1 OBJECTIVE AND SCOPE


1.1. Objective of this Procedure

This document describes the full procedure related to contract and PIR maintenance in SAP PE1 system. It’s a revised version from previous working instructions (Work Instruction - PUR - SAP - 02)

Requests can be performed by buyers and planners from each plant.

All requests are sent to Data Operations team via FreshDesk.

1.2. Scope

Under Riga SBS Data Operations’ scope is the management of Contracts and PIRs for all plants.

1.3. Abbreviations


Abbr.

Description

SBS

Solvay Business Services

HSE

Health, Safety and Environment

DG

Dangerous goods

MRP

Material Resource Planning

UoM

Units of Measure

PIR

Purchasing Info Record

STO

Stock Transfer Order

1.4. Roles and responsibilities

Prior to submitting a new Contract/PIR request, it is the requester’s responsibility to ensure the contract/PIR does not exist in SAP already, so no duplicates are created in the system. If the contract/PIR was not found, a request should be submitted to Data Operations for its set up in SAP. A second search in the system is performed by the Data Operations team to ensure no duplicates are created.

2 STANDARD OPERATING PROCEDURE DESCRIPTION


Below you can see when we can define what information is needed depending on the Purchase Type.

Purchase type

Contract

PIR

Source List

Standard

✔️


✔️

Stock Transfer

 

✔️

✔️

Consignment

 

✔️ (Consignment) 

✔️

Subcontracting

✔️

✔️ (Subcontracting)

✔️


2.1. Creation of contract in PE1

2.1.1. Prerequisites

Requester should provide:

  • Vendor code
  • Material number
  • Price
  • Unit of Measure (price and order)
  • Target Value
  • Currency
  • Plant


Note! If you have a request with more than one Contract to be created, add the TAG in Freshdesk with the number of Contracts created.

2.1.2. Checking for duplicates


 

#

Main activities

Tips / Best practices

Key points

1

Enter transaction ME33K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


2

Press multiple choice button to receive pop-up window with search options for material master

you can also press F4




#

Main activities

Tips / Best practices

Key points

3

Select Purchasing Documents per vendor

T-code can be entered directly in Command field. T-code can be saved in Favorites.


4

Add vendor


Information provided in the request

5

Purchasing Document Category


Always K

6

Order Type


Always ZDK2

7

Press enter

If no values return, you can proceed with the creation




#

Main activities

Tips / Best practices

Key points

8

Enter on contracts that show up

We have one contract by plant. In case it’s not the plant requested, proceed with contract creation, otherwise add item to the existing contract.


2.1.3. Creating a contract



#

Main activities

Tips / Best practices

Key points

9

Enter transaction ME31K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


10

Vendor 

Note! If the the vendor# provided is related to a Cytec company, go back to the requester to confirm if the vendor requested is out of PE1 scope and should be handled as an external vendor.
Example: Vendor 89405 Cytec Engineered Materials Ltd which belongs to Company code 7771 in WP1

Information provided in the request

11

Agreement type


Always ZDK2

12

Purchasing Organization


Always CP01

13

Purchasing Group


Plant buyer code

14

Plant 


Information provided in the request

15

Press enter





#

Main activities

Tips / Best practices

Key points

16

Validity end

Contracts are created in a 5 years period, last day before final Solstice Migration

Always 31.12.2023

17

Target Value 

If not informed, contact buyer to confirm correct value

Information provided in the request



NOTE: In the header you can also set up some different information other than the one in vendor master data, such as different payment term, incoterms, etc. (this information will be the one selected when PO is created)


18

Press Item Overview





#

Main activities

Tips / Best practices

Key points

19

Item Category 


If informed, otherwise blank

Options:

  • Blank: Standard
  • K: Consignment
  • L: Subcontracting
  • S: Third party
  • T: Text

20

Account Assignment Category 


if material starts with 7 should be populated with U, Otherwise Blank

21

Material 


As informed

22

Order Unit

If not populated, it will get from Material Master


23

Net Price

NOTE: Price can only be added with 2 decimal characters, in case price informed is as example $1.012 USD/EA > net price would be $10.12 and per will be 10

As informed

24

Per


As informed

25

Order Unit Price


As informed

26

Press enter

Once item is added we need to check the texts related to quality or additional information required for the item.



