| Status | In Progress |
|---|---|
| Owner | |
| Stakeholders |
Purpose
The purpose of this document is to define the conversion approach to create Operative Project Definition in S/4 HANA.
In SAP PS, the project definition acts as a framework that provides a binding structure for organizational element of a project, such as Work Breakdown Structures. It serves as the top-level element for creating a project, defining default values for company code, plant, and responsible persons, and is essential for structuring, planning, and controlling all aspects of a project, from initiation to closure.
Conversion Scope
The scope of this document covers the approach for converting active Project Definition from Legacy Source Systems into S/4HANA following the Master Data Design Standard- Project Definition.
As per SyWay design, there are two ways to create an Operative Project definition based on the scenarios,
Scenario 1: PS Project definition with WBS element hierarchy (Level 1 & 2) can be automatically created from the approved PPM item once stage-gate 1 is approved. This process involves mapping the PPM item type to a predefined PS template project (created as per CVN-1019 Template Projects) with the Decision Flow Management settings in the SAP system.
A project definition is automatically created for the specified PPM item types, using the corresponding project profile and applicable project coding mask. The conversion approach is dealt with in CNV-1022 Portfolio Item.
| PPM Item Type | PS Project Profile | PRJID | PS Coding Mask | Description |
| Z001 Industrial Project with Qualification | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z002 Industrial Project | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z003 Industrial Project - Simple ? | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z004 New Product Introduction | ZPS0001 - CAPITAL/ Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
| Z005 Product & Process Improvement | ZPS0001 - CAPITAL/ Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
| Z006 Customer and business support | ZPS0001 - CAPITAL/ Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
| Z007 OPD Opportunity Development | ZPS0002 - Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
| Z008 IT Full Lifecycle Project | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z009 IT Small Project | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z010 Opex Project | ZPS0002 - Operational Expense | E | ||
| Z011 Turnaround Projects | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z012 Direct Asset Purchase | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z013 Capitalised Maintenance | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z014 Capital Lease | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z017-New Application Development | ZPS0001 - CAPITAL/ Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
All project definition (new project profile ZPS0001, ZPS0002) relevant to PPM item type linking will be created from PPM items and is excluded from this conversion scope.
Scenario 2: A project definition created manually independent of the PPM item, with the data being sourced using a DCT (Data Collection Template).
These projects are:
- Statistical Expense Projects: Used for tracking non-capital costs. These are statistical project without Budget, created by GBS and no PPM item is required.
- Intercompany Recharges: Used for Inter company service recharge cost allocations. These are operational projects have billing WBS element without Budget, created by GBS and no PPM item is required.
- Provisional Expense: Used for expense provision. These are operational projects without Budget, created by GBS and no PPM item is required.
Conversion scope includes all projects that belong to Scenario 2.
The conversion will ensure all projects are aligned to the defined project coding mask and relevant Organizational Units as designed for the target S/4HANA landscape.
Below project profiles are configured to allow the creation of a project definition directly in the Project System, without requiring integration with a Portfolio and Project Management (PPM) item.
| PS Project Profile | PRJID | PS Coding Mask | PS Coding Mask Description |
ZPS0003 - Statistical Expense | F | -000000-00-00-XX-XX-XX | Statistical/ Recharge & Provision Projects |
ZPS0004 - Intercompany Recharges | F | -000000-00-00-XX-XX-XX | Statistical/ Recharge & Provision Projects |
ZPS0005 - Provisional Expense | F | -000000-00-00-XX-XX-XX | Statistical/ Recharge & Provision Projects |
Scope include:
- Extracting existing active Project Definition from SAP ECC systems WP2 and PF2.
- Extracting existing active Internal order having status Created / Release from SAP ECC systems WP2 and PF2.
- Applying transformation and cleansing logic via Syniti to conform with the S/4HANA data model.
- Loading the transformed Project definition into SAP S/4HANA while ensuring data integrity, correct assignment to project profile as per the project scenarios.
The data from legacy system includes:
All the projects below will be migrated from legacy source systems (PF2 and WP2) into S/4HANA (Within agreed timeframe)
- Open Projects WBS from in scope company codes.
Proj elements not in closed status
Table PROJ
Key in field "Company Code" in scope.
