> In order to calculate P&I 'Production LT' we take as default the 'Processing time' from Work scheduling view (SAP Material Master). If this value is empty, we take the 'Inhouse production time'.
P&I Lead Times | Level Required | Proposed SAP Field | Purpose in SAP | SAP Level | Comment |
Production LT | Material / Plant | Work scheduling view : Processing time (MARC-BEARZ) + Base quantity (MARC-BASMG)or if not filled-inMRP view or Work scheduling view : Inhouse production time (MARC-DZEIT) | Use by the MRP -> Scheduling activities | Material / PlantWorkdays | |
GR Processing LT | Material / Plant | GR processing time (MARC-WEBAZ) | Number of workdays required after receiving the material for inspection and placement into storage. | Material / PlantWorkdays |
To see the full list of LT extracted from SAP, please refer to: Leadtimes coming from SAP
Monolevel RLT Calculation
To calculate the total 'Monolevel' lead time of Produced Materials, we add the Good Receipt Processing time ("GR processing time" of SAP MM > MRP2 view).
Monolevel RLT Purchased Materials = Production LT + GR Processing LT
The best way to get IT support is to use the new
Service One Platform.