#

Main activities

Tips / Best practices

Key points

27

Select material line



28

Environment > Material 

this way we access the material information



#

Main activities

Tips / Best practices

Key points

29

Click on to open the menu



30

Select the option Quality Management

this way we access the material information



#

Main activities

Tips / Best practices

Key points

31

Check Certificate type information


If Certificate type is “Blank” no text needs to be maintained

If Certificate type is:

E21 the following text should be maintained:

"Goods supplied against this purchase order must be in compliance with the COC"

E31 the following text should be maintained:

"CoA is required with every shipment against this purchase order"

32

Go Back to contract




#

Main activities

Tips / Best practices

Key points

33

Select item line



34

select item texts




#

Main activities

Tips / Best practices

Key points

35

Double click on COA Instruction

if it’s not in the main screen, press Page Down



#

Main activities

Tips / Best practices

Key points

36

Paste the correct text



37

Return

NOTE: Other types of text that can be added as example: Item Additional Information, Material PO Text



#

Main activities

Tips / Best practices

Key points

38

Select item line

Additional information as Vendor Material number can be added


39

select Details




#

Main activities

Tips / Best practices

Key points

40

Vendor Material number


Add information as requested

41

Save it

After the contract  is created, source list should be created



NOTE: After Contract is created, a source list needs to be created and contract should be released.

We have 3 levels of blocks depending on the target value as below:

  • Level 1 (D1 Block) - $0.00 to $250,000 – Buyers (Procurement/Sourcing Associate)

  • Level 2 (D2 Block) - $250,001 to $1,000,000 – Procurement Managers (Procurement/Sourcing Associate & Procurement Manager)

  • Level 3 (D3 Block) - $1,000,001 to unlimited – Procurement Directors and VP of Procurement (Procurement/Sourcing Associate & Global Procurement Director & Global Procurement VP)


List of release responsible is on Appendix 2.

 

To check, what release level a contract requires, use transaction Display Contract (ME33K) or Change Contract (ME32K). Click Release Strategy button  to see, on which levels contract has been released and on which levels it needs to be released to be valid.

 

2.1.4. Adding new item in an existing contract

Note! If you have a request with more than one material to be added/updated in the contract, add the TAG in Freshdesk with the number of materials added/created.


#

Main activities

Tips / Best practices

Key points

42

Go to transaction ME32K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


43

Add contract number



#

Main activities

Tips / Best practices

Key points

44

Material number

Find the first blank line
Follow the same procedure as step 19 to 26

Add information as requested


#

Main activities

Tips / Best practices

Key points

45

Select material line



46

Environment > Material 

this way we access the material information



#

Main activities

Tips / Best practices

Key points

47

Click on to open the menu



48

Select the option Quality Management

this way we access the material information



#

Main activities

Tips / Best practices

Key points

49

Check Certificate type information

If Certificate type is “Blank” no text needs to be maintained

If Certificate type is

E21 the following text should be maintained:

Goods supplied against this purchase order must be in compliance with the COC

E31 the following text should be maintained:

CoA is required with every shipment against this purchase order


50

Go Back to contract




#

Main activities

Tips / Best practices

Key points

51

Select item line



52

select item texts




#

Main activities

Tips / Best practices

Key points

53

Double click on COA Instruction

if it’s not in the main screen, press Page Down



#

Main activities

Tips / Best practices

Key points

54

Paste the correct text



55


NOTE: Other types of text that can be added as example: Item Additional Information, Material PO Text


56

Return





#

Main activities

Tips / Best practices

Key points

57

Select item line

Additional information as Vendor Material number can be added


58

select Details




#

Main activities

Tips / Best practices

Key points

59

Vendor Material number


Add information as requested

60

Save it

After item is added, source list should be created



2.1.5. Changing items in an existing contract

Note! If you have a request with more than one material to be added/updated in the contract, add the TAG in Freshdesk with the number of materials added/created.

#

Main activities

Tips / Best practices

Key points

61

Go to transaction ME32K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


62

Add contract number



63

Press enter




#

Main activities

Tips / Best practices

Key points

64

Select line that needs to be changed

T-code can be entered directly in Command field. T-code can be saved in Favorites.