Field project profile not in excluded project profile.
Result: Object numbers of WBS that are in company codes in scope.
Table JEST:
Field "Object number" = Key in the object numbers of WBS (from Step A), Field "Status Inactive" = blank, Then filter object number that do not have status I0046 (Closed)
2. Closed Project from in scope company codes with postings in migration relevant financial year (Within agreed timeframe). The postings technically does not occur directly against the project definition but against objects within the project therefore, postings against a WBS element is used as a proxy for determination of postings against the project.
Closed Project that have WBS element with cost in current year (Within agreed timeframe) must also be migrated.
Logic:
Table PROJ, Field "Company Code" in scope.
Field project profile in scope project profile.
Result: Object numbers of WBS that are in company codes in scope.
Table JEST, Field "Object number" = Key in the object numbers of Project
Field "Status Inactive" = blank, Then filter object number that has status I0046 (Closed).
Result closed projects.
Table PRPS
Field PSPHI For closed projects numbers, Result WBS numbers for
Table RPSCO / COSP: Field "Object number" = Key in the object numbers of WBS
Field "Fiscal Year" = Current year, Field "Value Type" = 4
Result = Object numbers that have cost in current year.
These WBS needs to be migrated.
In addition to the migration of existing Project definitions from ECC there are also some internal orders in ECC which will be migrated to WBS elements in S4 Hana. As the project definition is a requirement for the creation of WBS elements, project definitions which does not exist in ECC will be required, these Project definitions will be defined in a DCT..
The data from legacy system excludes:
- Project not in scope company code.
- Project not in scope plant.
- Project marked as closed / deletion flag set.
Also exclude, project with project profile is ZPS0001 or ZPS0002 linked to PPM item type.
List of source systems and approximate number of records
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
| WP2 / PF2 | Relevant Open PS Projects | S/4HANA | ||
| WP2 / PF2 | Relevant Open Internal Orders (Provisional, Recharge) | S/4HANA | ||
| DCT | S/4 Hana |
Additional Information
Multi-language Requirement
Project definition, the following four language keys must be maintained
- English (EN)
- French (FR)
- Italian (IT)
- Chinese (ZN)
Document Management
Not Applicable
Legal Requirement
Not Applicable
Special Requirements
Not Applicable
Target Design
The technical design of the target for this conversion approach.
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PROJ | PSPID | PS_PSPID | Project definition | CHAR | 24 | Mandatory |
| PROJ | POST1 | PS_POST1 | Description | CHAR | 40 | Mandatory |
| PROJ | STSPR | PS_STSPR | WBS status profile | CHAR | 8 | System Generated |
| PROJ | VERNR | PS_VERNR | No. of Person Resp. | NUM | 8 | Mandatory |
| PROJ | ASTNR | PS_ASTNR | Applicant no. | CHAR | 25 | Mandatory |
| PROJ | VBUKR | PS_VBUKR | Company code | CHAR | 4 | Mandatory |
| PROJ | VKOKR | PS_VKOKR | Controlling area | CHAR | 4 | System Generated |
PROJ | PRCTR | PRCTR | Profit Center | CHAR | 10 | Mandatory |
| PROJ | PWHIE | PS_PWHIE | Project Currency | CHAR | 5 | System Generated |
| PROJ | PLFAZ | PS_PLFAZ_CHG | Start date | DATS | 8 | Mandatory |
| PROJ | PLSEZ | PS_PLSEZ_CHG | Finish date | DATS | 8 | Conditional |
| PROJ | WERKS | WERKS_D | Plant | CHAR | 4 | Conditional |
PROJ | KALID | FABKL | Factory Calendar | CHAR | 2 | System Generated |
| PROJ | PROFL | PROFIDPROJ | Project Profile | CHAR | 7 | Mandatory |
| PROJ | BPROF | BP_BPROFIL | Budget Profile | CHAR | 6 | System Generated |
| PROJ | BESTA | PS_BESTAND | Project stock | CHAR | 1 | System Generated |
| PROJ- | XSTAT | PS_XSTAT | Statistical | CHAR | 1 | Conditional |
| PROJ | PPROF | BP_PPROFIL | Planning Profile | CHAR | 6 | System generated |
| PROJ | PLINT | PLINT | Integrated Planning | CHAR | 1 | System generated |
| PROJ | FUNC_AREA | FKBER | Functional Area | CHAR | 16 | Mandatory |
| PROJ | USR00 | USRCHAR20 | Legacy Project ID | CHAR | 20 | Conditional |
| PROJ | USR02 | USRCHAR10 | Item Type | CHAR | 10 | Conditional |
Data Cleansing
| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
1 | C1 | Projects marked as Closed /deletion - | Not to migrate | Report | WP2/PF2 |
2 | C2 | Projects without postings in FY -3 to be closed - | Not to migrate | Report | WP2/PF2 |
3 | C3 | Internal orders marked as Closed / deletion - | Not to migrate | Report | WP2/PF2 |
4 | C4 | All active internal orders to be closed and map to Project | Map internal order to WBS as per below mapping relevancy | Report | WP2/PF2 |
Mapping relevancy for active internal order to Projects. Look for settlement rule assigned to the internal order in ECC WP2/PF2.
