| Status | Revision in progress |
|---|---|
| Owner | FRUTEAU-ext, Sabrina |
| Stakeholders | |
| Jira Request ID | ERP-131 Automated Close of Portfolio Item, Project & WBS |
| Jira Development ID | ERP-106 Automated Close of Portfolio Item, Project & WBS |
High- Level Specification
| Parameter | Value |
|---|---|
| Application System | SAP S/4HANA - CUI instanceSAP S/4HANA - China instance SAP S/4HANA - Rest of World instance |
| Business Process Reference | 10.02.04.01. Manage Project Settlement and Closure |
Functional Overview
Over time, many PPM items and SAP Project System (PS) projects reach completion or become inactive but remain open in the system. This leads to administrative inefficiencies, a cluttered project portfolio, and potential compliance risks. To address these challenges, this enhancement proposes the automation of idle project closure. To address these issues, this enhancement introduces a program supporting 2 scheduled processes to manage idle projects and assets:
1. Projects Closure (Quarterly)
Run on a quarterly basis to identify inactive or idle projects, which have not been set to Closed status. The program will attempt to automatically close these projects if all closure criteria are met. If a project cannot be closed due to outstanding issues (such as open balances or commitments), the system will notify the responsible Financial Controller for further review and action.
2. Pending Closure AuC (Monthly)
Run on a monthly basis to identify any idle Assets under Construction (AuC). The program will generate a consolidated notification listing all such AuCs that require attention and send it to the Asset Manager, enabling timely follow-up and resolution.
Scope and Objectives
This enhancement specifically targets SAP Project System (PS) projects that meet the following both criteria:
- Project status is either "Technically Completed" (TECO) or "Cancelled"
- No financial or logistical transactions have occurred for the past six months.
The scope includes:
- Assessment of whether these projects can be fully closed in the system.
- Notification to the responsible Financial Controller if closure is not possible due to outstanding issues (e.g., open balances or commitments).
- Notification for regular review of idle Assets under Construction (AuC) to the Asset Manager.
The objectives are:
- Minimize erroneous postings by preventing transactions on inactive projects
- Optimize reporting by ensuring only active and relevant projects appear as open
- Maintain good data hygiene by keeping project data accurate,
- Highlighting non capitalized costs and POs or WOs left open.
Process Flow Diagram
- Inactive Project Closure Review
(for SAP PS projects with no transactions for 6 months and status TECO or Cancelled)
Step | Description | Comment |
|---|---|---|
| 1 | 3 possible scenarios:
2. User/Responsible person - Project: Changes the PPM item status to Cancelled.
3. User/Responsible person - Project: No PPM item related to the SAP PS project. The User changes the SAP PS project status to TECO or Cancelled. | The program only selects the SAP PS Projects with status = TECO or Cancelled. |
| 2 | Inactivity Period
| X = Inactivity period defined as input parameter. |
| 3 | System (Scheduled Process): On a quarterly basis, scans for SAP PS projects with:
| The program identifies the SAP PS projects in scope. |
| 4 | Closure Attempt The program checks if the eligible projects can be closed.
|
2. Idle Asset Under Construction (AuC) Monitoring
(for periodic review and notification of AuCs with no recent activity)
Step | Description | Comment |
|---|---|---|
| 1 | AuC created and assigns it to a specific WBS element, linking it to a project. Transactions are posted to the AuC as project activities occur. | |
| 2 | Inactivity Period
| X = Inactivity period defined as input parameter. |
| 3 | System (Scheduled Process): On a monthly basis, scans for SAP PS projects with:
| The program identifies the SAP PS projects in scope. |
| 4 | The program compiles a consolidated list of all identified idle AuCs. Sends a monthly consolidated notification to the Asset Manager with details of all idle AuCs requiring attention. | |
| 5 | Asset Manager: Reviews the notification and takes appropriate follow-up actions (e.g., investigates, initiates settlement, etc...).
|
Assumptions
Dependencies
ERP-167 Sync Project Person Responsible & Applicant with HR Positions
ERP-174 Synch Status from PPM Item to PS Project/WBS
Security, Integrity and Controls
Configuration Requirements
Language Requirements
Special Requirements
Design Rationale
Functional Requirements
This section describes the business process and decision logic for managing inactive SAP PS projects and idle Assets under Construction (AuCs). It outlines the key steps and criteria used to identify, review, and act on inactive projects and assets.