65

Click on conditions




#

Main activities

Tips / Best practices

Key points

66

Single click on the valid period



67

New with reference




#

Main activities

Tips / Best practices

Key points

68

Amount


Information provided

69

Save it

Note: Additional information can be changed also (texts)



2.1.6. Changing Target value in an existing contract



#

Main activities

Tips / Best practices

Key points

70

Go to transaction ME32K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


71

Add contract number



72

Select Header Details




#

Main activities

Tips / Best practices

Key points

73

Change to Target value to the information provided

After Target value, contract needs to be released again by the responsible party


74

Save it




2.1.7. Deleting item in an existing contract

#

Main activities

Tips / Best practices

Key points

75

Go to transaction ME32K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


76

Add contract number



77

Press enter




#

Main activities

Tips / Best practices

Key points

78

Select Line(s) you want to delete



79

Click on “Delete



80

Save it





#

Main activities

Tips / Best practices

Key points

81

After deleting all lines go to header



82

Change Validity end to the past



83

Save it





2.2. Creation of PIR (Purchase Info Record) in PE1

PIRs are created when we have STO,  consignment PO or a subcontracting contract.

We have 4 types of PIR: 

  • Standard - Specifies that the info record is used only in connection with standard purchase orders. This is the most ordinary PIR type and is the one used for STO.

  • Subcontracting - Specifies that the info record is used only in connection with subcontract orders orders.

  • Pipeline - Specifies that the info record is used specifically for pipeline withdrawals.

  • Consignment - Specifies that the info record is only used in the case of consignment withdrawals.


2.2.1. Requirements for new PIR

In order to create new PIR we will need the following information:

  • Vendor

  • Plant

  • Price

  • Purchasing Organization - Always CP01

Note! If you have a request with more than one PIR to be created, add the TAG in Freshdesk with the number of PIRs created.

2.2.2. Creating PIR

#

Main activities

Tips / Best practices

Key points

84

Enter transaction ME11

T-code can be entered directly in Command field. T-code can be saved in Favorites.


85

Vendor 


Information provided in the request


Material


As informed

86

Purchasing Organization


Always CP01

87

Plant 


Information provided in the request

88

PIR category


If not informed choose Standard

89

Press enter




#

Main activities

Tips / Best practices

Key points

90

Go to Purch. Org data 1

Nothing to be filled here



#

Main activities

Tips / Best practices

Key points

91

Standard quantity


If not informed, use 1

92

Minimum quantity


If not informed, leave it blank

93

Tolerance Underdl/Overdl.


Change only if requested

94

Conf. Control


For external Purchases - Z004

For internal purchases (STO) - leave it blank

95

Price

If external purchase, this field becomes mandatory.

If internal purchase, field doesn’t show up

Fill with the price informed.

96

Save it

Once PIR is created, you need to create a source list



2.2.3. Change PIR

Note! If you have a request with more than one PIR to be updated, add the TAG in Freshdesk with the number of PIRs updated.

#

Main activities

Tips / Best practices

Key points

97

Enter transaction ME12

T-code can be entered directly in Command field. T-code can be saved in Favorites.


98

Vendor 


Information provided in the request

99

Material


As informed

100

Purchasing Organization


Always CP01

101

Plant 


Information provided in the request

102

PIR category


If not informed choose Standard

103

Press enter




#

Main activities

Tips / Best practices

Key points

104

Go to Conditions




#

Main activities

Tips / Best practices

Key points

105

Single click on the valid period



106

New with reference




#

Main activities

Tips / Best practices

Key points

107

Amount


As informed

108

Per


As informed

109

Price Unit of measure


As informed

110

Save it





2.2.4. Delete PIR

#

Main activities

Tips / Best practices

Key points

111

Enter transaction ME12

T-code can be entered directly in Command field. T-code can be saved in Favorites.


112

Vendor 


Information provided in the request

113

Material


As informed

114

Purchasing Organization


Always CP01

115

Plant 


Information provided in the request

116

PIR category


If not informed choose Standard

117

Press enter




#

Main activities

Tips / Best practices

Key points

118

Go to Conditions




#

Main activities

Tips / Best practices

Key points

119

Select Valid period




#

Main activities

Tips / Best practices

Key points

120

Vadid to


Always a date in the past

121

Go Back




#

Main activities

Tips / Best practices

Key points

122

Go to Extras > Deletion flags




#

Main activities

Tips / Best practices

Key points

123

Complete info record

If you need to block all PIR data


124

Purch. Org Data

If you need to block a specific Plant/P.Org data


125

Save it




2.3. Source List

A source list is needed every time a new contract is created, a new line is added in an existing contract or when a PIR is created.