| Internal Order Settlement | Map to Project Definition | |
|---|---|---|
| 1. | Internal order Settlement to CTR list of internal order from AUFK, order category = 01 - Internal order, with status = CRTD, REL (exclude status = CLSD), get OBJNR. OBJNR from AUFK, pass in COBRB, check for account assignment cat = CTR | Project code 'F-' with project profile as ZPS0003 - Statistical Expense |
| 2 | Internal order Settlement to WBS list of internal order from AUFK, order category = 01 - Internal order, with status = CRTD, REL (exclude status = CLSD), get OBJNR. OBJNR from AUFK, pass in COBRB, check for account assignment cat = WBS, check WBS in PRPS = billing element = x | Project code 'F-' with project profile as ZPS0004 - Recharge Projects |
| 3 | Internal order Settlement to order list of internal order from AUFK, order category = 01 - Internal order, with status = CRTD, REL (exclude status = CLSD), get OBJNR. OBJNR from AUFK, pass in COBRB, check for account assignment cat = ORD Check if final settlement for receiver order is GL, If settlement to GL, get GL account and check in table SKA1 for which balance sheet account check = X | Project code 'F-' with project profile as ZPS0005 Provisional Projects |
| 4 | Internal order Settlement to GL list of internal order from AUFK, order category = 01 - Internal order, with status = CRTD, REL (exclude status = CLSD), get OBJNR. OBJNR from AUFK, pass in COBRB, check for account assignment cat = GL, fetch GL account and check in table SKA1 for balance sheet account check = X | Project code 'F-' with project profile as ZPS0005 Provisional Projects |
Conversion Process
The high-level process is represented by the diagram below:
Data Privacy and Sensitivity
Not ApplicableExtraction
Extract data from a source into Syniti Migrate.
. There are 2 possibilities:
- The data exists. Syniti Migrate connects to the source and loads the data into Syniti Migrate. There are 3 methods:
- Perform full data extraction from relevant tables in the source system(s).
- Perform extraction through the application layer.
- Only if Syniti Migrate; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
- The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
Extraction Run Sheet
| Req # | Requirement Description | Team Responsible |
|---|---|---|
1 | Confirm scope and extraction approach for each ECC source systems WP2, PF2 (direct DB or manual extract) | Data Team (I2M), Data Team (Syniti) |
2 | Establish and validate Syniti connectivity to both ECC source systems | Technical / Basis Team, Data Team (Syniti) |
3 | Perform full data extraction from relevant SAP PROJ / AUFK (internal orders) /COBRB from both source systems WP2, PF2 | Data Team (Syniti) |
4 | Google Sheet report pre-populated with PF2 and WP2 information to be generated based on relevancy criteria | Data Team (I2M), Data Team (Syniti) |
5 | Perform data quality checks on extracted records (e.g., missing fields, invalid dates, incorrect formats) | Data Team (I2M), Data Team (Syniti) |
6 | Review and approve extracted data sample sets from each source system before transformation begins | Business / Functional Team |
Selection Screen
Not Applicable| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
| Not applicable |
Data Collection Template (DCT)
Target Ready Data Collection Template will be created for Project Definitions data with exception of some fields which require transformation as mentioned in the transformation rule.
