| Domain: Finance Data & Reporting |
Responsibility area: Maintain Costing Master Data |
The purpose of this document is to describe the process of creating a profit center.
This document applies to all the processes of creating a profit center.
I receive a request to create a new profit center.
Only authorized requesters should be able to ask for data.
In the case of Costing master data, which is the case of the profit center, usually it's a GBU/function Controller.
Check that the requester is an “authorized requester” in document
This list is maintained by the Process Expert Costing assigned to Data Management.
I check that the profit center that needs to be created follows these rules:
All new profit center groups and new profit center created have to be transferred from PF2 & WP2 to MDG system (Profit center D* and F* only for PF2).
Execute
|
And execute
You will have a message validate:
New message , validate:
|
In WP2, since we can not restrict the usage of the profit center to a certain controlling area, it is recommended that whenever creating a new profit center in a certain controlling area, it's also extended to the VPART nodes in the other active controlling areas.
It's common that some intercompany processes occur between companies operating in different controlling areas, where the origin profit center is taken in the several subsequent steps in the other controlling area. In order to avoid blocking this particular processes or generating assignments to dummy profit centers (Example: Z006-9999 in controlling area Z006), it's better to have all the profit centers available in all the active controlling areas.
You can find the VPART nodes in each profit center hierarchy at the bottom of the list:

There's only one VPART node per GBU. You should create the required VPART profit center by copy from the one created in the main controlling area and just change the related profit center group parameter, so it gets properly assigned to the VPART nodes and not in any other controlling area nodes:
Example:

I notify the requester.