Please note that technical implementation details are provided separately in the Processing Logic section.
1. Scheduled Processing
- The program runs in two modes:
- Inactive Project Closure Review: Conducted quarterly to identify and process inactive projects.
- Idle AuC Monitoring: Conducted monthly to identify and report on idle Assets under Construction.
- The period of inactivity (default: six months) can be adjusted as needed (input parameter).
- The program offers a test mode execution, which will issue a report with all the projects that can be closed and the ones that cannot. List the different reasons preventing the closure. See job log details in Handling Error section.
2. Inactive Project Closure Review
2.1. Identification of Inactive SAP PS Projects
- The program identifies projects that are no longer active, marked as “Technically Completed” or “Cancelled.”
- Projects used solely for statistical or intercompany recharge purposes are excluded from this review.
- Only projects and WBS elements with no recorded activity (actuals or commitments) in the past X months are considered inactive and subject to further review. X = Inactivity period.
2.2 Closure Criteria Review:
Attempt to close the WBS elements. Closure is only possible if all of the following conditions are met:
- Outstanding Time Transfer Check: Confirm that all time bookings have been fully transferred to the relevant WBS elements
- No open purchase orders or purchase requisitions
- No open process or work orders
- All linked assets under construction are fully capitalized or settled
- The WBS element has a zero balance
- All stock values are fully settled
Project Closure Action:
- If all conditions are satisfied, the project status is set to closed. If the project is linked to a portfolio management item, its status is also updated to “Close.”
- If any condition is not met, the project remains open and the reasons are documented in a notification to the Financial Controller (see section 4).
3. Idle AuC Monitoring
For each AuC assigned to a WBS element project:
- Identify any AuCs that have not been fully capitalized or settled.
- Identify last activity (posting) date.
- If last activity date > Inactivity period and outstanding balance exist, send a consolidated notification to the Asset Manager (see section 4).
4. Notifications
Inactive Project Closure:
Financial Controllers receive a consolidated notification listing:- Projects that were successfully closed
- Projects that could not be closed, with reasons for each (e.g., open commitments, pending time transfers, unsettled assets)
- Guidance on next steps and the date of the next scheduled review
Idle AuC Monitoring:
Asset Managers receive a notification listing all identified idle AuCs, including relevant details and recommended actions.If a responsible recipient cannot be identified, the issue is logged for further investigation.
- Email recipients are derived based on WBS element and Asset master data, described in processing logic. TBD
Proposed Technology to Use
Data Source Considerations
| Table | Field Name | Comments/Calculation/Field Manipulation |
|---|---|---|
| PROJ | PSPNR, OBJNR, PROFL | Used to select the projects in scope |
| JEST | OBJNR, STAT | Select Projects which are set to status TECO |
| CATSCO | RPROJ, TRANSFERRED | Check if CATS time entries not transferred to WBS element |
| /RPM/ITEM_D | ITEM_D | If SAP PS project id exists in this table, then there is a corresponding PPM item. The PPM item status must be changed to Closed. |
| ACDOCA | ANLN1 | Check if the AuC asset still has a balance |
| ANLA | ANLKL | Check the asset class = AuC. |
| COBRB | OBJNR, COBRB | Identify assets linked to the related WBS element |
Data Validation Considerations
| Table | Field Name | Comments/Calculation/Field Manipulation |
|---|---|---|
Custom Tables
Master Data
| Field | Description | Data Type/Length | Validation rule/ Value Help |
|---|---|---|---|
Configuration Table
| Field | Description | Data Type/Length | Validation rule/ Value Help |
|---|---|---|---|
Selection Screen Enhancement
| Field Name | Description | Select: | Data Type/Length | Default Value/ Validation rule/ Value Help | Selection Logic |
|---|---|---|---|---|---|
Processing Logic
1. Scheduled Processing
The program can be executed in 2 modes:
- Inactive project closure review: The identification and processing of inactive projects must occur quarterly.