2.3.1. Creating Source List


#

Main activities

Tips / Best practices

Key points

126

Enter transaction ME01

T-code can be entered directly in Command field. T-code can be saved in Favorites.


127

Material


As informed

128

Plant


As informed

129

Press enter





We have 2 options on how to create/update source list

1st option:

#

Main activities

Tips / Best practices

Key points

130

Click on generate records




#

Main activities

Tips / Best practices

Key points

131

Press enter or click on confirm




#

Main activities

Tips / Best practices

Key points

132

Select “Not changed”



133

Press enter or click on confirm





#

Main activities

Tips / Best practices

Key points

134

Select duplicated lines or irrelevant information and delete



135

MRP Relevant 


Always 1

136

Save it





2nd option:


#

Main activities

Tips / Best practices

Key points

137

Valid from


Today’s date

138

Valid to


If contract - validity to from contract

If PIR or STO - 31.12.2999

139

Purchasing Organization


Always CP01

140

Purchasing Plant

Ony for STO

Add Shipping from plant (source plant)

141

Contract

For external Purchase

Add contract created

142

Item

For external Purchase

Add line from contract related to the item

143

MRP Relevant 

If there are several sources, we should verify with Buyer, which source needs to be marked as MRP relevant. 

Always 1

144

Save it




2.4. Quota Arrangement

Purchasing (MM-PUR)

A mechanism enabling the system to compute which source of supply to assign to a requirement for a material. The quota arrangement facilitates the determination of the applicable sources of supply for a purchase requisition at a certain time. Setting quotas permits the automatic apportionment of a total material requirement over a period to different sources. A quota arrangement consists of quota arrangement records identifying the source (such as a vendor or an internal plant), the validity period, and the quota.

Master Data (SCM-APO-MD)

Percentage specifying which proportion of the required quantity of product is to be procured from a source of supply (incoming quota arrangement) or supplied to a location (outgoing quota arrangement). Quota arrangements can be defined as either version-dependent or model-dependent, and as either product-dependent or product-independent. Quota arrangements are defined for a certain area of validity. Incoming quota arrangements can be defined for the following source of supply types:

  • Locations (transportation lanes)

  • External procurement relationships

  • In-house production (production process models, iPPE access objects, or production data structures)

Outgoing quota arrangements can only be created for locations.

Supplier Relationship Management (SRM)

An algorithm with which the system determines the sources of supply for a purchase requisition. The quota arrangement defines percentages according to which the system assigns purchase contracts as a source of supply. By setting quotas, you can automatically distribute the purchase requisitions for the duration of a validity time period to different sources.

2.4.1. Quota Arrangement creation


#

Main activities

Tips / Best practices

Key points

141

Enter transaction MEQ1

T-code can be entered directly in Command field. T-code can be saved in Favorites.


142

Material


As informed

143

Plant


As informed

144

Press enter





#

Main activities

Tips / Best practices

Key points

145

Valid to


As informed

146

Click on item





#

Main activities

Tips / Best practices

Key points

147

Procurement Type

Normally value is ”F

As informed

148

Special Procurement Type

Normally value is ”U

As informed

149

Vendor 

Vendor code for shipping from plant (Source plant)

As informed

150

Procurement Plant 

Shipping from plant (Source plant)

As informed

151

Quota is fine as default

Normally value is ”100

As informed

152

Save it




2.4.2. Quota Arrangement deletion



Main activities

Tips / Best practices

Key points

Enter transaction MEQ1

T-code can be entered directly in Command field. T-code can be saved in Favorites.


