The purpose of this document is to define the conversion approach to load Maintenance Plan Start in order to Start the Maintenance Plans in S/4 HANA.
The purpose of the Maintenance Plan Start is to initiate the creation of Work Orders based on the criteria specified in the Maintenance Plans.
Maintenance Plans for Syensqo are defined with the purpose of:
The conversion scope covers the approach for loading Maintenance Plan Start in S/4 HANA system.
The data from legacy system includes:
The data from legacy system excludes:
List of source systems and approximate number of records
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
| PF2, WP2 | Relevant Maintenance Plan for Maintenance Plan Start will be extracted from PF2 and WP2. | 70,000 | S/4 HANA | 70,000 |
| DCT | Maintenance Plan for Maintenance Plan Start for plants which do not have data existing from PF2 and WP2 | TBD | S/4HANA | TBD |
| DCT | Relevant Maintenance Plan for Maintenance Plan Start will be extracted from PF2 and WP2 which require business decision. |
Not Applicable
Not Applicable
Not Applicable
Not Applicable
If the data conversion involves third-party systems or external data sources, such as Icertis, describe any additional requirements related to data mapping, transformation logic, validation rules or security measures that must be followed.
With Functional input, document the technical design of the target fields that are in the scope of this document.
The technical design of the target for this conversion approach.
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| MPLA | WARPL | WARPL | Maintenance Plan Identifier | CHAR | 12 | Mandatory |
| MPLA | STADT | STADT | Start Date for Scheduling | DATS | 8 | |
| MPLA | STIME | Start Time for Scheduling | TIMS | 6 | ||
| MPLA | SZAEH | SZAEHC | Start counter reading | CHAR | 22 | |
| MPLA | LRMDT | Date of Last Completion in Maintenance Plan | ||||
| MPLA | CONF_TIME | Completion Time of Call | ||||
| MPLA | ZYKLOFFSET | Offset with Start in Cycle | Mandatory | |||
| MPLA | ZYKLUNIT | Unit for the Performance of Maintenance Tasks | ||||
| MPLA | RZAEH | Completion Counter Reading | ||||
| MPLA | CYCLESEQIND | Cycle Set Sequence | ||||
| MPLA | SETREPEATIND | Repeat Factor for Cycle Set Sequence | ||||
| MPLA | KEEP | Keep Calls on Hold (KEEP=X) or Delete Calls on Hold (KEEP=' ') Default Value |
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
PF2, WP2 |
Note: List of Cleansing is maintained here: Conversion Specs Register (DCT & Cleansing Report)
The high-level process is represented by the diagram below:

Data Privacy and Sensitivity
Summarize Data Privacy and Sensitivity Requirements, if any| Req # | Requirement Description | Team Responsible |
|---|---|---|
| 1 | Extract data from source system based on relevancy rule | SyWay Data Team |
| 2 | Google Sheet report pre-populated with PF2 and WP2 information to be generated based on relevancy criteria. | SyWay Data Team |
Selection Screen
If applicable, this section will give the details on any selection screen parameters, including the parameter type, that are required to be entered to ensure consistent data extracts.| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
<Object> DCT Rules
| Field Name | Field Description | Rule |
|---|---|---|
List the steps that need to occur before extraction can commence
| Item # | Step Description | Team Responsible |
|---|---|---|
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti Migrate to make the data Target ready:
| Item # | Step Description | Team Responsible |
|---|---|---|
Transformation Rules
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| Mapping Table Name | Mapping Table Description |
|---|---|
Exclusion List of Maintenance Plans to be Started | |
| Item # | Step Description | Team Responsible |
|---|---|---|
| Task | Action |
|---|---|
| Verify Record Count | SyWay A2D Data Team to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets. |
| Task | Action |
|---|---|
| Conversion Accuracy | SyWay A2D Data Team to verify that all fields below meet pass the checks:
|
| Review Error Reports | Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data. |
| Task | Action |
|---|---|
| Verify Record Count | Business Data Owner/s to verify that the total number of relevant records from the the DCT is equal to the total number of records in the Preload and Load Sheets. |
| Task | Action |
|---|---|
| Conversion Accuracy | Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules (and signed-off DCT data). |
The load process includes:
| Item # | Step Description | Team Responsible |
|---|---|---|
Load Phase and Dependencies
Identify the phase as to “when” the load for this object will occur. <Pre-Cutover, Cutover, Post Cutover> and list the steps that need to occur before the load can commence
List the Configurations required before loading can commence
| Item # | Configuration Item |
|---|---|
| Object # | Preceding Object Conversion Approach |
|---|---|
| list the exact title of the conversion object of only the immediate predecessor – this will then confirm the DDD (Data Dependency Diagram) | |
The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management
| Error Type | Error Description | Action Taken |
|---|---|---|
| Task | Action |
|---|---|
Verify Count | SyWay A2D Data Team to verify the record count created in target S/4 HANA by accessing post load reports in dspMigrate or standard reports from S/4 HANA. |
Verify Logs | Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.). |
| Task | Action |
|---|---|
Conversion Accuracy | Verify that the EAM Maintenance Plant Start data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA. |
| Task | Action |
|---|---|
Verify Count | Download Post Load Reports from dspMigrate and verify that the record count loaded in the target S/4 HANA is the same count as of the endorsed load file. |
| Task | Action |
|---|---|
Conversion Accuracy | Verify that the EAM Maintenance Plant Start data in target S/4 HANA were loaded correctly via dspMigrate post load reports or standard reports from S/4 HANA. |
Any additional key assumptions.
Insert links and references to other documents which are relevant when trying to understand this decision and its implications. Other decisions are often impacted, so it's good to list them here with links. Attachments are also possible but dangerous as they are static documents and not updated by their authors.