- Idle AuC Monitoring: The identification and reporting of idle AuCs must occur monthly.
The Inactivity period (defined as 6 months in this FS) is set as an input parameter.
2. Inactive project closure review
For each identified inactive project, the program:
2.1.Identification of Inactive SAP PS Projects
- The program identify SAP PS projects with:
- status TECO or Cancelled:
- JEST: Object Status (stores status information for objects like projects and WBS) STAT field = I0045 TECO and E0003 CNCL
- PROJ: Project Definition (main project header data)
- Join the 2 tables to keep only project definitions.
- Result: List of project definitions (IDs) that are TECO and CNCL.
- Exclude PS project with Project profile = PROJ-PROFL
- status TECO or Cancelled:
- The program identify SAP PS projects with:
| ZPS0003 | Statistical Expense |
| ZPS0004 | Intercompany Recharges |
- Check that no transactions for the past 6 months: no Actuals nor Commitment posted on all of the related WBS elements.
2.1 Checks if no outstanding time transfer
All time booking is transferred to the WBS element (Time booked and time transfer completed).
Check table CATSCO
RPROJ = WBS element = Project id followed by * to obtain all WBS elements for a given project definition (Example, if the project id = A.000004, then search all RPROJ values starting with A.000004);
TRANSFERRED = " "
If any records with Transferred = " ", then some records are still expected to be transferred. The project cannot be closed.
2.2 Attempt to set the project status to CLSD (Closed). Simulate a SAP PS Project status change to Closed. If not the below closure criteria are met, the system will prevent the closure and issue an error message.
| No Open Commitments - Outstanding purchase orders - Outstanding purchase requisitions |
| No Open R&I Process Orders All process orders assigned to the WBS element are completed and closed in the system. |
| No Open Work Orders All work orders (maintenance, production, or service) assigned to the WBS element are completed and closed in the system. |
No Open AuC |
| Overall balance on WBS element = 0 |
| Good receipt Stock value fully settled |
2.3 If all the above criteria (1 and 2) are met, the project can be closed:
- If the SAP PS project is related to a PPM id, the PPM item status should be set to Closed Z004.
Check project id exist in /RPM/ITEM_D field ITEM_D
Function Module /RPM/ITEM_CHANGE - This function module allows to change attributes of a PPM item, including its status.
The status change to Close on the PPM item will be replicated to the SAP PS project.
- Else set the SAP PS project to status CLSD.
- A consolidated notification is sent to the Financial Controller. See section 4.
2.4 If condition 3.1 and/or 3.2 are not fulfilled, the project will not be closed. A notification is sent.
Notifications detailed in section 5 will be issued.
3. Idle AuC Monitoring
3.1. Identifying AuC Related to WBS
Use fields:
ANLN1 (Asset Number)
ANLN2 (Asset Subnumber)
POSNR (WBS Element)
ANLKL (Asset Class — to filter for AuC)
Filter where ANLKL corresponds to your AuC asset class and POSNR matches your WBS element.
3.2. Checking for the last Activity (identifying dormant AuC)
Use BUDAT (Posting Date) in ACDOCA.
If there are no entries for the asset in the last X months (X= Inactivity period), it meets inactivity criterion.
3.3. Checking Capitalization/Settlement
Analyze postings in ACDOCA for the asset to determine if it’s fully capitalized or settled.
Look at:
Transaction types (field BWASL)
Amounts (fields DMBTR, WRBTR)
Document types (field BLART)
If there are still open balances or no settlement/capitalization postings, the asset is not fully settled.
3.4 If AuCs not fully capitalized, send a notification to Asset Manager. Details in section 4.
4. Notification
4.1. Inactive project closure review:
A consolidated notification for each Financial Controllers highlighting:
- Projects that were automatically closed
- Projects that cannot be closed and the reasons.
Template email:
Subject: Inactive Project Closure Review Results – [Processing Date]
Dear [Financial Controller, see section 5.3 for deriving Financial Controller],
As part of the regular review of inactive projects (status TECO or Cancelled, no activity in the past [Inactivity period] months), please find below the summary of closure attempts performed on [Processing Date].