Delta Data Management: Initial collection will be done via the report and one-time load to the DCT will be performed. Any delta after the initial collection within the DCT will require business to take due diligence to ensure any subsequent delta cleansing is verified and aligned within the DCT.
Note: All rules specified below should be documented as a tooltip in the DC Page
DCT applicable to project created manually, with project profile, PROJ-PROFL
- Expense Cost Collector - Statistical Project Project Profile ZPS0003
- Recharge Cost Collectors - Expense Project - Project profile ZPS0004
- Provision Cost collectors - Expense Projects - Project Profile ZPS0005
| Field Name | Field Description | Rule |
|---|---|---|
| PSPID | Project definition | Unique Identifier for the project definition via coding mask starting with "F-000000". It is a Required Field.
Rule 1 Target Ready Data Collection Template will be created for Project (ESG) which represent project per GBU/Cocd/ Plant (site specific) with project type: Rule 2: Mapping with Internal orders to project: Other expenses, for active internal order exist as per the mapping relevancy, target ready Data Collection Template will be created for Project which represent project per Company code/ Plant (site specific). No migration, to be created as needed 2. Recharge Cost Collectors - Expense Project - Project profile ZPS0004 As per the mapping relevancy, target ready Data Collection Template will be created for Project which represent project per Company code, project type for WBS as 15 - Intercompany Recharge 3. Provision Cost collectors - Expense Projects - Project Profile ZPS0005 As per the mapping relevancy, target ready Data Collection Template will be created for Project which represent project per Company code project type for WBS as 13 Safety and Environment Provision |
| POST1 | Description | Short description, Name of the Project It is a Required Field |
| STSPR | WBS status profile | Profile used to Control User Statuses. Automatically Inherited from the Project Profile. Change not allowed. |
| VERNR | No. of Person Resp. | Project Owner Position number Refer configuration table field TCJ04-PS_VERNR for data validation. |
| ASTNR | Applicant no. | This field represent the position of the Project Financial Controller. Refer configuration table field TCJ05-ASTNR for data validation. Project Financial Controller Position entered manually for project created manually, with project profile, PROJ-PROFL |
| VBUKR | Company code | Represents legal entity . Refer configuration table field T001-BURKS for data validation. Company code is entered manually for project created manually, with project profile, PROJ-PROFL |
| VKOKR | Controlling area | Controlling Area is a self-contained organizational unit used for internal cost accounting, Default from Project Profile and Cannot be changed |
| PRCTR | Profit Center | Profit Center represent a plant or a site or generic for GBU. Refer master data table field CEPC-PRCTR for allowed values. |
| PWHIE | Project Currency | Currency of the Project derived from the Company code and cannot be changed |
| PLFAZ | Start date | Planned Start date of the Project. Entered Manually, it is a required field |
| PLSEZ | Finish date | Planned finish date of the Project, Conditional entered manually. |
| WERKS | Plant | Plant represent a site of Project. Entered manually. |
| KALID | Factory Calendar | Derived from the Plant. Refer configuration table field TFACD-IDENT for allowed values. |
| PROFL | Project Profile | The profiles contain default values and control parameters for processing objects and functions in the Project System. Allowed Project Profiles for creation of Project definition: Entered Manually, it is a required field. |
| BPROF | Budget Profile | The budget profile brings together the control parameters for budgeting Such as Time horizon, Currency Translation, availability control. This will be inherited from the Project profile. |
| BESTA | Project stock | This field determines the behavior of the stock for Project. The Field will be automatically determined from Project Profile. Once set it cannot be changed. No Project Stock will be used |
| XSTAT | Statistical | Indicator to specify whether a WBS element is only for statistical purposes or whether it may carry actual costs. Mandatory for Statistical Projects with Project profile PROJ-PROFL= ZPS0003 Such projects are created as needed. |
| PROFL | Planning Profile | Profile which control parameters for cost planning. This is derived from Project profile |
| PLINT | Integrated Planning | This indicator specifies whether an order/project participates in integrated planning or not. Derived from project profile. |
| FUNC_AREA | Functional Area | Functional Area will be maintained manually Refer configuration table field TFKB-FKBER for allowed values." |
| USR00 | Legacy Project ID | Legacy system Project ID, updated for migrated Projects Otherwise must be blank |
| USR02 | Item Type | It remains blank when the PS project is created manually for Project Profiles ZPS0003, ZPS0004 & ZPS0005 PROJ-USR02 = Blank. |
Extraction Dependencies
| Item # | Step Description | Team Responsible |
|---|---|---|
Not Applicable | Data Team |
Transformation
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow to make the data Target ready:
- Perform value mapping and data transformation rules.
