| Status | Approved |
| Owner | |
| Stakeholders | GERVAIS, Pascal ROSSE, Jean-Luc Lorena Baggio, Alain Theoret |
Issue
Several Manufacturing Plants in the current scope for project Sy-Way are not using AVEVA PI nor Aspentech. Therefore, we must define a common solution for Manufacturing Control and Actual Production Postings for these plants.
The list of plants includes:
| Specialty Polymers | NEWARK |
| Specialty Polymers | Rheinberg |
| Novecare | Dhaymers(Taboão) |
| Novecare | Méréville |
| Novecare | Levin |
| Novecare | Roha |
| Composite Materials | Rock Hill SC |
| Composite Materials | Orange CA |
| Composite Materials | Kalamazoo MI |
As per the information collected in Conceptual Design
Newark plant is currently in SAP ECC, but it is not using any Manufacturing SAP functionality.
Recommendation
The Project Team recommend Option 2: use one single Production Confirmation Dashboard to fulfill with one object three requirements coming from different directions:
- Provide a flexible and easy to use tool for production confirmations. This is going to be the new Syensqo standard for all production operators who need to book their time tickets and the goods movements directly in S4/HANA, either because they do not have an MES system or their MES is not integraed yet.
- Subsitute the current IPA custom development in Composite with a new Dashboard that provide the same functionalities with a better user experience and a modernized technology
- Provide a Validation/Confirmation Tools for the plants and production lines served by the MES integration, to allow the supervisors to check, edit, validate the proposals from MES interface.
Background & Context
Assumptions
Constraints
Impacts
Business Rules
Options considered
Option A:
Option B:
Option C:
Option D:
Evaluation
Option A | Option B | Option C | Option D | |
|---|---|---|---|---|
| Criterion 1 |
|
|
|
|
| Criterion 2 |
|
|
| |
| Criterion 3 |