| Status | DECIDED |
| Owner | Gautier Todeschini |
| Stakeholders | LEAP Steering Committee; Business Representatives |
Decision: Option 3
Decision made by: Business Steering Committee
Date:
Online Meeting: MS Programme Business SteerCo (organized by R. Clerc)
Issue
Due to the size and complexity of the organization, the migration must be executed in manageable "waves," with each wave containing approximatively 4000 users (no more than 5,000).
A key challenge is ensuring business continuity and minimizing disruption, while also accommodating specific group preferences and technical constraints.
Background & Context
- Wave Structure: The migration is divided into four personal data waves (1-4) and one wave of shared data (5).
- Stakeholder Involvement: The proposal was validated in the Business Steerco on February 17th, with input from business representatives and leadership teams.
- Industrial sites working during weekends: Identified as critical operation, with specific concerns on Composite Materials side - requires dedicated migration batches for sub-populations during cutover weekends, to limit the soft data freeze period.
Wave preparation process
Assumptions
General assumptions:
- March 2026 update: Oil & Gas are out of scope of the migration due to the ongoing carve-out
- Decided in Business Steerco on 17/02/26: no hybrid approach will be considered with sites populated by many different functions: Silex to link with IT, Aubervilliers to link to Novecare & Aroma, Explorer ...
- Decided in Business Steerco on 17/02/26: VIPs will be migrated along with their GBUs, not separately
Migration schedule assumptions:
- To be considered in the beginning of the migration:
- IT (already heavily involved in pilots + typical first wave population & able to support their peers)
- One Composite site of 80 pax as part of the first or second wave? (suggestion from the business representative)
- In the middle:
- Specialty Polymers (filling one full wave because of its size)
- At the end:
- Composite materials (they have the most specificities & critical data)
Constraints
- Approx people per wave = 4000 (not more than 5000)
- Data volume = 3 weeks of pre-staging per wave minimum (i.e. historical data pre-migration)
- First Wave preferably smaller (either in amount of user/data, and/or in complexity)
- Ex: users with special characters in the documents names or email titles typically generate more migration errors
- Shared resources wave:
- Watchpoint on integrated mailboxes that have to be reconfigured during the cutover weekend
- Shared drives renaming will be frozen from beg. of April until their migration mid June
- Specific to Organizations:
- GBS & related functions, especially Financen= not at the end of a month (closing)
- Requirement from GBS LT: Finance, HR & Procurement BSA's should be in the GBS Wave
Impacts
- Mixed use of GWS and M365 across organization ("coexistence").
- Duration: ~4 weeks until shared data is migrated.
- Potential collaboration and communication challenges, mitigated by extensive change management efforts.
- Increased IT support demand.
Options considered
Option 1:
Option 2:
Option 3:
See also
The following section describes relevant documentation:
Description | Repository | ||