- Legacy values are mapped to the to-be values (this could include a default value)
- Values are transformed according to the rules defined.
- Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation
Transformation Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Obtain DCT Sign-off from Business | Data Team |
2 | Execute and Load and perform Transformation | Data Team |
3 | Monitor the transformation progress and ensure performance and completion is within allowed timeframe | Data Team |
4 | Review and Validate Error and Preload Reports | Data Team |
5 | Generate data load count. | Data Team |
6 | Generate Load Files | Data Team |
7 | Log errors as defects, if any and address resolutions. Close defects. | Data Team |
| 8 | Re-transform and re-validate the Pre-load reports if necessary. | Data Team |
| 9 | Validate the transformed file as part of pre-load validation, raise data defects or provide the pre-load sign-off. | Business |
| 10 | Analyze and resolve any pre-load defects logged by business. | Data Team |
| 11 | Repeat steps 7 to 10 if necessary | Data Team |
| 12 | Proceed to pre-load validations | Data Team |
Transformation Rules
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| PF2 / WP2 | PROJ | PSPID | Project definition | S/4 | PROJ | PSPID | Project definition | Mapping from source For Project profile, PROJ-PRFL = ZPS0003 Statistical Expense | |
| PF2 / WP2 | AUFK | AUFNR | Internal Order | S/4 | PROJ | PSPID | Project definition | Mapping from source (Internal order) to Project as per mapping relevancy For Project profile, PROJ-PRFL = ZPS0005 Provisional Projects, map internal order to Project. Check Internal order Settlement rule to GL: Get list of internal order from AUFK, order category = 01, with status = CRTD, REL (exclude status = CLSD), get OBJNR. OBJNR from AUFK, pass in COBRB, check for account assignment cat = GL, fetch list of GL account and check in table SKA1 for which balance sheet account check = X. All such orders are relevant for mapping with S/4 Project, project ID F- Check Internal order Settlement rule to G Get list of internal order from AUFK, order category = 01, with status = CRTD, REL (exclude status = CLSD), get OBJNR. OBJNR from AUFK, pass in COBRB, check for account assignment cat = ORD. All such orders are relevant for mapping with S/4 Project, project ID F- | |
| PF2 / WP2 | PROJ | PSPID | Project definition | S/4 | PROJ | USR00 | Legacy Project ID | Mapping from source | |
| DCT | POST1 | Description | S/4 | PROJ | POST1 | Description | Copy from source | ||
| DCT | S/4 | PROJ | STSPR | WBS status profile | Inherit from Project Profile | ||||
| DCT | VERNR | No. of Person Resp. | S/4 | PROJ | VERNR | No. of Person Resp. | Copy from source | ||
| DCT | ASTNR | Applicant no. | S/4 | PROJ | ASTNR | Applicant no. | Copy from source | ||
| DCT | VBUKR | Company code | S/4 | PROJ | VBUKR | Company code | Mapping from source: Company Code Old to new | ||
| DCT | S/4 | PROJ | VKOKR | Controlling area | Default from project profile | ||||
| DCT | PRCTR | Profit Center | S/4 | PROJ | PRCTR | Profit Center | Mapping from source: Profit Center Old to new | ||
| DCT | S/4 | PROJ | PWHIE | Project Currency | Mapping from Company Code | ||||
| DCT | PLFAZ | Start date | S/4 | PROJ | PLFAZ | Start date | Copy from source | ||
| DCT | PLSEZ | Finish date | S/4 | PROJ | PLSEZ | Finish date | Copy from source | ||
| DCT | WERKS | Plant | S/4 | PROJ | WERKS | Plant | Mapping from Source: Plant Old to new | ||
| DCT | S/4 | PROJ | KALID | Factory Calendar | Mapping from Plant | ||||
| DCT | PROFL | Project Profile | S/4 | PROJ | PROFL | Project Profile | Copy from source | ||
| DCT | S/4 | PROJ | BPROF | Budget Profile | Inherit from Project Profile | ||||
| DCT | S/4 | PROJ | BESTA | Project stock | Inherit from Project Profile | ||||
| DCT | S/4 | PROJ- | XSTAT | Statistical | Inherit from Project Profile Mandatory for Statistical Projects with Project profile, PROJ-PROFL= ZPS0003 | ||||