1- Projects Successfully Closed
The following projects were successfully closed:
Project ID | Project Name/Description |
... | ... |
2- Projects Not Closed
The following projects could not be closed.
Project ID | Project Name/Description | Object (Order IDs, AuC, etc.) | Reason (SAP Error Message) |
... | ... | AuC: 1000000456 | Error when processing asset under construction (AuC) for WBS element A |
... | ... | WBS element id | Balance of WBS A.000046.01.02.02 is not zero |
... | ... | WBS element id | Pending CATS time entry records for transfer.* |
*In this case the notification does not display the SAP error message, as no error is generated. Please use the mentioned reason. This occurs if condition 3.1 is valid.
Please review the reasons and take the necessary actions (e.g., settle balances, close orders, resolve AuC issues) to enable closure in the next review cycle.
Next scheduled review: [Next Review Date]
4.2 Idle AuC Monitoring:
A consolidated notification highlighting all the AuC which have not been
Email template:
Subject: Consolidated List of Idle Assets Under Construction (AuC) – [Processing Date]
Dear [Asset Manager, see section 5.3 for deriving Asset Manager],
As part of the periodic review of inactive AuC, the following Assets have been identified as inactive (no activity in the past [Inactivity period] months) and are not fully capitalized or settled.
Please review the list below and take appropriate action to settle or capitalize these assets as needed.
| AuC Number | AuC Description | Linked WBS Element | Project ID | Outstanding Amount | Capitalization date |
| Identified AuC in section 4. | Taken from table ANLA: input ANLN1 Asset number and retrieve TXT50 | WBS element identified in section 4. | Project ID identified in section 4. | Section 4.3 Table ACDOCA Sum up all company code currency (HSL) postings for that asset | Maintained on the WBS element. Table PRPS field USR08. |
4.3 Deriving email recipients
- Financial controller: Financial controller position is stored in table PRPS, field ASTNR. From the position ID the SAP Personal ID can be derived through table HRP1001. Then obtain the email address through PA0105.
- Asset Manager: TBD
4.4 Handling notification errors (No recipient derived)
If email recipients cannot be identified, no notification is sent, error is shown in the job error log report.
Volumetrics
Unknown.
Performance Considerations
Error Handling
The job log report should:
- Record the execution details of the program, including start and end times and selection criteria (Inactivity period).
- Log the number of objects processed (e.g., number of projects with TECO status found).
- List SAP PS projects successfully closed
- List PPM items successfully closed
- List SAP PS projects not closed and provide reason (error or pending timesheet transfer)
- Capture any errors encountered during execution.
- Provide an overview of the notifications sent (recipient, successful or failed)
Testing
How to Test
Test Conditions and Expected Results
| ID | Condition | Expected Result |
|---|---|---|
| 1 | Prepare test data:
| Projects are created covering the various scenarios. |
| 2 | Execute the program in test mode with Inactivity period = 0. | Report shows all the projects that could be closed and the ones that cannot be closed due to conditions not all fulfilled. |
| 3 | Execute the program (no test mode). | Expected projects are closed. Expected PPM items are closed. Notification is sent with the errors report for non closed projects and closed projects overview. Records of all actions are included in the notification, including:
The job log should be reviewed for audit and troubleshooting. |
Test Considerations/Dependencies
Other Information
Development Details
Package
| Package Name | Parent Package |
|---|---|
Enhancement Implementation
| Enhancement Type | Standard Definition Name | Custom Implementation Name | Design Rationale Reference |
|---|---|---|---|
Other Development Objects
| Object Type | Object Name | Purpose/High Level Logic | Design Rationale Reference |
|---|---|---|---|
Appendix
Custom Authorization Group Naming Convention
This table is based on the Syensqo development standards document. It provides the naming conventions for authorization groups to associated with custom reports and tables to comply with security requirements.
ABAP | ZFI | ZMM | ZPS | ZCO | ZSD | ZBC | ZFI | ZCA |
|---|---|---|---|---|---|---|---|---|
| TABLES | ZFIT | ZMMT | ZPST | ZCOT | ZSDT | ZBCT | ZFIT | ZCAT |