Once a plant starts using the SAP QM Module, the next step is to leverage on the new capability to determine when each new lot will be available (=released from QC).

This also allows SAP (and especially ATP) to prevent a lot to ship while it is in quality inspection.

In addition, it allows SAP (and especially ATP) to determine if a specific lot can ship at a given date, while still being under quality inspection.

In order to achieve this, the Lab reviews their statistics and establishes the expected completion time of a given product (or family of products), which goes into SAP.


Both Picaso and SAP have to be kept in synchronization when accounting for time the Lab needs to complete quality control. We will call this time: Lab Time.  (Lab Time: from receiving sample, to registering results of tests and analysis).

Step-by-step guide

Now, in order to determine the SAP QC Time, SAP Average Inspection Time, SAP Goods Receipt Processing Time, SAP Planned Delivery Time, Picaso QC Lag, and Picaso QC Lag Adjustment, first determine what material flow applies:

  • Scenario A: Lot is received in inventory at the manufacturing plant, then ships from the plant to final customer. All happening from within the production plant.
  • Scenario B: Lot is received in inventory at the manufacturing plant, then is pushed to the warehouse once released from QC. Once it arrives at the warehouse, it can ship to final customers.
  • Scenario C: Lot is received in inventory at the manufacturing plant, then is pushed to the warehouse right away, that is, before QC release. It is received at the warehouse in QC status. It will ship to final customers once released from QC.
  • Scenario D: Same as C, with lots being received in SAP, and QC starting, while campaign still in progress. Even more complex, therefore only if adds value (to be continued)
  • Special scenarios, when there is no external scheduling system:
    • Scenario A-bis (same as A, no external scheduling system)
    • Scenario B-bis (----------B,----------------------------------)
    • Scenario C-bis (----------C,----------------------------------)


Tips: The SAP QC Time, SAP Average Inspection Time, Goods Receipt Processing Time, Planned Delivery time, Picaso QC Lag, and Picaso QC Lag Adjustment apply during specific events of the life of a lot:

Applies before the lot is received in inventory

Applies once the lot has been received in inventory and the QM Lot has been generated

Picaso QC Lag

Picaso Schedule Upload Lag Adjustment

Goods Receipt Processing Time

Planned Delivery Time

Average Inspection Duration

Material flows:

PhaseScenario A

Production run time: 6 days

Lab time = 4 days

Before Goods Receipt from Production in the manufacturing plant

(why the interface created a 10 days planned order in SAP when the original Picaso run is 6 days? Find the answer here)

After Goods Receipt from Production in the manufacturing plant

After QC Release

Master Data:

Picaso: QC Lag = Lab Time (4 days)

SAP (at the plant)

  • Av.Ins.Duration (@plant) = Lab Time (ex. : 4 days)
  • Make sure these are blank (or 0):
    • Planned Delivery Time (@plant)
    • Goods Receipt Processing Time (@plant)
PhaseScenario B

Production run time: 6 days

Lab time = 4 days

Transfer time between manufacturing plant and warehouse = 1 day

Lot moved to the warehouse after QC release

Before Goods Receipt

(why the interface created a 10 days planned order in SAP when the original Picaso run is 6 days? Find the answer here)

After Goods Receipt from Production in the manufacturing plant

After QC Release

After Goods Receipt from Transfer in the warehouse

Master Data:

Picaso:

  • QC Lag = Lab Time + transfer to the warehouse, including handling. (ex. : 11 days)
  • Schedule Upload Lag Adjustment = - transfer time (ex. : -1 days)

SAP (at the plant)

  • Av.Ins.Duration (@plant) = Lab Time (ex. : 4 days)
  • Make sure these are blank (or 0):
    • Planned Delivery Time (@plant)
    • Goods Receipt Processing Time (@plant)

SAP (at the warehouse)

  • Planned Delivery Time (@warehouse)= Transfer time (ex. : 1 days)
  • Make sure these are blank (or 0):
    • Av.Ins.Duration (@warehouse)
    • Goods Receipt Processing Time (@warehouse)
PhaseScenario C

Production run time: 6 days

Lab time = 4 days

Transfer time between manufacturing plant and warehouse = 1 day

Lot moved to the warehouse during QC

Before Goods Receipt from Production

After Goods Receipt from Production in the manufacturing plant

After Goods Receipt from Transfer in the warehouse

After QC Release



Master Data:

Picaso:

  • QC Lag = expected max of Lab Time / transfer to the warehouse, including handling. (ex. : 4 days)
  • Schedule Upload Lag Adjustment = - QC Lag (ex. : -4 days)

SAP (at the plant)

  • Make sure these are blank (or 0):
    • Av.Ins.Duration (@plant)
    • Planned Delivery Time (@plant)
    • Goods Receipt Processing Time (@plant)