Material


As informed

Plant


As informed

Press enter



Main activities

Tips / Best practices

Key points

Select the line


Click on

Main activities

Tips / Best practices

Key points

Remove the Quota


The field should be blank

Save the change





Appendix 1 - Approved Requesters


Plant

Buyer

Planner

Heanor (2010)

Manchester (2020)

Ammar Alsalih

Graham Hill (2010)

Ben Woodcock (2010)

Amanda Brown (2020)

James Taylor (2010/2020)

Keighley (2050)

Marie Woodhouse

Melanie Greenfield

Tulsa (2015)

Clint Baker

Patti Cline

Mondovi (2045)

Logind (2085)

Davide Mina

Gilberto Barale, Elena Vinai

Santa Fe Springs (2040)

Tracy Ng

Jennifer Dominguez

Tracy Ng

Jennifer Dominguez

Toulouse (2035)

Eurocenter (2100)

Claire Thomas

Laetitia Villemeney

Adeline Gourc

Alison Gal


Appendix 2 - Contract Release


Releases per plant

D1

D2

D3

Heanor (2010)

Manchester (2020)

Ammar Alsalih

Ammar Alsalih

Jean-Pierre Demeunynck

 

Tulsa (2015)

Clint Baker

Keighley (2050)

Marie Woodhouse

Tracy Ng

Mondovi (2085)

Logind (2085)

Gilberto Barale

Santa Fe Springs (2040)

Tracy Ng

Jennifer Dominguez

Toulouse (2035)

Eurocenter (2100)

Claire Thomas


Appendix 3 - Most common errors and stoppers

Appendix 3.1 - Block-Allow BOM/Costing

In case of the above error, advise requestor that Data Steward should be contacted to remove the block. 

Appendix 3.2 - No QM info record exists for material 

If Quality Info Record (QIR) is missing, requestor should contact quality department to set up the QIR.

Appendix 3.3 - Define QM Procurement Key

Quality view and material master are not fully maintained. Advise to contact Quality department to set up QM procurement key for material.

Appendix 3.4 - Not possible to assign a source of supply

a.       Check ME03 for a source availability (Is that who you want to buy from?) and contact SBS Procurement for any changes.

b.      Check your delivery period (is the source extended to that year/month/day?)

c.       If desired supplier is not in source list, review Special Procurement Key (SPK) for accuracy.

                                                               i.      SPK is found in MM03 --> MRP2 tab

                                                             ii.      STO SPK = Letter + Number

                                                            iii.      External Proc SPK = blank

                                                           iv.      Consignment = 30

                                                             v.      Subcontracting = 10

d.      Make sure your Item category on the PR reflect your procurement type (STO; Subcon; Consignment; Standard)

                                                               i.      If it is automatically assigned and is incorrect, investigate SPK and contact Data Steward if it is incorrect.

e.      If the Source list is maintained correctly, check if the contract is released. ME33K → Green flag

Extremely rare - regenerate the PR by re-running MRP after the source list was created

Appendix 3.5 - STO PR has blank price field 

Price is taken from Material Master, Costing 2 tab. If the Standard price is 0 in material master, contact data steward

Appendix 3.6 - Following mandatory roles missing in partner maintenance: PI

When the system presents the message bellow, please note that the missing role should be added to this contract.

In order to check all the partners for the vendor:

  • Please access transaction XK03
  • Populate the vendor number
  • Populate the purchase organization: always CP01
  • Mark the checkbox for "partner functions"

Check each roll assigned to the main vendor and go to ME31K transaction for the contract creation


Once all the information is populated, assigned the missing role for the contract by following the steps bellow:

  • Select the line
  • Click on the  button



  • Double click on the first line

  • Assign the missing role by adding the function and the vendor number 


  • Press enter an return to contract in order to finish the set up

Appendix 4 - Additional Definitions

CONSIGNMENT 

A form of business in which a vendor (external supplier) maintains a stock of materials at a customer (purchaser) site. The vendor retains ownership of the materials until they are withdrawn from the consignment stores. Payment for consignment stock is required only when the material is withdrawn for use. For this reason, the vendor is informed of withdrawals of consignment stock on a regular basis.

SUBCONTRACTING

An instruction to a supplier (subcontractor) to manufacture an ordered part, material or assembly using specified "materials to be provided" (free-issue materials).  A subcontract order contains a maximum of one order item for the ordered material, service, or work, and one or more "material to be provided" items for materials that the orderer makes available to the subcontractor, without charge, for processing.

Appendix 5 - Q&A


In this link we have a Q&A where we can find the most common questions and answers regarding this activity.