| DCT | S/4 | PROJ | PPROF | Planning Profile | Inherit from Project Profile | ||||
| DCT | PLINT | Integrated Planning | S/4 | PROJ | PLINT | Integrated Planning | Copy from source | ||
| DCT | FUNC_AREA | Functional Area | S/4 | PROJ | FUNC_AREA | Functional Area | Copy from source | ||
| DCT | USR02 | Item Type | S/4 | PROJ | USR02 | Legacy Project ID | Blank |
Transformation Mapping
| Mapping Table Name | Mapping Table Description |
|---|---|
| Company Code | Value Mapping: Old to New Company Code |
| T001 | Value Mapping: Currency From Company Code |
| Plant | Value Mapping: Old Plant to New |
| Profit Center | Value Mapping: Profit Center Old to New |
| Internal Order | Value Mapping: internal order to Project |
Transformation Dependencies
List the steps that need to occur before transformation can commence| Item # | Step Description | Team Responsible |
|---|---|---|
| Ensure all the fields and values are imported into ADM Construction page correctly | Data Team |
Pre-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
| Generation of Pre-load report | Check all the required fields |
Verify Record Count | SyWay I2M Data Team to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets. |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | SyWay I2M Data Team to verify that all fields below meet pass the checks:
|
Review Error Reports | Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source (DCT) data. |
Business
Completeness
| Task | Action |
|---|---|
Verify Record Count | Business Data Owner/s to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets. |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules (and signed-off DCT data). |
Load
The load process includes:
- Execute the automated data load into target system using load tool or product the load file if the load must be done manually
- Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation
Load Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Load using transaction CNMASSCREATE or Migration cockpit | Data Team |
2 | Load 3 records for < > to validate if data is loaded successfully without errors | Data Team |
3 | Load 3 records for < > to validate if data is loaded successfully without errors | Data Team |
4 | Proceed with full load if steps 2 and 3 are validated | Data Team |
5 | Validate few records loaded by accessing CN41N report | Data Team |
6 | Generate post load report if step 5 is validated | Data Team |
Load Phase and Dependencies
Configuration
| Item # | Configuration Item |
|---|---|
| 1 | Controlling Area |
| 2 | Company Code |
| 3 | Factory Calendar |
| 4 | Currency Code |
| 5 | Project Profile |
| 6 | Budget Profile |
| 7 | Planning Profile |
| 8 | Functional Area |
| 9 | Profile for WBS scheduling |
Conversion Objects
| Object # | Preceding Object Conversion Approach |
|---|---|
| list the exact title of the conversion object of only the immediate predecessor – this will then confirm the DDD (Data Dependency Diagram) |
Error Handling
| Error Type | Error Description | Action Taken |
|---|---|---|
| Project Definition already exist | Correct upload data |
Post-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
Verify Count | SyWay I2M Data Team to verify the record count created in target S/4 HANA by accessing post load reports or standard reports from S/4 HANA. |
Verify Logs | Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.). |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Verify that the Project Definition in target S/4 HANA were loaded correctly via Project Builder display and table PROJ |
Business
Completeness
| Task | Action |
|---|---|
| Verify template Project data - Project Definition | Extract data from PS report CN41N in S/4 Hana |
Accuracy
| Task | Action |
|---|---|
| Verify template Project data - Project Definition | Extract data from PS report CN41N in S/4 Hana |
Key Assumptions
- Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
- Project Definition is in scope based on data design and any exception requested by business.