You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 8 Next »

Status

  Approved

OwnerAntonio Zappone 
Stakeholders

Issue

Decision is required as the when to deploy the new S4\HANA In-House-Bank.


Recommendation


Background & Context

In-House Bank

The existing IHB within ECC resides in PI1, within the legal entities SSA and SFA.  SSA and SFA entities also reside in PF1 for all non IHB processes.  Interfaces are current in place to link PF1 and WP1 to the IHB in PI1. 

All entities are mandated to participate in the IHB process, except where it's not legally possible.  For example, China, x ,x ,x , is not part of the IHB due to legal restrictions.


Internal Factoring

A high level of complexity exists with IHB largely due to the internal factoring process. Internal factoring brings benefits in the way of; 

  • Tax cash advantage of ~3 m€ per year for Syensqo
  • Native centralisation of the cash flows onto Syensqo SA and SFA without the need to pool further
  • Centralisation of the FX exposures that enable centralised and efficient hedging over the largest exposures possible
  • Centralisation of the collection and credit risk allowing to streamline the CCT activities (Note: should be shared with CCT)
  • Centralisation of the vendor payments allowing the streamline the A/P and Payroll activities (Note: should be shared with A/P and HR-Payroll)

Internal factoring is not a common process and not supported by standard SAP, hence the current solution requires nemerous complex custom developements.  To "to-be" design will aim to streamline and simplify, hwever it is epected that some level of custom developments will still be required. 


Risk

Cash movements related to payments and receipts is a higher risk area of any ERP implementation. The internal factoring complexity increases the risk. 

Risk is a major consideration in the recommendation and decision of this KDD.


Assumptions

IHB and internal factoring will continue in S4HANA.

Entities not operating within the IHB will go-live with Bank Communication Managament (BCM) in line with Overall project release\s.


Constraints

Nil 


Impacts

Depending on the approach,  interfaces from S4HANA to PI1 require consideration. If they are required, the existing interfaces from PF1 \ WP1 will need to be replicated for S4HANA.

The new Consolidations tool will go-live in the last release.  This requires considerations for the Consolidation of the entities and processes within PI1.


Business Rules

Participation in the IHB will continue to be mandatory unless not legally supported.


Options considered

Early deployment (prior to the main S4HANA releases) of IHB was considered, however due to the impact of extending the overall ERP project timeline, and earlier transfer of master data, this option was not review in this KDD.  

Option A: (Overall Deployment = "Phased" OR "All-in-one"Defer the deployment of IHB until after all GBUs/entities are live. 


Option B: (Overall ERP Deployment = "Phased") Deploy IHB for live GBUs/entities in-line with the Phased Releases.

This option entails running two IHBs.  One IHB in PI1 for entites still on ECC,  and a second IHB for GBUs\entities that have S4HANA for transitioned to S4HANA.

This allow


Option C: (Overall ERP Deployment = "Phased") Deploy IHB for live GBUs/entities in the second Release with the Phased Releases.


Option D: 

(Overall ERP Deployment = "All-in one") Deploy IHB for live GBUs/entities in line with th all-in-one go-live.


Evaluation



Option A

Option B
Option C
Option D
Option A
Option B
Option C
Option D
Lowest Risk

(plus) PI1 will be available to as a contigency should there be significants issues with the S4HANA IHB. 


(minus) PI1 will not be a possible fall back.   

(plus) Phased transitioned entails less entities go-live in first phase is a lower risk. if there is a significant issue, it will only impact the entities which have transitioned to S4HANA. 

(plus) PI1 will be available to as a contigency should there be significants issues with the S4HANA IHB.  (only for Release 1 entities)

(minus) PI1 will not be a possible fall back.

High

Medium

Medium

Low

Less Complexity - Less Interfaces

(minus) Requires interfaces to be built for integration of PI1 with S4HANA. Interfaces are required for all GBUs\Enttites.

(plus) New interfaces are not required for PI1 to S4HANA


(minus) New interfaces are required for integration of PI1 with S4HANA., for  GBUs\Entities transitioning in Release 1. 

(plus) New interfaces are not required for PI1 to S4HANA


Low

High

Medium

High

Less Complexity - One IHB Operating is less complex than two IHB in operation 

(plus) One IHB Operating

(minus) Two IHBs Operating

(plus) One IHB Operating

(plus) One IHB Operating

High

Low

High

High

Cost

(minus) With the go-live of IHB deferred, relevant resources will be required for an extended period.

(plus) No additional project costs.(plus) No additional project costs.(plus) No additional project costs.LowHighHighHigh
Ability to run Productions Simulations(plus) Production simulation possible, for all entities, which contributes to lowering the risk.(minus) Unable to excute production simulations prior to go-live.(plus) Production simulation possible, for Release 1 entities,  which contributes to lowering the risk.(minus) Unable to excute production simulations prior to go-live.HighLowHighLow
Ease of Consolidation(minus) Consolidation of the entities on PI1 will require an interim solution, for new Consolidations Tool(minus) Consolidation of the entities on PI1 will require an interim solution. Utilise existing approach into BFC Consolidation Tool.(minus) Consolidation of the entities on PI1 will require an interim solution, or new Consolidations Tool(plus) No impact on consolidation.  LowMediumLowHigh
Cut-over impact (less payments outages).(plus) One payment outage as only one cut-over is required.(minus) Two payment outages to manage.(plus) One payment outage as only one cut-over is required.(plus) One payment outage as only one cut-over is required.HighLowHighHigh
Business resource impact(plus) No additional\adverse impact on business resources

(minus) Additional resourcs likely required to run two IHBs. 

(minus) Business resources will likely need to perform manual clearing payment sub-ledgers.

(plus) No additional\adverse impact on business resources(plus) No additional\adverse impact on business resourcesHighLowHighHigh
Stabilisation on integrated process (Sales\Accounts Receivable, Payments\Accounts Payables)(plus) Integrated processes will have had time to stabilise.

(minus) No additional time for integrated process to stabilise, and higher probability of integration issues.

(plus) Integrated processes will have had time to stabilise, (for GBUs\Entities from Release 1).(minus) No additional time for integrated process to stabilise, and higher probability of integration issues.HighLowHighLow

See also


No files shared here yet.

Change log

Version Published Changed By Comment
CURRENT (v. 8) Nov 14, 2024 08:01 ZAPONNE-ext, Antonio
v. 81 Nov 14, 2024 05:58 ZAPONNE-ext, Antonio
v. 80 Nov 14, 2024 03:47 ZAPONNE-ext, Antonio
v. 79 Nov 14, 2024 03:23 ZAPONNE-ext, Antonio
v. 78 Nov 13, 2024 16:33 ZAPONNE-ext, Antonio
v. 77 Nov 13, 2024 16:32 ZAPONNE-ext, Antonio
v. 76 Nov 13, 2024 09:12 ZAPONNE-ext, Antonio
v. 75 Nov 07, 2024 16:25 WENNINGER-ext, Sascha
v. 74 Nov 07, 2024 16:23 WENNINGER-ext, Sascha
v. 73 Nov 06, 2024 15:43 ZAPONNE-ext, Antonio

Go to Page History

Workflow history

Title Last Updated By Updated Status  
There are no pages at the moment.

  • No labels