Sprint Report



 

Start

 

End 

 

Sprint  Goal(s)

Define change management plan 

Start change management activities

Engagement of APAC PA Have defined target date + action plan for EDI and Promaster for EMEA

Initial pilot testing engaged with cards issued

New entitites added to the existing Concur feed file

Sprint reportSprint 14
Completed Story Points 5
 SummaryThe sprint goals above will be completed during this sprint (sprint 15)
CommentsThe communication on planning for Wave 2 was delayed which kept the Squad from achieving their sprint goals. 


Burndown Chart

Velocity Chart

Issues Status Report