You are attempting to cost material x in plant p. The bill of material for this material may have either:
- a validity period that does not correspond to the cost estimate
- a lot size range that does not contain the costing lot size (with multiple BOMs)
- A bill of material status, that does not allow the bill of material to be used in a cost estimate
Example
You are attempting to cost material 70532 in plant 0214. The bill of material for this material may have either
- a validity period that does not correspond to the cost estimate
- a lot size range that does not contain the costing lot size (with multiple BOMs)
- A bill of material status, that does not allow the bill of material to be used in a cost estimate
What to do ?
Enter a status Z1 in the view costing of the master data of the material code with transaction MM02 until the BOM is created or updated
What happens if the issue is not solved and the costing released ?
- The field BOM is blank
- There is no raw material cost in the costing of the finished product, the costing is not accurate