| Domain: SU Management Accounting |
Responsibility area: Maintain Costing Master Data |
The purpose of this document is to describe the process of creating a WBS (OPEX/Expense).
This document applies to all the processes of creating a WBS to process expense costs (non capitalized).
I receive a request to create a WBS, some mandatory fields are necessary such as:
After the project code is provided and details to introduce into the WBS we can enter the project using CJ02 or CJ20N, in this case we will use "R8.PU05SP" and T-Code CJ20N in WP2.
![]()

The Project Structure has Project R8.PU05SP in first line, WBS level 1 R8.PU05SP in second line and WBS level 2 R8.PU05SP.xxx in third line.

In this case we will create a new WBS Element (level 2) R8.PU05SP.305 inside Level 1 WBS R8.PU05SP.
By selecting WBS Level 1, right click mouse to view options and select Create > WBS Element.
![]()
The new line in the project was now created but with several empty fields in tab Basic data that will need to be edited:
WBS Element Code: R8.PU05SP.305 |
Next tab to be maintained is Assignments:
The fields will be automatically populated using the same information provided in the Project Master data.
|
Next tab to be maintained is User fields:
Only some GBU's use field Code of Group, in order to aggregate projects by groups created in T-Code ZWPST004. Checkboxes: X Replicon (If the WBS is used to track and charge hours of labor by engineer's or laboratory employees)
|
Next tab to be maintained is Cust. Enhancement:
The majority of the information related to Cust. Enhancement is to identify the market that is related the WBS and Invoicing information. First Fields are related to the GBU/Business Unit, that should be filled in according to request.
Fill in next fields related to WBS Family, and Position Code (SMR7 Approver) provided by the requester.
Specifically for R&I Projects the WEGO Number and Category can be requested: |
The Settlement Rule and Settlement Parameters define how the costs will be processed for expense costs we can have the following cost objects available:
Options Available will change according to what is defined in the Settlement Rule Parameters:
For R&I WP2 example, to allocate costs to a CC in the Settlement Parameters should be the Settlement Profile: ZPS3 and Allocation Structure: AL. There are several different combinations possible in order to reflect the costs with different accounts in the receiver cost object. |