| Status | |
| Owner | Eric TRIFFAUX |
| Stakeholders | LAI DAWN, MATHE, Alexandre , TRIFFAUX, Eric |
Decision: Option 1: GCP same project : reuse existing project with an additional machine to not impact the run activities, while the data export will be huge. (today the delegation are managed manually) Decision made by: LAI DAWN, MATHE, Alexandre , TRIFFAUX, Eric Date: Online Meeting: 2026.04.02 - GAM VM alignment call |
The data extraction phase is scheduled to commence in early April and will conclude by late June , running concurrently with the five migration waves to ensure all necessary data is captured prior to final decommissioning.
Activity | Pilot | Wave 1 | Wave 2 | Wave3 | Wave4 | Wave5 |
Audit and Data extraction | N/A | 08/04/2026 | 15/04/2026 | 27/04/2026 | 1/05/2026 | 6/05/2026 |
Go/NoGo to start Prestaging | 2/03/2026 | 10/04/2026 | 17/04/2026 | 29/04/2026 | 5/05/2026 | 8/05/2026 |
Go/NoGo to start Cutover Readiness | 16/03/2026 | 4/05/2026 | 11/05/2026 | 18/05/2026 | 25/05/2026 | 1/06/2026 |
Go/NoGo to start Cutover Execution | 20/03/2026 | 8/05/2026 | 15/05/2026 | 22/05/2026 | 29/05/2026 | 5/06/2026 |
Cuto-off/Go-Live | 23/03/2026 | 11/05/2026 | 18/05/2026 | 25/05/2026 | 1/06/2026 | 8/06/2026 |
To perform all of those activities Syensqo will rely on Revevol who will use Google Application Manager (GAM).
Go for Option 1 reusing one of the existing GCP project running GAM today for daily operation with a new dedicated machine completely delegated to Dawn and Revevol. Delete the data and or the machine a the end of the migration in June or July 2026.
Option 1: GCP same project : reuse existing project with an additional machine to not impact the run activities, while the data export will be huge. (today the delegation are managed manually)
Option 2: GCP but with a new project completely managed by REVEVOL : replicate current GCP project flows etc, Dawn having the access, and sharing appropriate permission with Revevol only. But do not make sense to segregate the project while we can have a dedicated machine in one of the existing project.
Option 3: AWS : too long, and extra security concerns
Option 4: AZURE : too long, and extra security concerns, Azure is not yet configured for T0
Option 5: Revevol : if we can handle on our GCP , better to avoid.
The following section describes relevant documentation:
Description | Repository | ||
| GAM High and Low level Design | |||