Sprint Report

Squad A Sprint 1 Report
Date

 

Start

 

End 

 

Sprint  Goal(s)

Finalize design for Wave 2

Change Management activities updated for Wave 2

Update reporting to reflect Wave 2 and HSBC card provider

Hierarchies created on HSBC side

Sprint ReportSprint 14
Completed Story Points 35
 SummaryIn this sprint, the Squad was focused on finalizing the design for Wave 2 (there was also a 2-day in-person workshop in Lisbon to focus on it). 
CommentsThailand & South Korea may not be able to go live in Wave 2 due to issues with payments in US dollars (it is a showstopper for now and will be resolved during the current sprint (sprint 15))


Burndown Chart

Velocity Chart

Issues Status Report