You are attempting to cost material x in plant p. The bill of material for this material may have either:

  • a validity period that does not correspond to the cost estimate
  • a lot size range that does not contain the costing lot size (with multiple BOMs)
  • A bill of material status, that does not allow the bill of material to be used in a cost estimate

Example 

You are attempting to cost material 70532 in plant 0214. The bill of material for this material may have either

  • a validity period that does not correspond to the cost estimate
  • a lot size range that does not contain the costing lot size (with multiple BOMs)
  • A bill of material status, that does not allow the bill of material to be used in a cost estimate


What to do ?

Enter a status Z1 in the view costing of the master data of the material code with transaction MM02 until the BOM is created or updated


STEP 1

  • Use transaction MM02
  • Enter the material code and 

 

 

 

 


STEP 2

  • Select the view "Costing 1" and 

 

 


STEP 3

  • Enter the plant code and 

 

 

 


STEP 4

  • Enter the status Z1 in the field Plant-sp.matl status and save 
  • A message confirms the change 

 

 

 

What happens if the issue is not solved and the costing released ?

  • The field BOM is blank
  • There is no raw material cost in the costing of the finished product, the costing is not accurate