SAP (at the warehouse)

  • Planned Delivery Time (@warehouse)= Transfer time (ex. : 1 days)
  • Goods Receipt Processing Time (@warehouse)= Lab Time - Transfer time (ex. : 4 days)
  • Av.Ins.Duration (@warehouse)= Lab Time - Transfer time (ex. : 3 days) = GRPT
PhaseScenario A bis

Production run time: 6 days

Lab time = 4 days

Before Goods Receipt from Production in the manufacturing plant


After Goods Receipt from Production in the manufacturing plant

After QC Release

Master Data:

SAP (at the plant)

  • Av.Ins.Duration (@plant) = Lab Time (ex. : 4 days)
  • Goods Receipt Processing Time (@plant) = Lab Time (ex. : 4 days)
  • Make sure these are blank (or 0):
    • Planned Delivery Time (@plant)
PhaseScenario B bis

Production run time: 6 days

Lab time = 4 days

Transfer time between manufacturing plant and warehouse = 1 day

Lot moved to the warehouse after QC release

Before Goods Receipt


After Goods Receipt from Production in the manufacturing plant

After QC Release

After Goods Receipt from Transfer in the warehouse

Master Data:

SAP (at the plant)

  • Av.Ins.Duration (@plant) = Lab Time (ex. : 4 days)
  • Goods Receipt Processing Time (@plant) = Lab Time (ex. : 4 days)
  • Make sure these are blank (or 0):
    • Planned Delivery Time (@plant)

SAP (at the warehouse)

  • Planned Delivery Time (@warehouse)= Transfer time (ex. : 1 days)
  • Make sure these are blank (or 0):
    • Av.Ins.Duration (@warehouse)
    • Goods Receipt Processing Time (@warehouse)
PhaseScenario C-bis

Production run time: 6 days

Lab time = 4 days

Transfer time between manufacturing plant and warehouse = 1 day

Lot moved to the warehouse during QC

Before Goods Receipt from Production

After Goods Receipt from Production in the manufacturing plant

After Goods Receipt from Transfer in the warehouse

After QC Release



Master Data:

SAP (at the plant)

  • Make sure these are blank (or 0):
    • Av.Ins.Duration (@plant)
    • Planned Delivery Time (@plant)
    • Goods Receipt Processing Time (@plant)

SAP (at the warehouse)

  • Planned Delivery Time (@warehouse)= Transfer time (ex. : 1 days)
  • Goods Receipt Processing Time (@warehouse)= Lab Time - Transfer time (ex. : 4 days)
  • Av.Ins.Duration (@warehouse)= Lab Time - Transfer time (ex. : 3 days) = GRPT


Recap:

ScenarioMaster Data PicasoMaster Data SAP
A

QC Lag = Lab Time

Schedule Upload Lag Adjustment = 0 (or none)

@the plant

Av.Ins.Duration = Lab Time

Planned Delivery Time = 0

Goods Receipt Processing Time = 0

B

QC Lag = Lab Time + transfer to the warehouse, including handling

Schedule Upload Lag Adjustment = - transfer time

@the plant

Av.Ins.Duration = Lab Time

Planned Delivery Time = 0

Goods Receipt Processing Time = 0

@the warehouse

Planned Delivery Time = Transfer time

Av.Ins.Duration = 0

Goods Receipt Processing Time = 0

C

QC Lag = max of (Lab Time // transfer time)

Schedule Upload Lag Adjustment = - QC Lag


@the plant

Av.Ins.Duration = 0

Planned Delivery Time = 0

Goods Receipt Processing Time = 0

@the warehouse

Planned Delivery Time = Transfer time

GRPT = Lab Time - Transfer time

Av.Ins.Duration = Lab Time - Transfer time

A-bisN/A

@the plant

Av.Ins.Duration = Lab Time

Goods Receipt Processing Time = Lab Time

Planned Delivery Time = 0

B-bisN/A

@the plant

Av.Ins.Duration = Lab Time

Goods Receipt Processing Time = Lab Time

Planned Delivery Time = 0

@the warehouse

Planned Delivery Time = Transfer time

Av.Ins.Duration = 0

Goods Receipt Processing Time = 0

C-bisN/A

@the plant

Av.Ins.Duration = 0

Planned Delivery Time = 0

Goods Receipt Processing Time = 0

@the warehouse

Planned Delivery Time = Transfer time

GRPT = Lab Time - Transfer time

Av.Ins.Duration = Lab Time - Transfer time


 Use this  file to help calculate the data en masse.

Maintain the QC Lag and the Schedule Upload Lag Adjustment in their respective tables in ADM.

Maintain 