Not Applicable


Note: List of Cleansing is maintained here: Conversion Specs Register (DCT & Cleansing Report)


Conversion Process

The high-level process is represented by the diagram below:

Collection will be done manually in the Data Collection Template for the following scenarios:

  • For all A2D In-scope Planning Plants.

Data Privacy and Sensitivity

Not Applicable


Extraction

Data extraction is not applicable, as no corresponding data exists in the legacy system.

Extraction Run Sheet

Req #Requirement DescriptionTeam Responsible

Not Applicable


Selection Screen

If applicable, this section will give the details on any selection screen parameters, including the parameter type, that are required to be entered to ensure consistent data extracts.
Selection Ref ScreenParameter NameSelection TypeRequirementValue to be entered/set

Not Applicable



Data Collection Template (DCT)

Target Ready Data Collection Template will be created for Safety Certificate Template data with exception of some fields which require transformation as mentioned in the transformation rule.

Note: All rules specified below should be documented as a tooltip in the DC Page.

Format:

  • Line 1: Mandatory / Conditional
  • Line 2: Remaining text

1.General information DCT Rules

Field NameField DescriptionRule

Number



Description


Note: 

- Template will start with three letters, which will be a prefix for the type of safety certificate (e.g. CON for Confined Space, HOT for hot work, etc). This is followed by a running number. The prefix for the description must be aligned with the safety certificate template type setup in the configuration, e.g. the description of a confined space certificate can only be created for a confined space certificate template type.

- AAA - Safety certificate 

- NNN should be running number

- All Letters must be Capital

- There should be no duplicate descriptions within the same plant.

-Example: CON-001, CON-002, etc.


Maintenance Planning Plant


Note: 

Manual input based on plant where safety certuificate template  is designed for


Safety Certificate Template type

Valid From


Note:

 Must be current or future date. No date in past.


Valid-From Time

Valid toMust be a date in future and later than the Valid From date.

Valid-To Time

Main Work Center

Main Work Center Plant

 2.Safety Precautions DCT Rules

Field NameField DescriptionRule

Safety Precautions Category

Safety Precautions Description

 3.Approvals DCT Rules

Field NameField DescriptionRule

Approval type

Approval Description

Approval Requirement

Approval Information

Approval status

Extraction Dependencies

List the steps that need to occur before extraction can commence

Item #Step DescriptionTeam Responsible













Transformation

The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:

  1. Perform value mapping and data transformation rules.
    1. Legacy values are mapped to the to-be values (this could include a default value)
    2. Values are transformed according to the rules defined in Syniti Migrate
  2. Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation

Transformation Run Sheet

Item #Step DescriptionTeam Responsible













Transformation Rules

Rule #Source systemSource TableSource FieldSource DescriptionTarget SystemTarget TableTarget FieldTarget DescriptionTransformation Logic









































Transformation Mapping

Use the exact name and reference this section in the “Transformation rules” above
Mapping Table NameMapping Table Description








Transformation Dependencies

List the steps that need to occur before transformation can commence
Item #Step DescriptionTeam Responsible













Pre-Load Validation

Project Team

The following pre-load validations will be performed by the Project Team.

Completeness

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Accuracy

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Business

The following pre-load validations will be performed by the business.

Completeness

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Accuracy

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Load

The load process includes:

  1. Execute the automated data load into target system using load tool or product the load file if the load must be done manually
  2. Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation

Load Run Sheet

Item #Step DescriptionTeam Responsible













Load Phase and Dependencies

Identify the phase as to “when” the load for this object will occur. <Pre-Cutover, Cutover, Post Cutover> and list the steps that need to occur before the load can commence

Configuration

List the Configurations required before loading can commence

Item #Configuration Item






Conversion Objects

Object #Preceding Object Conversion Approach

list the exact title of the conversion object of only the immediate predecessor – this will then confirm the DDD (Data Dependency Diagram)




Error Handling

The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management

Error TypeError DescriptionAction Taken










Post-Load Validation

Project Team

The following post-load validations will be performed by the Project Team.

Completeness

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Accuracy

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Business

The following post-load validations will be performed by the business.

Completeness

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Accuracy

TaskAction
titlespecific details of what and how the task needs to be performed e.g. which reports are being used etc.





Key Assumptions

  • Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
  • Data Object is in scope based on data design and any exception requested by business.

Any additional key assumptions.


See also

Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.

Change log